Marshall v Department of Transport
[2002] QLC 51
•27 June 2002
LAND COURT OF QUEENSLAND
CITATION: Marshall v Department of Transport [2002] QLC 51
PARTIES: Melville Robert Marshall
(claimant)
v
Director-General, Department of Transport
(respondent)
FILE NO: A1992-0077
DIVISION: Land Court of Queensland
PROCEEDING: Hearing of Application
DELIVERED ON: 27 June 2002
DELIVERED AT: Brisbane
HEARD AT: Brisbane
MEMBER: Mr RP Scott
ORDER: 1. The engineering experts for the parties file a joint statement of their agreement/disagreement by 28 June 2002.
2.The claimant file and serve on the respondent, any further reports from its hydraulic experts arising out of the videos of the physical model, including a shortened video (if it wishes), on or before 3 July 2002.
3.The hydraulic experts for the respondent file and serve any additional report, if necessary, in response to and arising out of the reports from the claimant's hydraulic experts (covering areas of disagreement only) by 17 July 2002.
4.The hydraulic experts for the parties meet to agree and disagree any further issues, especially regarding the physical model videos, by 18 July 2002.
5.The hydraulic experts for the parties file a joint statement of their agreement/disagreement by 19 July 2002.
6.Costs be reserved.
IN THE LAND COURT
OF QUEENSLAND
A1992/0077
BETWEEN:
Melville Robert Marshall
and Director General, Department of Transport
Claimant
Respondent
Before Mr RP Scott BRISBANE
The Twenty-seventh day of June 2002
The parties having been heard and by consent of the parties, the Court vacates the orders numbered 5 to 9 made on 1 May 2002 and in lieu thereof makes the following ORDERS:
1.The engineering experts for the parties file a joint statement of their agreement/disagreement by 28 June 2002.
2.The claimant file and serve on the respondent, any further reports from its hydraulic experts arising out of the videos of the physical model, including a shortened video (if it wishes), on or before 3 July 2002.
3.The hydraulic experts for the respondent file and serve any additional report, if necessary, in response to and arising out of the reports from the claimant's hydraulic experts (covering areas of disagreement only) by 17 July 2002.
4.The hydraulic experts for the parties meet to agree and disagree any further issues, especially regarding the physical model videos, by 18 July 2002.
5.The hydraulic experts for the parties file a joint statement of their agreement/disagreement by 19 July 2002.
6.Costs be reserved.
By the Court
Registrar
2
0
0
0