PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
McConaghy Properties Pty Ltd v Townsville City Council & Anor [2017] QPEC 11
PARTIES:
McCONAGHY PROPERTIES PTY LTD
ACN 108 353 331
(Appellant)
v
TOWNSVILLE CITY COUNCIL
(Respondent)
and
PARKSIDE DEVELOPMENT PTY LTD
ACN 009 802 233
(Co-Respondent)
FILE NO/S:
315 of 2016
DIVISION:
Planning and Environment
PROCEEDING:
Appeal
ORIGINATING COURT:
Brisbane
DELIVERED ON:
10 March 2017
DELIVERED AT:
Brisbane
HEARING DATE:
15, 19, 20, 21, 22, 23 and 26 September 2016
JUDGE:
Morzone QC DCJ
ORDER:
1. Appeal allowed.
2. The development application is refused.
3. I will hear the parties as to any consequential orders.
CATCHWORDS:
PLANNING AND ENVIRONMENT – Appeal against approval of major commercial development including a supermarket, specialty shops - land currently zoned open space, sport and recreation purposes – land owned and occupied by rugby union association – relocation of existing use to larger facilities subject of future application, assess and approval.
OUT OF CENTRE DEVELOPMENT – provision of the necessities of life (food and groceries) - whether unacceptable adverse impacts on the centres network – whether unacceptable adverse impacts on the open space network - whether unacceptable adverse impacts on the traffic network.
CONFLICT – Conflict with the scheme – at serious end of spectrum - whether the proposal will meet an existing town planning and community need, and economic need, without unacceptable amenity or economic impacts; whether the proposal will create a definable node of uses; whether the proposal will result in improvements to the road network; whether proposal will provide additional employment opportunities during construction and operation; whether the zoning of the subject land has been “overtaken by events” - whether sufficient grounds to approve the application despite the conflicts.
Legislation
Sustainable Planning Act 2009 (Qld (“SPA”)
Cases
Australian Capital Holdings v Mackay Regional Council & Anor [2008] QCA 157
Brown v Moreton Shire Council [1972 26 LGERA 310
Bunnings Building Supplies Pty Ltd v. Redland Shire Council and Ors [2000] QPELR 193
Calligaris v Bundaberg CC 2002 QPELR 210
Chelmer Bowls Pty Ltd v BCC [2006] QPELR 611
Cut Price Stores Retailers & Ors v. Caboolture Shire Council [1984] QPLR 126
Elan Capital Corporation Pty Ltd & Anor v BCC & Ors [1990] QPLR 209
Elfband & Anor v Maroochy Shire Council & Ors [1995] QPLR 290
Fitzgibbon Hotel Pty Ltd v Logan CC [1997] QPLER 208
Gaven Developments Pty Ltd v Scenic Rim Regional Council [2010] QPELR 750
Gillion Pty Ltd v Scenic Rim Regional Council & Ors [2014] QCA 021
Grosser v Gold Coast City Council [2001] 117 LGRA 153
Handley v BCC & Anor [2005] QPELR 80
Holts Hill Quarries Pty Ltd v Gold Coast CC & Ors [2001] 1 QdR 372,
Hydrox Nominees Pty Ltd v Sunshine Coast Regional Council [2014] QPEC 18
Hymix Australia Pty Ltd v BCC & Ors [2014] QPELR 645
Intrafield Pty Ltd v. Redland Shire Council [2001] 116 LGERA 350
JPF Australia Pty Ltd v Livingstone Shire Council [2006] QPELR 359
Kangaroo Point Residents…
Keep reading for free
Create a free CaseChat account to read McConaghy Properties Pty Ltd v Townsville City Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QPEC 11
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to address included whether the proposed development would result in unacceptable adverse impacts on the existing centres network, open space network, and traffic network. The court also had to determine whether the proposal met an existing town planning and community need, and economic need, without causing unacceptable amenity or economic impacts. Furthermore, the court had to consider whether the proposal would create a definable node of uses, improve the road network, and provide additional employment opportunities during construction and operation. The court also considered whether the zoning of the subject land had been "overtaken by events" and whether there were sufficient grounds to approve the application despite the conflicts.
The court found that the proposal was at the serious end of the spectrum in terms of conflict with the scheme. The court held that the proposal did not meet an existing town planning and community need, and economic need, without unacceptable amenity or economic impacts. The court also found that the proposal would not create a definable node of uses, would not result in improvements to the road network, and would not provide additional employment opportunities during construction and operation. The court concluded that the zoning of the subject land had not been "overtaken by events" and that there were not sufficient grounds to approve the application despite the conflicts.
The court allowed the appeal and refused the development application. The court will hear the parties as to any consequential orders.
Orders
Orders of the court
1. Appeal allowed.
2. The development application is refused.
3. I will hear the parties as to any consequential orders.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi