Marianne Velickovic & Others on behalf of the Widji People/Western Australia/Polymetals (WA) Pty Ltd; Western Resources Pty Ltd, Zetek Resources Pty Ltd
[2009] NNTTA 161
•2 December 2009
NATIONAL NATIVE TITLE TRIBUNAL
Marianne Velickovic & Others on behalf of the Widji People/Western Australia/Polymetals (WA) Pty Ltd; Western Resources Pty Ltd, Zetek Resources Pty Ltd, [2009] NNTTA 161 (2 December 2009)
Application Nos: WO09/446, WO09/465
IN THE MATTER of the Native Title Act 1993 (Cth)
-and-
IN THE MATTER of an inquiry into expedited procedure objection applications
Marianne Velickovic & Others on behalf of the Widji People – WC98/27 (native title party)
-and-
The State of Western Australia (Government party)
-and-
Polymetals (WA) Pty Ltd (WO09/446)
Western Resources Pty Ltd, Zetek Resources Pty Ltd (WO09/465)(grantee parties)
DECISION TO DISMISS OBJECTION APPLICATIONS
Tribunal: Hon C J Sumner, Deputy President
Place: Perth
Date of decision: 30 November 2009
Date of reasons: 2 December 2009
Catchwords: Native title – future acts – proposed grant of prospecting licences – expedited procedure objection applications – failure to comply with directions – springing orders dismissing expedited procedure objection applications in event of non-compliance – objection applications dismissed.
Legislation: Native Title Act1993 (Cth) ss 29, 148(b)
Cases:Leonne Velickovic on behalf of the Widji People/Western Australia/Frederick Saunders, NNTT WO05/564, [2006] NNTTA 76 (15 June 2006), Hon C J Sumner
Representative of the
native title party: Mr Jerome Frewen, Desert Management Pty Ltd
Representatives of the Mr Greg Abbott, Department of Mines and Petroleum
Government party: Ms Claire Malavaux, Department of Mines and Petroleum
Representative of the Mr Kevin Connell, Austwide Mining Title Management P/L (WO09/446)
grantee parties: Mr Eamon Cornelius, Western Tenement Services (WO09/465)
REASONS FOR DECISION TO DISMISS OBJECTION APPLICATIONS
Background
On 1 July 2009, the Government party gave notice under s 29 of the Native Title Act1993 (Cth) of its intention to grant prospecting licence P25/2031 to Polymetals (WA) Pty Ltd and prospecting licence P24/4431 to Zetek Resources Pty, Western Resources Pty Ltd (‘the grantee parties’) and included in the notice a statement that it considered that the grants attracted the expedited procedure.
On 30 June 2009, Marianne Velickovic & Others on behalf of the Widji People - Native Title Claim No. WC98/27 registered on 15 June 1998 (‘the native title party’) made expedited procedure objection applications to the Tribunal in relation to P25/2031 (WO09/446) and P24/4431 (WO09/465).
In each case the Tribunal made directions on 12 August 2009, requiring all parties to produce contentions and evidence for the conduct of the inquiry to determine whether or not the expedited procedure was attracted. The native title party was to provide a statement of contentions, documentary evidence and witness statements verified where possible by affidavits on or before 30 November 2009. The directions imposed a springing order which has the effect of immediately dismissing the objection applications pursuant to s 148(b) of the Native Title Act if there is non-compliance by close of business on the due date. In making the decision to impose the springing order I adopted the Tribunal’s findings in Leonne Velickovic on behalf of the Widji People/Western Australia/Frederick Saunders, NNTT WO05/564, [2006] NNTTA 76 (15 June 2006), Hon C J Sumner at [15]–[21]. The native title party has in each case failed to comply by the due date.
Decision
Expedited procedure objection applications WO09/446 and WO09/465 are dismissed pursuant to s 148(b) of the Native Title Act 1993 (Cth).
Hon C J Sumner
Deputy President
2 December 2009