Set aside by Appeal:
Set aside by Appeal in part 6/10/2004
Sotiropoulos -v- Mattana Coiffure Pty Limited (No 2) (RLD) [2004] NSWADTAP 43
CITATION: Mattana Coiffure Pty Limited v Sotiropoulos (No2) [2004] NSWADT 80 DIVISION: Retail Leases Division PARTIES: APPLICANT
Mattana Coiffure Pty Limited
RESPONDENT
Vlasios Vasilios SOTIROPOULOSFILE NUMBER: 035024 HEARING DATES: 6 April 2004 SUBMISSIONS CLOSED: 04/06/2004 DATE OF DECISION:
04/23/2004BEFORE: Fox R - Judicial Member APPLICATION: Claim for payment of money - Claim for rectification of the lease - Costs MATTER FOR DECISION: Orders; costs LEGISLATION CITED: Retail Leases Act 1994 CASES CITED: REPRESENTATION: APPLICANT
M Drake, barrister
RESPONDENT
G Burton, barristerORDERS: Building works orders; 1.The Respondent use all reasonable endeavours to obtain approval for Development Application 8.2003.408.1, in its current form or as amended only so far as is necessary to satisfy the requirements of Mosman Council (“Development Application”), from Mosman Council at the earliest possible time.; 2.The Respondent, within 8 weeks of obtaining approval for the Development Application construct and rectify treatment room 2 (excluding joinery) in accordance with the plans and schedule of fittings provided by Michael Sandberg, SMS Architects and the four paint finishes specified in the applicant’s schedule of finishes attached to these orders and marked “A” (“building works”).; 3.The Respondent ensure that the premises are secure and locked and provided with adequate toilet facilities throughout the building works. ; 4.The Respondent, within nine weeks of obtaining approval for the Development Application provide the Applicant with certifications:; i) from a practising structural engineer with corporate membership of the Institute of Engineers Australia that the excavation works have either left the existing wall at the back of treatment room 2 in structurally sound condition, or that underpinning or similar works have been effected to render it structurally sound; and; ii) from an accredited certifier, qualified to make these assessments and accredited under section 109T of the Environmental Planning and Assessment Act 1979, that the building works have been completed in accordance with order 2 above, the Building Code of Australia and any development consents entitling those works to be carried out. ; Compensation orders; 5.The Respondent pay the Applicant $37,900 in compensation for the period from 5 September 2002 to 23 September 2003. ; 6.The Respondent pay the Applicant compensation in the sum of $1,803 a day for: ; i) three days lost trading on 24-26 September 2003 by closure of the salon during the installation of the temporary facilities, being $5409; and; ii) each additional day of trading lost from 6 April 2004 until the completion of the building works by closure of the salon, payable at the end of each week in which a day or more of trading is lost by cheque delivered to the leased premises during the trading hours of the applicant’s business or as otherwise agreed between the parties.; 7.The Respondent pay the Applicant compensation in the sum of: $4,284 for the loss of the use of Treatment Room 2 from 24 September 2003…
Keep reading for free
Create a free CaseChat account to read Mattana Coiffure Pty Limited v Sotiropoulos (No2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NSWADT 80
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court included whether Sotiropoulos had breached the lease by failing to obtain the necessary development approval and by not ensuring the premises were habitable. It was also necessary to determine if Mattana Coiffure was entitled to compensation for the period during which the salon was closed and for the loss of use of Treatment Room 2. The court had to consider the terms of the lease, the obligations of the landlord under the Environmental Planning and Assessment Act 1979, and whether Sotiropoulos's actions constituted a breach of the lease terms.
Justice Hulme found that Sotiropoulos had indeed breached the lease by failing to obtain the required development approval and by not maintaining the premises. The court held that the landlord's actions had resulted in significant losses for Mattana Coiffure, including lost trading days and the loss of use of Treatment Room 2. The court ordered Sotiropoulos to use all reasonable endeavours to obtain the necessary development approval and to complete the building works within specified timeframes. Additionally, Sotiropoulos was required to compensate Mattana Coiffure for the losses incurred. The court awarded Mattana Coiffure compensation for lost trading days, the loss of use of Treatment Room 2, and other related expenses. The court also ordered Sotiropoulos to pay interest on part of the compensation and specified the costs to be borne by each party.
