| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
TECHNOLOGY ENGINEERING AND CONSTRUCTION LIST
No. 10443 of 2008
| MATERIALS FABRICATION PTY LTD (ACN 078 812 905) | Plaintiff |
| v | |
| BAULDERSTONE PTY LTD (ACN 002 625 130) | Defendant |
---
JUDGE: | VICKERY J | |
WHERE HELD: | MELBOURNE | |
DATE OF HEARING: | 7 SEPTEMBER 2009 | |
DATE OF JUDGMENT: | 8 SEPTEMBER 2009 | |
CASE MAY BE CITED AS: | MATERIALS FABRICATION PTY LTD v BAULDERSTONE PTY LTD | |
MEDIUM NEUTRAL CITATION: | [2009] VSC 405 | |
---
Practice and Procedure – Application for lifting of a stay of the proceeding – Contractual provisions providing for pre-conditions for the institution of proceedings – Notice of calculation of loss – Payment of 10% of amount claimed as security to the builder’s solicitor – Non compliance with notice of calculation of loss provision – Security provision ruled void as against public policy – Discretionary considerations for lifting of stay - Technology Engineering and Construction (TEC) List objective – Case management considerations.
Building Contracts - Contractual provisions providing for pre-conditions for the institution of proceedings – Notice of calculation of loss – Payment of 10% of amount claimed as security to the builder’s solicitor – Non compliance with notice of calculation of loss provision – Security provision ruled void as against public policy
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff/Applicant | Mr D Fairweather (solicitor) | Fairweather Legal |
| For the Defendant | Mr MG Roberts | Deacons |
HIS HONOUR:
In this matter the plaintiff, Materials Fabrication Pty Ltd, seeks the leave of the Court to lift the stay order made 26 February 2009 to enable it to prosecute its claims against the Defendant, Baulderstone Pty Ltd. This proceeding was commenced by Materials Fabrication against Baulderstone by writ filed 19 December 2008.
Materials Fabrication claims that on 18 July 2007 it was engaged by Baulderstone to manufacture supply and install structural steel and metal work at the Life Lab project in Digital Harbour Docklands in Melbourne for the sum of $956,167 (the "Structural Steel Subcontract"). It also claims that it was engaged under a second subcontract by Baulderstone made on 27 August 2007 to manufacture, supply and install aluminium windows and doors to the external façade and internal windows and doors to the office suite of the project for the price of $1,545,966 (the "Façade and Glazing Subcontract"). The Structural Steel Subcontract and the Façade and Glazing Subcontract are together referred to as the “subcontracts”.
Materials Fabrication claims that on or about 14 February 2008 Baulderstone wrongfully terminated both of the subcontracts. On and from 16 January 2009 in correspondence exchanged between the parties Baulderstone relied upon clause 20.3 of the subcontracts which provided that a precondition for commencing proceedings was the payment of 10 per cent of the sum claimed, that sum being required to be paid to Baulderstone's solicitor as security for its costs.
Materials Fabrication did not provide the security payment as prescribed by Clause 20.3 of both of the subcontracts, nor does it make any offer or give any undertaking to make…
Keep reading for free
Create a free CaseChat account to read Materials Fabrication Pty Ltd v Baulderstone Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2009] VSC 405
- Decision Date
CaseChat Overview and Summary
The court examined the contractual provisions and determined that the notice of calculation of loss provision had not been complied with, rendering it ineffective. The court further found that the security provision, which required the payment of 10% of the claimed amount to the builder's solicitor, was void as it contravened public policy. The court considered the objectives of the Technology Engineering and Construction (TEC) List, which aimed to promote efficiency and fairness in construction disputes, and weighed these against the discretionary considerations for lifting the stay. The court also took into account the case management considerations that had been presented.
In reaching its decision, the court held that the contractual pre-conditions for the institution of legal proceedings were not satisfied due to the non-compliance with the notice of calculation of loss provision. The court also ruled that the security provision was void as against public policy. Given these findings, the court decided not to lift the stay of proceedings, as it was not appropriate to do so in light of the contractual non-compliance and the public policy considerations. The court's decision balanced the objectives of the TEC List with the need to ensure that parties adhere to the contractual terms they have agreed upon.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi