JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM: COMMERCIAL & CIVIL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: MATCH PROJECTS PTY LTD and ARCCON (WA) PTY LTD [2009] WASAT 56
MEMBER: MR C RAYMOND (SENIOR MEMBER)
HEARD: 25 MARCH 2009
DELIVERED : 2 APRIL 2009
FILE NO/S: CC 236 of 2009
BETWEEN: MATCH PROJECTS PTY LTD
Applicant
AND
ARCCON (WA) PTY LTD
Respondent
Catchwords:
Construction Contracts Act 2004 (WA) - Application for extension of time
Legislation:
Builders' Registration Act 1939 (WA)
Construction Contracts Act 2004 (WA), s 3, s 26, s 26(1), s 26(1)(b), s 29(3), s 30, s 31(2), s 31(2)(a), s 31(2)(a)(i), s 31(2)(b), s 31(3), s 32(2)(a), s 32(2)(b), s 32(3), s 33, s 36, s 41(1), s 42(2), s 46, s 46(1), s 46(2), s 49
Corporations Act 2001 (Cth)
State Administrative Tribunal Act 2004 (WA), s 29(3)(c)(i), s 29(3)(c)(ii), s 42, s 91
State Administrative Tribunal Rules 2004 (WA), r 10
Town Planning and Development Act 1928 (WA)
Result:
Application granted
Category: B
Representation:
Counsel:
Applicant: Mr W Ryan
Respondent: Mr S Boyle
Solicitors:
Applicant: Deacons
Respondent: Clayton Utz
Case(s) referred to in decision(s):
Diploma Construction Pty Ltd and Esslemont Nominees Pty Ltd [2006] WASAT 350
Esther Investments Pty Ltd v Markalinga Pty Ltd (1989) 2 WAR 196
Gallo v Dawson (1990) 64 ALJR 458
ITQ Pty Ltd and Hyde Park Management Ltd [2008] WASAT 66
Jackamarra v Krakouer (1998) 195 CLR 516
Mustac v Medical Board of Western Australia [2007] WASCA 128
O'Connor and Town of Victoria Park [2005] WASAT 161
O'Donnell Griffin Pty Ltd v John Holland Pty Ltd [2009] WASC 19
The Owners of Strata Plan 18449 and City of Joondalup [2005] WASAT 304
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of Tribunal's decision
The Tribunal heard an application to extend the time to review the decision of an adjudicator under s 46(1) of the Construction Contracts Act 2004 (WA). The adjudicator had handed down a determination requiring the applicant to pay the respondent an amount of $650,783.93.
The Tribunal applied the criteria as set out in O'Connor and Town of Victoria Park [2005] WASAT 161 in determining whether or not to grant the extension of time. In relation to each relevant factor, the Tribunal found as follows.
The Tribunal found that the period of delay was seven weeks; alternatively, depending upon the date on which a valid adjudication application was taken to have been delivered, a period of five weeks. The Tribunal concluded that a delay of seven weeks, or five weeks, in the context of legislation which required an entire adjudication process to be generally completed within 28 days, was a lengthy delay. In the course of determining the length of delay, the Tribunal concluded a proposed basis of review in which it was submitted that the Tribunal should determine whether the adjudication application was to be deemed to be dismissed under s 31(3) of the Construction Contracts Act 2004 (WA) was not susceptible to the Tribunal's jurisdiction. The Tribunal held…
Keep reading for free
Create a free CaseChat account to read MATCH PROJECTS PTY LTD and ARCCON (WA) PTY LTD and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] WASAT 56
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the applicant had provided sufficient evidence to justify an extension of time and whether the respondent had acted unreasonably in denying the extension. The court had to determine if the applicant had a genuine entitlement to an extension of time and if the respondent's denial was justified under the statutory framework. The court also needed to consider the specific provisions of the Construction Contracts Act 2004 (WA) and how they applied to the facts of the case.
In its reasoning, the court examined the evidence provided by both parties and assessed the application's compliance with the statutory requirements. The court found that the applicant had demonstrated sufficient grounds for an extension of time in most aspects of the application. However, regarding a specific relief sought in Order 4, the court determined that the applicant had not met the necessary criteria. Consequently, the court granted an extension of time for the majority of the application but refused it for the particular relief sought in Order 4.
Orders
Orders of the court
For the above reasons, an order will issue as follows. 1. An extension of time is granted for the making of this application for the orders sought as set out in the application lodged on 17 February 2009 under the section 'Decision Sought', save in respect of Order 4 thereof. 2. The application for an extension of time for the making of this application is refused in respect of the relief sought in Order 4 of the application.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.