Mayfield Development Corporation Pty Ltd v NSW Port Operations Hold Co Pty Ltd (No 3)

Link copied
Case Copied 17 min read

FEDERAL COURT OF AUSTRALIA

Mayfield Development Corporation Pty Ltd v NSW Port Operations Hold Co Pty Ltd (No 3) [2023] FCA 713  

File number: NSD 862 of 2019
Judgment of: LEE J
Date of judgment: 22 June 2023
Date of publication of reasons: 28 June 2023
Catchwords:

PRACTICE AND PROCEDURE –  where proceeding stayed pending determination of proceeding commenced by Australian Competition and Consumer Commission (ACCC) – where ACCC proceeding and appeal now finalised – matter to be progressed with case management imperatives in Pt VB of the Federal Court of Australia Act 1976 (Cth) in mind

PRACTICE AND PROCEDURE –  where applicant intends to contend Full Court plainly wrong – whether proceeding properly constituted – whether separate determination of issues appropriate – whether demurrer appropriate

Legislation:

Competition and Consumer Act 2010 (Cth) ss 2B(1)(a), 45, 45(2)(a)(ii)

Evidence Act 1995 (Cth) s 191

Federal Court of Australia Act 1976 (Cth) Pt VB, s 37P(2)

Federal Court Rules 2011 (Cth) r 30.01

Cases cited:

Australian Competition and Consumer Commission v Baxter Healthcare Pty Ltd [2007] HCA 38; (2007) 232 CLR 1

Australian Competition and Consumer Commission v NSW Ports Operations Hold Co Pty Ltd [2021] FCA 720

Australian Competition and Consumer Commission v NSW Ports Operations Hold Co Pty Ltd [2023] FCAFC 16; (2023) 407 ALR 627

Australian Competition and Consumer Competition v NSW Ports Operations Hold Co Pty Ltd (No 2) [2021] FCA 1040

Bass v Permanent Trustee Co Ltd (1999) 198 CLR 334

Mayfield Development Corporation Pty Ltd v NSW Ports Operations Hold Co Pty Ltd [2020] FCA 260

Wynyard Investments Pty Ltd v Commissioner for Railways (NSW) (1955) 93 CLR 376

Central Practice Note: National Court Framework and Case Management (CPN-1)
Division: General Division
Registry: New South Wales
National Practice Area: Commercial and Corporations
Sub-area: Economic Regulator, Competition and Access
Number of paragraphs: 42
Date of hearing: 22 June 2023
Counsel for the Applicant: Mr P McQueen with Ms N Wootton
Solicitor for the Applicant: Banton Group
Counsel for the Respondents: Mr B Lim
Solicitor for the Respondents: Gilbert + Tobin

ORDERS

NSD 862 of 2019
BETWEEN:

MAYFIELD DEVELOPMENT CORPORATION PTY LTD (ACN 154 495 048)

Applicant

AND:

NSW PORTS OPERATIONS HOLD CO PTY LTD (ACN 163 262 351)

First Respondent

PORT BOTANY OPERATIONS PTY LTD (ACN 161 204 342)

Second Respondent

PORT KEMBLA OPERATIONS PTY LTD (ACN 161 246 582)

Third Respondent

ORDER MADE BY:

LEE J

DATE OF ORDER:

22 JUNE 2023

THE COURT ORDERS THAT:

1.The stay of the proceeding ordered on 19 August 2019 be lifted.

2.On or by 29 June 2023, Mayfield Development Corporation Pty Ltd (MDC) provide security in respect of NSW Port Operations Hold Co Pty Ltd (NSW Ports) costs of the proceeding in the amount of $250,000, by placing that sum into a controlled-money account operated by the solicitors for MDC.

3.Order 2 is without prejudice to NSW Ports seeking to apply for subsequent security for further stages of the proceeding, and…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mayfield Development Corporation Pty Ltd v NSW Port Operatio... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2023] FCA 713
Decision Date

CaseChat Overview and Summary

In the case of Mayfield Development Corporation Pty Ltd v NSW Port Operations Hold Co Pty Ltd, the Federal Court was tasked with managing a complex litigation involving a stay of proceedings and derivative crown immunity defences. The case arose from a dispute between Mayfield Development Corporation Pty Ltd (MDC) and NSW Port Operations Hold Co Pty Ltd (NSW Ports), concerning the validity of a lease and associated derivative crown immunity issues. The court was called upon to determine the appropriate procedural steps to manage the case effectively, considering the finalisation of related proceedings by the Australian Competition and Consumer Commission.

The primary legal issues before the court were whether the proceeding was properly constituted, if a separate determination of issues was appropriate, and whether a demurrer was an appropriate procedural step. The court also needed to consider the implications of the derivative crown immunity defence, particularly in light of MDC’s concession that such a defence would be a complete answer if the Full Court’s ruling remained undisturbed. Furthermore, the court had to balance the case management imperatives set out in the Federal Court of Australia Act 1976 (Cth) with the need to ensure a fair and efficient resolution of the dispute.