In conclusion, the court's orders mandated that Sotiropoulos secure the necessary development approval and complete the building works to make the premises habitable. Compensation was awarded to Mattana Coiffure for the losses suffered due to the landlord's breaches. The orders also included provisions for ongoing compensation for lost trading days and the loss of use of Treatment Room 2, as well as interest on part of the compensation. The court directed that certain costs be borne by Sotiropoulos, reflecting the breaches found in the case.
Orders
Orders of the court
Building works orders; 1.The Respondent use all reasonable endeavours to obtain approval for Development Application 8.2003.408.1, in its current form or as amended only so far as is necessary to satisfy the requirements of Mosman Council (“Development Application”), from Mosman Council at the earliest possible time.; 2.The Respondent, within 8 weeks of obtaining approval for the Development Application construct and rectify treatment room 2 (excluding joinery) in accordance with the plans and schedule of fittings provided by Michael Sandberg, SMS Architects and the four paint finishes specified in the applicant’s schedule of finishes attached to these orders and marked “A” (“building works”).; 3.The Respondent ensure that the premises are secure and locked and provided with adequate toilet facilities throughout the building works. ; 4.The Respondent, within nine weeks of obtaining approval for the Development Application provide the Applicant with certifications:; i) from a practising structural engineer with corporate membership of the Institute of Engineers Australia that the excavation works have either left the existing wall at the back of treatment room 2 in structurally sound condition, or that underpinning or similar works have been effected to render it structurally sound; and; ii) from an accredited certifier, qualified to make these assessments and accredited under section 109T of the Environmental Planning and Assessment Act 1979, that the building works have been completed in accordance with order 2 above, the Building Code of Australia and any development consents entitling those works to be carried out. ; Compensation orders; 5.The Respondent pay the Applicant $37,900 in compensation for the period from 5 September 2002 to 23 September 2003. ; 6.The Respondent pay the Applicant compensation in the sum of $1,803 a day for: ; i) three days lost trading on 24-26 September 2003 by closure of the salon during the installation of the temporary facilities, being $5409; and; ii) each additional day of trading lost from 6 April 2004 until the completion of the building works by closure of the salon, payable at the end of each week in which a day or more of trading is lost by cheque delivered to the leased premises during the trading hours of the applicant’s business or as otherwise agreed between the parties.; 7.The Respondent pay the Applicant compensation in the sum of: $4,284 for the loss of the use of Treatment Room 2 from 24 September 2003 until 6 April 2004 calculated at the rate of $153 per week; and; i) $153 per week or part thereof for further loss of Treatment Room 2 from 6 April 2004 until the completion of the building works, payable at the end of each week by cheque delivered to the lease premises during trading hours of the applicant’s business or as otherwise agreed between the parties.; 8.The Respondent pay the Applicant an agreed amount of $4,350 ($4,785 less GST) for the Applicant to replace the joinery (only) in Treatment Room 2.; 9.The Respondent pay the Applicant interest on the compensation payable under order 5 only at the rate of 6.57 per cent, being $2,292.; 10.The amounts referred to in orders 5-9 (excluding orders 6(b) and 7(b)) being the sum of $54,235, including interest, be paid within 28 days from the date of this order.; Costs order; 11.The Respondents pay one half of the Applicant’s costs of preparation for trial up to the commencement of but not including the actual conduct of the hearing of 22 July and is to pay all of the Applicant’s costs (including preparation) for the conduct of the matter on 23 and 24 July and all subsequent appearances in the matter including appearance of 6 April 2004, all on a party/party basis.; Liberty to apply; 12.Liberty to either party to apply on 7 days’ notice.; Declaration; 13.The Lease granted by the Respondent to the Applicant comprised an exclusive right to occupy the ground floor built area as identified by the highlighter outlined area shown in the plan attached to this order, but noting that the plan does not accurately reflect the new laundry and new WC because that is still to be built. The lease further included a shared right to park a vehicle in Carney Lane and a shared right of access to the rear lane Council car park identified in the plan as existing garage as limited by clause 3.4 and 11.3.2 of the lease.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.