Mariane Velickovic on behalf of the Widji People/Western Australia/Peter Romeo Gianni; Siberia Mining Corporation Pty Ltd

Case

[2009] NNTTA 12

12 February 2009


NATIONAL NATIVE TITLE TRIBUNAL

Mariane Velickovic on behalf of the Widji People/Western Australia/Peter Romeo Gianni; Siberia Mining Corporation Pty Ltd, [2009] NNTTA 12 (12 February 2009)

Application Nos:               WO08/525, WO08/526, WO08/527, WO08/528, WO08/529

IN THE MATTER of the Native Title Act 1993 (Cth)

-and-

IN THE MATTER of an inquiry into expedited procedure objection applications

Marianne Velickovic on behalf of Widji People – WC98/27 (native title party)

-and-

The State of Western Australia (Government party)

-and-

Peter Romeo Gianni (WO08/525-526)
Siberia Mining Corporation Pty Ltd (WO08/527-529) (grantee parties)

DECISION TO DISMISS OBJECTION APPLICATIONS

Tribunal:  Hon C J Sumner, Deputy President
Place:  Perth
Date of dismissal:               9 February 2009
Date of reasons:                 12 February 2009

Catchwords:  Native title – future acts – proposed grant of prospecting licences - expedited procedure objection applications – failure to comply with directions – springing order dismissing expedited procedure objection applications in event of non-compliance – objection applications dismissed.

Legislation:Native Title Act1993 (Cth) s 148(b)

Cases:Leonne Velickovic on behalf of the Widji People/Western Australia/Frederick Saunders, NNTT WO05/564, [2006] NNTTA 76 (15 June 2006), Hon C J Sumner

Representative of the

native title party:              Mr Jerome Frewen, Desert Management Pty Ltd

Representatives of the      Mr Greg Abbott, Ms Violet Jacobs,

Government party:           Department of Mines & Petroleum

Representatives of the      Mr Mike Lewis, Rubysands Pty Ltd (WO08/525 & WO08/526)

grantee party:  Ms Grace Tan, Central Tenement Services (WO08/527, WO08/528 & WO08/529)

REASONS FOR DECISION TO DISMISS OBJECTION APPLICATIONS

Background

  1. On 18 June 2008, the Government party gave notice under s 29 of the Native Title Act1993 (Cth) of its intention to grant prospecting licences P24/4289 and P24/4290 to Peter Romeo Gianni and prospecting licences P24/4177, P24/4178 and P24/4180 to Siberia Mining Corporation Pty Ltd and included in the notice a statement that it considered that each of the grants attracted the expedited procedure.

  2. On 20 June 2008, Marianne Velickovic on behalf of the Widji People – Native Title Claim No. WC98/27 registered on 15 June 1998 (‘the native title party’) made expedited procedure objection applications to the Tribunal in relation to P24/4289 (WO08/525), P24/4290 (WO08/526), P24/4177 (WO08/527), P24/4178 (WO08/528) and P24/4180 (WO8/528).

Relevant facts

  1. In each case the Tribunal made directions on 22 July 2008 requiring all parties to produce contentions and evidence for the conduct of the inquiry to determine whether or not the expedited procedure was attracted. The native title party was to provide a statement of contentions, documentary evidence and witness statements verified where possible by affidavits on or before 9 February 2009. The directions imposed a springing order which has the effect of immediately dismissing the objection applications pursuant to s 148(b) of the Native Title Act if there is non-compliance by close of business on the due date.  In making the decision to impose the springing order I adopted the Tribunal’s findings in Leonne Velickovic on behalf of the Widji People/Western Australia/Frederick Saunders, NNTT WO05/564, [2006] NNTTA 76 (15 June 2006), Hon C J Sumner at [15] – [21]. The native title party has in each case failed to comply by the due date.

Decision

  1. Expedited procedure objection applications specified in the attached schedule are dismissed pursuant to s 148(b) of the Native Title Act1993 (Cth).

Hon C J Sumner
Deputy President
12 February 2009