The court addressed these issues by proposing a structured approach to managing the case. It ordered the lifting of the stay of proceedings and required MDC to provide security for costs. The court also outlined a series of steps for the parties to follow, including the filing of further amended originating applications and statements of claim, the lodging of a defence by NSW Ports, and the identification of facts necessary for the separate determination of derivative crown immunity or preclusion defences. The court emphasised the importance of clarity and agreement between the parties to ensure the justiciable controversy would be resolved. Ultimately, the court scheduled a further case management hearing to determine the next steps in the proceeding, ensuring the case was progressed in line with the Federal Court Rules 2011.

The court made several orders to facilitate the proposed regime, including the lifting of the stay, setting deadlines for the filing of amended documents, and scheduling a further case management hearing. The orders also provided for the provision of security by MDC and allowed for potential subsequent applications for further security by NSW Ports. The court emphasised the need for the State of New South Wales to clarify its position in the interim, ensuring all relevant parties were aligned in the resolution of the case.

Orders

Orders of the court

1. The stay of the proceeding ordered on 19 August 2019 be lifted.

2. On or by 29 June 2023, Mayfield Development Corporation Pty Ltd (MDC) provide security in respect of NSW Port Operations Hold Co Pty Ltd (NSW Ports) costs of the proceeding in the amount of $250,000, by placing that sum into a controlled-money account operated by the solicitors for MDC.

3. Order 2 is without prejudice to NSW Ports seeking to apply for subsequent security for further stages of the proceeding, and in the event that MDC fails to provide security in accordance with Order 2, the proceeding be stayed without necessity for further order.

4. On or by 17 July 2023, MDC file a further amended originating application and a further amended statement of claim, limited to any change as to the parties to the proceeding.

5. Leave be granted to MDC to file the documents pursuant to Order 4, subject to NSW Ports making any further complaint about the form of the further amended statement of claim, including any argument as to the amendment effected by paragraph 34A of the amended statement of claim, and whether that amendment should be allowed and the date upon which that amendment is to take effect.

6. On or by 14 August 2023, NSW Ports file any defence to the further amended statement of claim.

7. NSW Ports serve on the other parties and provide to the Associate to Justice Lee a copy of a statement of facts (in a form which could amount to an admission) being the facts it contends are necessary to be found in order for the Court to determine separately any issue of derivative Crown immunity or in relation to any preclusion defence.

8. On or by 8 September 2023, MDC notify NSW Ports and the Associate to Justice Lee whether any of the facts specified in the document filed pursuant to Order 7 are disputed, and if so, the ambit of such dispute.

9. On or by 13 September 2023, the parties provide to each other and the Associate to Justice Lee a copy of any orders they propose to seek, together with a short submission identifying reasons why they contend for such orders, including any submissions they wish to make in relation to the separate determination of the derivative Crown immunity defence and/or any defence of preclusion pleaded.

10. The matter be listed for a further case management hearing to identify orders for the further conduct of the proceeding, including any separate determination, at 2:15pm on 15 September 2023.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

NSW Ports is, at present, not averse to such a course, subject to there being utmost clarity that, in the event MDC is unsuccessful in its attack on the Full Court’s decision, the justiciable controversy between MDC and NSW Ports would be entirely resolved. This hesitation is understandable. My present view is, however, that given MDC concedes derivative crown immunity would be a complete answer should the Full Court’s ruling remain undisturbed, one should be able to fashion a means by which this issue is resolved in line with the overarching purpose.E CONCLUSION AND ORDERS I propose to put in place the following regime. MDC should file a further amended originating application and a further amended statement of claim, limited to any change as to the parties to the proceeding. NSW Ports should then file a defence. Immediately following the close of pleadings, NSW Ports should identify any facts that would need to be either agreed or determined for the purposes of the Court separately determining any derivative crown immunity or preclusion defence. Next, MDC should indicate whether any of those facts are in dispute (or perhaps agree facts that may be tendered at any separate hearing pursuant to s 191 of the Evidence Act 1995 (Cth)). Finally, I will bring the matter back for another case management hearing to determine where to go from there. At that point in time, I will be in a position to determine whether I should make orders pursuant to s 37P(2) of the FCA Act and FCR 30.01 for a separate trial of any issue. It will, of course, be necessary for the State of New South Wales to consider its position in the interim. It may be that the State of New South Wales agrees it will be bound by any determination made in this proceeding without being joined, or files a submitting appearance (at least before me). Needless to say, any separate hearing before me should be an entirely straightforward affair if there are no disputed facts, given the authority binding upon me. I will make orders giving effect to these reasons.

Ratio Decidendi

Legal Principle Established