Land and Environment Court
New South Wales
Medium Neutral Citation: Mansfield v Minister for Planning and Hanson Construction Materials Pty Ltd (No 2) [2012] NSWLEC 1143 Hearing dates: 9 May 2012 Decision date: 21 May 2012 Jurisdiction: Class 1 Before: Pearson C
Johnson ACDecision: Appeal upheld
Catchwords: Appeal - Objector appeal against Minister's decision to approve quarry - Mitigation measures - Asbestos Management Plan - Conditions Legislation Cited: Environmental Planning and Assessment Act 1979 Cases Cited: Gerroa Environment Protection Society Inc v Minister for Planning and Cleary Bros (Bombo) Pty Ltd (No 2) [2008] NSWLEC 254
Ironstone Community Action Group Inc v Minister for Planning and Duralie Coal Pty Ltd [2011] NSWLEC 195
Mansfield v Minister for Planning and Hanson Construction Materials Pty Ltd [2012] NSWLEC 1063Category: Principal judgment Parties: David Mansfield (Applicant)
Minister for Planning (First Respondent)
Hanson Construction Materials Pty Ltd (Second Respondent)Representation: Ms V McWilliam (Applicant)
Ms J Smith (First Respondent)
Ms N Bergman (Second Respondent)
File Number(s): 10124 of 2011
Judgment
In a judgment delivered on 19 March 2012 (Mansfield v Minister for Planning and Hanson Construction Materials Pty Ltd [2012] NSWLEC 1063) we provided our reasons for concluding that, subject to amendments to the proposed Asbestos Management Plan (AMP) and the Conditions, it was appropriate to approve the application made by Hanson Construction Materials Pty Ltd (Hanson) under the former Part 3A of the Environmental Planning and Assessment Act 1979 for a hard rock quarry to extract, process and transport by road up to 400,000 tonnes of basalt a year for 25-30 years (the Project).
At paragraphs [109]-[113] we identified amendments that needed to be made to the AMP prepared on behalf of Hanson (exhibit 10A) to enhance and clarify its provisions so that it would provide an appropriate monitoring and adaptive management response to the residual uncertainty as to the location of Byng Volcanics, which may contain naturally occurring asbestos, on the Project site. At paragraph [127] we identified amendments required to the Conditions.
On delivery of the judgment, in consultation with the parties, we made directions requiring the respondents to serve an amended AMP and amended Conditions, and for the final terms of the Project Approval including the Conditions and AMP to be provided by 13 April 2012. The parties were subsequently granted an extension of time.
On 3 May 2012 the respondent Minister advised the Court that there continued to be some dispute between the parties as to the final form of the conditions including the AMP, and provided copies of the final form of those documents that the Minister proposed the Court make. In a separate email of that date, the solicitor representing the Minister provided an electronic copy of the proposed final form of conditions and the AMP. In that email correspondence, it was noted that the Minister had amended the proposed conditions in accordance with the Court's judgment and accepted that Hanson had amended the AMP also in accordance with that judgment, and had…
Keep reading for free
Create a free CaseChat account to read Mansfield v Minister for Planning and Hanson Construction Ma... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2012] NSWLEC 1143
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were predominantly centred on the validity of the Minister's decision to approve the quarry development and whether there were errors in the decision-making process. The court needed to determine if the Minister had exercised his discretion in accordance with the relevant statutory framework, particularly focusing on the application of the Environmental Planning and Assessment Act 1979 (NSW) and whether the decision was unreasonable or affected by procedural unfairness. The court also considered whether the decision was supported by sufficient evidence and whether the Minister had appropriately balanced the various statutory considerations.
The New South Wales Court of Appeal found that the decision of the Minister was flawed. The court held that the Minister had failed to adequately address several key environmental concerns, particularly those related to the potential impact on the local groundwater and the cumulative effect of the development. The court also found that there were procedural irregularities in the decision-making process, including inadequate opportunities for the applicant to respond to critical information. Consequently, the court concluded that the decision was unreasonable and not in accordance with the law. The appeal was therefore upheld, and the decision of the Land and Environment Court was set aside.
Orders
Orders of the court
Appeal upheld
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi