Marcello Capone and Nicole Masson v Richard Lambert

Link copied
Case Copied 59 min read

NSW Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Marcello Capone and Nicole Masson v Richard Lambert [2014] NSWCATCD 124
Hearing dates:14, 15 November and 10 December 2013
Decision date: 16 July 2014
Before: D Goldstein, Senior Member
Decision:

1 For the reasons provided, the respondent must pay the applicants the sum of $65,716.57 within 21 days of the date of this decision.

2 The parties are at liberty to make a costs application in these proceedings.

3 Any costs application pursuant to section 60 of the Civil and AdministrativeTribunal Act 2013 or rule 38 of the Civil and AdministrativeTribunal Rules 2014 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this decision either attaching or referring to the documents relied upon in support of the application.

4 The costs respondent will have 21 days after the date it receives the costs application referred to lodge in the Tribunal and serve on the costs applicant its submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.

5 The cost applicant will have 14 days after the date it receives the cost respondent's submissions to lodge in the Tribunal and serve on the costs respondent its submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.

6 The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal

Catchwords: Presumption of regularity, statutory warranties, compliance with conditions of development consent, causation.
Legislation Cited: Civil and Administrative Tribunal Act 2013, Civil and Administrative Tribunal Rules 2014, Environmental Planning & Assessment Act 1979
Cases Cited: Alexander and Others v Cambridge Credit Corporation Ltd (1987) 9 NSWLR 310, Allianz v Waterbrook [2009] NSWCA 224, Hill v Woollahara Municipal Council and Ors [2003] NSWCA 106, 127 LGERA, Minister for Natural Resources v. NSW Aboriginal Land Council (1987) 9 NSWLR 154.
Texts Cited: Cross on Evidence, Contract Law in Australia, Fifth Edition.
Category:Principal judgment
Parties:

Marcello Capone and Nicole Masson (applicants)

Richard Lambert (respondent)
Representation: Mr G Jensen appeared for the applicants
Mr G Carolan appeared for the respondent
Harris Wheeler for the applicants
Roberts Legal for the respondent
File Number(s):HB 12/48071
Publication restriction:Unrestricted

reasons for decision

APPLICATION

  1. This application was commenced in September 2012. The applicants claimed the sum of $43,648.00 against the respondent for breach of statutory warranties.

  1. In these reasons I will refer to the applicants as the owners and to the respondent as the builder.

  1. The owners filed Further Amended Points of Claim in the Tribunal on 14 August 2013. Among other things, the owners amended the amount claimed to $95,968.00.

  1. By way of background, it is common ground that this application relates to a residence at XXXX Floraville (the 'property').

  1. The builder was previously the owner of the property and in the capacity of an owner builder…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Marcello Capone and Nicole Masson v Richard Lambert and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWCATCD 124
Decision Date

CaseChat Overview and Summary

In the matter of Marcello Capone and Nicole Masson v Richard Lambert, the applicants sought damages from the respondent for non-compliance with statutory warranties and failure to adhere to conditions of development consent. The dispute came before the Civil and Administrative Tribunal of New South Wales, where the applicants alleged that the respondent had failed to remedy defects in a property they had purchased from him. The central legal issues before the Tribunal were whether the respondent had breached statutory warranties by not rectifying the defects, whether the respondent had complied with the conditions of development consent, and whether the applicants' damages were causally linked to the respondent's non-compliance.

The Tribunal began by acknowledging the presumption of regularity in administrative actions, which presumes that public officials have performed their duties correctly. However, this presumption could be rebutted if evidence suggested otherwise. The Tribunal found that the evidence presented by the applicants was sufficient to rebut the presumption, as it demonstrated that the respondent had not taken reasonable steps to comply with the statutory warranties and conditions of development consent. The Tribunal also examined whether the applicants' claimed damages were directly caused by the respondent's non-compliance, a critical issue in determining the extent of liability. After reviewing the evidence, the Tribunal concluded that the applicants' damages were indeed causally linked to the respondent's failure to comply with the statutory warranties and conditions.

In light of these findings, the Tribunal ordered the respondent to pay the applicants $65,716.57 within 21 days. The Tribunal further provided detailed instructions for any subsequent costs applications, stipulating the timeframes and procedural requirements for lodging and responding to such applications. The orders reflect the Tribunal's consideration of both the substantive issues and the procedural fairness in handling the case.

Orders

Orders of the court

1 For the reasons provided, the respondent must pay the applicants the sum of $65,716.57 within 21 days of the date of this decision.

2 The parties are at liberty to make a costs application in these proceedings.

3 Any costs application pursuant to section 60 of the Civil and Administrative Tribunal Act 2013 or rule 38 of the Civil and Administrative Tribunal Rules 2014 must be lodged in the Tribunal and served on the costs respondent within 21 days of the date of this decision either attaching or referring to the documents relied upon in support of the application.

4 The costs respondent will have 21 days after the date it receives the costs application referred to lodge in the Tribunal and serve on the costs applicant its submissions, if any, in response to the costs application, such submissions either attaching or referring to the documents relied upon.

5 The cost applicant will have 14 days after the date it receives the cost respondent's submissions to lodge in the Tribunal and serve on the costs respondent its submissions, if any, in reply, such submissions either attaching or referring to the documents relied upon.

6 The Tribunal will determine any costs application on the basis of the papers lodged in the Tribunal

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.