Mazurek v Fisniku

Case [2023] NSWCATCD 81


Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Mazurek v Fisniku [2023] NSWCATCD 81
Hearing dates: 22 June 2023
Date of orders: 18 July 2023
Decision date: 18 July 2023
Jurisdiction:Consumer and Commercial Division
Before: G Ellis SC, Senior Member
Decision:

(1) By consent, the respondents are to carry out a satisfactory rectification of items referred to in Appendix A (the works).

(2) By consent, Central Coast Certifiers is to be the sole determiner of whether the works have been done in compliance with Order 1.

(3) By consent, the respondents are to bear the costs of Central Coast Certifiers.

(4) By consent, the respondents are to complete the works by 21 July 2023 (the completion date).

(5) By consent, with prior written notice to the applicants, the completion date may be extended to no later than 4 August 2023 where unforeseen events prevent completion of the works by the completion date.

(6) By consent, the applicants have leave to renew the proceedings, in accordance with clause 8(2) of Schedule 4 to the Civil and Administrative Tribunal Act 2013.

(7) The application is otherwise dismissed.

(8) Any application for costs is to be made by filing and serving, by 31 July 2023, submissions (not exceeding five pages), together with any relevant evidence.

(9) Any submissions in response (not exceeding five pages), together with any relevant evidence, are to be filed and served by 14 August 2023.

(10) Any submissions in reply from the party applying for costs (not exceeding two pages), together with any relevant evidence, are to be filed and served on or before 21 August 2023.

(11) Any such submissions should include an indication of whether the party agrees that costs should be determined on the papers, without a further hearing.

Catchwords:

BUILDING AND CONSTRUCTION - Whether costs plus contract replaced by fixed price contract – validity of termination – finding of mutual termination

ESTOPPEL - Promissory estoppel - estoppel by convention

BUILDING AND CONSTRUCTION - Cost of completion - alleged overcharging - storage costs

Legislation Cited:

Civil and Administrative Tribunal Act 2013 (NSW) – ss 38, 60

Civil and Administrative Tribunal Regulation (NSW)

Civil and Administrative Tribunal Rules 2014 (NSW) - rr 38, 39

Civil Procedure Act 2005 (NSW) - s 100

Home Building Act 1989 (NSW) - s 18B

Cases Cited:

Banco de Portugal v Waterlow and Sons [1932] AC 452 at 506

Bonita v Shen [2016] NSWCATAP 159

Browne v Dunn (1893) 6 R. 67, HL

Con-Stan Industries of Australia Pty Ltd v Norwich Winterthur Insurance (Australia) Limited [1986] HCA 14; 160 CLR 226

Dabbs v Seaman [1925] HCA26; 36 CLR 538

Fox v Percy [2003] HCA 22

Grundt v Great Boulder Pty Gold Mines Ltd [1937] HCA 58; 59 CLR 641

Hadley v Baxendale (1854) 9 Exch 341

Hasell v Bagot, Shakes & Lewis Ltd [1911] HCA 62

Karacominakis v Big Country Developments Pty Ltd [2000] NSWCA 313

Latoudis v Casey [1990] HCA 59

L’Estrange v F Graucob Ltd

Continue reading Mazurek v Fisniku

Sign in free to access the full text

Details
AGLC
Mazurek v Fisniku [2023] NSWCATCD 81
Case
[2023] NSWCATCD 81
Decision Date

CaseChat Overview and Summary

The dispute between the applicants, Mazurek, and the respondents, Fisniku, was heard in the Civil and Administrative Tribunal of New South Wales. The primary issue was whether the original costs plus contract for the construction of a home was replaced by a fixed price contract. Additionally, the court had to determine the validity of the termination of the contracts and whether there was a mutual termination. The applicants also argued that the respondents had overcharged for the cost of completion and storage.

The court considered the legal principles of promissory estoppel and estoppel by convention in relation to the contract variation and termination. It also examined the evidence regarding the cost of completion and storage. The court concluded that the original costs plus contract was indeed replaced by a fixed price contract, and that the termination of the contracts was mutual. The court found that there was no overcharging by the respondents. The applicants' claims for costs were dismissed, and the respondents were ordered to complete the works by a specified date, with the possibility of an extension in case of unforeseen events.

The court's orders included the rectification of specified works, the appointment of a certifier to ensure compliance, and the allocation of costs. The applicants were granted leave to renew the proceedings, and a process was established for applications for costs, with specific deadlines for submissions and evidence. The court also provided for the possibility of determining costs on the papers, without a further hearing, if agreed by the parties.

Orders

Orders of the court

(1) By consent, the respondents are to carry out a satisfactory rectification of items referred to in Appendix A (the works).

(2) By consent, Central Coast Certifiers is to be the sole determiner of whether the works have been done in compliance with Order 1.

(3) By consent, the respondents are to bear the costs of Central Coast Certifiers.

(4) By consent, the respondents are to complete the works by 21 July 2023 (the completion date).

(5) By consent, with prior written notice to the applicants, the completion date may be extended to no later than 4 August 2023 where unforeseen events prevent completion of the works by the completion date.

(6) By consent, the applicants have leave to renew the proceedings, in accordance with clause 8(2) of Schedule 4 to the Civil and Administrative Tribunal Act 2013.

(7) The application is otherwise dismissed.

(8) Any application for costs is to be made by filing and serving, by 31 July 2023, submissions (not exceeding five pages), together with any relevant evidence.

(9) Any submissions in response (not exceeding five pages), together with any relevant evidence, are to be filed and served by 14 August 2023.

(10) Any submissions in reply from the party applying for costs (not exceeding two pages), together with any relevant evidence, are to be filed and served on or before 21 August 2023.

(11) Any such submissions should include an indication of whether the party agrees that costs should be determined on the papers, without a further hearing.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.