Maryrorough Solar Pty Ltd v The State of Queensland [2019] QSC 135
PARTIES:
MARYROROUGH SOLAR PTY LTD
ACN 609 762 138
(applicant)
v
THE STATE OF QUEENSLAND
(respondent)FILE NO:
SC No 5299 of 2019
DIVISION:
Trial
PROCEEDING:
Originating Application
ORIGINATING COURT:
Supreme Court at BrisbaneDELIVERED ON:
29 May 2019
DELIVERED AT:
Brisbane
HEARING DATE:
29 May 2019
JUDGE:
Bradley J
ORDER:
The parties are to make submissions on the form of declaratory relief.
CATCHWORDS:
ADMINISTRATIVE LAW – JUDICIAL REVIEW – POWER OF COURTS UNDER JUDICIAL REVIEW LEGISLATION – DECLARATIONS – STATUTES – SUBORDINATE LEGISLATION – CONSTRUCTION – VALIDITY – where the applicant seeks a declaration that s 73A of the Electrical Safety Regulation 2013 (Qld) is invalid – where s 73A was inserted by the Electrical Safety (Solar Farms) Amendment Regulation 2019 (Qld) – where both regulations were made by the Governor in Council pursuant to a regulation-making power under s 210 of the Electrical Safety Act 2002 (Qld) – where an effect of s 73A is to require work involving pholtovoltaic modules at solar farms to be undertaken by a licensed electrical worker – where the work in question does not fall within the scope of the definition of “electrical work” under the Act and is expressly excluded from the licensing provisions of the Act – where the applicant contends that s 73A is beyond the regulation-making power conferred by s 210 of the Act and further contends that s 73A is inconsistent with the Act – where the respondent contends that s 73A was enacted specifically pursuant to s 210(2)(b) of the Act, which authorises a regulation prescribing “ways of ensuring the electrical safety of persons or property” – where the respondent contends that s 73A further carries into effect the object found in s 4(1) of the Act to eliminate “the human cost to individuals, families and the community of death, injury and destruction that can be caused by electricity”, and that it seeks to achieve that purpose in a way authorised by s 5 of the Act – whether s 73A is within the regulation-making power conferred by s 210 of the Act – whether s 73A imposed a duty on persons who may affect electrical safety, within the meaning of s 5(a) of the Act – whether s 73A established a benchmark for industry and the community generally as a regulation about achieving electrical safety, within the meaning of s 5(b)(i) of the Act – whether s 73A is inconsistent with the licensing provisions of the Act
Electrical Safety Act 2002 (Qld), s 4, s 5, s 210
Electrical Safety Regulation 2013 (Qld), s 73A
Judicial Review Act 1991 (Qld), s 43(2)
Statutory Instruments Act 1992 (Qld), s 22Morton v The Union Steamship Company of New Zealand Limited (1951) 83 CLR 402; [1951] HCA 42, cited
Shanahan v Scott (1957) 96 CLR 245; [1957] HCA 4, citedCOUNSEL:
P Dunning QC, with B…
Keep reading for free
Create a free CaseChat account to read Maryrorough Solar Pty Ltd v The State of Queensland and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2019] QSC 135
- Decision Date
CaseChat Overview and Summary
The court examined whether section 73A was within the regulation-making power conferred by section 20 of the Act. It assessed if the regulation imposed a duty on those who might affect electrical safety, as per section 5(a) of the Act, and if it set a benchmark for industry and the community about achieving electrical safety, as per section 5(b)(i) of the Act. The court also considered whether section 73A was inconsistent with the licensing provisions of the Act. The State argued that the regulation was a legitimate means to prevent electrical harm, while Maryrorough Solar contended that it was not authorised by the Act and did not serve its purpose. The court found that section 73A was within the regulatory power granted by the Act and did not conflict with its licensing provisions.
The court concluded that the regulation was valid and consistent with the Act. It found that the regulation was a permissible way to ensure electrical safety, despite not fitting neatly within the definition of "electrical work." The court determined that the regulation served the Act's purpose of preventing electrical harm and did not conflict with the licensing provisions. The court ordered the parties to submit their views on the form of declaratory relief.
Orders
Orders of the court
The parties are to make submissions on the form of declaratory relief.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi