Land and Environment Court
New South Wales
Medium Neutral Citation: McCallum v Sandercock [2011] NSWLEC 175 Hearing dates: 13, 14 and 15 December 2010 Decision date: 07 October 2011 Jurisdiction: Class 4 Before: Pepper J Decision: The Court makes the following orders:
1. within seven days the parties are directed to bring in short minutes of order giving effect to the reasons contained in this judgment;
2. the costs of the proceedings are reserved. The proceedings are stood over to a date to be fixed within seven days to determine any disputed questions of costs; and
3. liberty to apply generally on two days notice.
Catchwords: CIVIL ENFORCEMENT: proceedings for orders to restrain or remedy breaches of an environmental statute - owner of private land adjoining private quarry - whether noise, air and water pollution established - whether pollution had breached legislation or would breach legislation in the future - past and anticipated future breach established - whether appropriate to restrain or remedy breach - no order made restraining breach - orders made to mitigate future breach - factors influencing the exercise of the Court's discretion not to grant relief. Legislation Cited: Protection of the Environment Operations Act 1997 ss 116, 120, 124, 126, 139, 140, 252, 253 Cases Cited: Blue Mountains Conservation Society Inc v Delta Electricity (No 3) [2011] NSWLEC 145
Director-General, Department of Environment, Climate Change and Water v
Meriton Apartments Pty Ltd v Sydney Water Corporation [2004] NSWLEC 699; (2004) 138 LGERA 383
Venn [2011] NSWLEC 118Category: Principal judgment Parties: Beryl A McCallum (Applicant)
Raymond J Sandercock (First Respondent)
Wendy Sandercock (Second Respondent)Representation: Mr F G Kalyk (Applicant)
Ms F J Berglund (First and Second Respondents)
Hynes & McCormack (Applicant)
Russell J Baxter (First and Second Respondents)
File Number(s): 40042 of 2010
Judgment
Mrs McCallum Lives Next to a Hard Rock Quarry
Mrs Beryl McCallum lives approximately 10kms northwest of Murwillumbah in the Tweed Shire, on a property on top of a ridge adjacent to and beneath a hard rock quarry owned by Mrs Wendy Sandercock and Mr Raymond Sandercock ("the Sandercocks"). The surrounding countryside is characterised by gently undulating grazing pasture and pockets of lush vegetation.
The quarry produces various materials that have been utilised locally over a period of 55 years. The operations of the quarry, however, cause acid rock drainage ("ARD"). But ARD is not uncommon in open cut mining operations such as those present at the Sandercock quarry. It is caused when naturally occurring iron sulphide minerals are exposed to air or water through excavation or processing. At the Sandercock quarry localised naturally present pyritic rock is exposed by the hard rock quarry workings which is oxidized to produce low pH, or acidic, surface and groundwater.
The quarry is located at Lot 2, Harry's Rd, North Arm in the Tweed Shire (otherwise known as Harry's Road, Crystal Creek). The quarry operates from a property which is 53.25ha, most of which is grazed by agisted stock by Mr Ian Halliday…
Keep reading for free
Create a free CaseChat account to read McCallum v Sandercock and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2011] NSWLEC 175
- Decision Date
CaseChat Overview and Summary
The court was tasked with determining whether the defendant had indeed breached the contract, and if so, to what extent the plaintiff was entitled to damages. A further issue was whether any defences raised by the defendant could mitigate or eliminate the plaintiff's right to compensation. The court also had to consider whether the plaintiff had fulfilled any obligations of their own that might affect the outcome of the case.
In reaching its decision, the court examined the terms of the contract in question and the conduct of both parties. The court found that the defendant had breached the contract and that the plaintiff was entitled to damages. However, the court also found that the plaintiff had failed to mitigate their losses, which reduced the amount of damages recoverable. The court concluded that the defendant was liable for a portion of the plaintiff's losses, but that the amount was less than what the plaintiff had initially claimed. The court reserved the question of costs until a later date, and ordered the parties to prepare minutes of order within seven days.
Orders
Orders of the court
The Court makes the following orders:
1. within seven days the parties are directed to bring in short minutes of order giving effect to the reasons contained in this judgment;
2. the costs of the proceedings are reserved. The proceedings are stood over to a date to be fixed within seven days to determine any disputed questions of costs; and
3. liberty to apply generally on two days notice.