| CITATION: | Makarenko v Page [2018] QCAT 143 |
| PARTIES: | Justyn Makarenko (Applicant) |
| v | |
| Peter William Page (Respondent) |
| APPLICATION NUMBER: | BDL231-17 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | On the papers |
| HEARD AT: | Brisbane |
| DECISION OF: | Dr Alan Collier, Member |
| DELIVERED ON: | 21 May 2018 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | Respondent to pay Applicant $16,953.55 within 21 days. |
| CATCHWORDS: | CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – LEGALITY – whether agreement formed by the parties satisfies the requirements of a level 1 regulated contract as prescribed in the Queensland Building and Construction Commission Act 1991 (Qld) – whether the contract has effect CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – STATUTORY WARRANTIES FOR RESIDENTIAL BUILDING WORK – where implied warranty that builder will perform the work for which he was engaged in an appropriate and skilful way and with reasonable care and skill – whether builder breached that warranty TRADE AND COMMERCE – COMPETITION, FAIR TRADING AND CONSUMER PROTECTION LEGISLATION – CONSUMER PROTECTION – GUARANTEES, CONDITIONS AND WARRANTIES IN CONSUMER TRANSACTIONS – GUARANTEES, CONDITIONS AND WARRANTIES – whether builder breached guarantee relating to the supply of services under the Australian Consumer Law – whether builder breached guarantee as to due care and skill under the Australian Consumer Law CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – REMUNERATION – RECOVERY – whether the builder is entitled to payment for the work – whether the builder is entitled to recover the cost of work on quantum meruit – where work of such poor quality that the applicant obliged to have work performed again in its entirety – where applicant has received no benefit from the work performed by the builder and accordingly where quantum meruit is not applicable – where appropriate remedy is for applicant to be compensated in an amount equal to having the work done again in its entirety Australian Consumer Law, s 60 |
APPEARANCES: |
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act)
REASONS FOR DECISION
Procedural Matters
The Application commencing this matter was filed on 26 September 2017.
There is an Affidavit of Service dated 13 October 2017 in which the deponent, the Applicant in this matter, Mr Makarenko, deposes that he posted a copy of the Application to the Respondent at 18 Tovey Road Boronia Heights Queensland 4124.
Applying the relevant QCAT Rule (rule 39) in relation to service of the Application, in conjunction with s 109A of the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act), the enabling Act in this case, it is clear…
Keep reading for free
Create a free CaseChat account to read Makarenko v Page and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCAT 143
- Decision Date
CaseChat Overview and Summary
The tribunal first assessed the legality of the contract and concluded that the agreement did not satisfy the requirements of a level 1 regulated contract. However, the tribunal found that the contract still had effect because the parties intended to be legally bound by its terms. Regarding the quality of the work, the tribunal found that the builder did not perform the work in an appropriate and skilful way, breaching the implied warranty. Additionally, the tribunal determined that the builder breached the guarantee relating to the supply of services under the Australian Consumer Law by not exercising due care and skill. The tribunal found that the work was of such poor quality that the homeowner was obliged to have the work performed again in its entirety. As a result, the tribunal concluded that the builder was not entitled to payment for the work and that quantum meruit was not applicable. Instead, the appropriate remedy was for the builder to compensate the homeowner in an amount equal to having the work done again in its entirety.
The tribunal ordered the builder to pay the homeowner $16,953.55 within 21 days. This decision highlights the importance of ensuring that building contracts comply with statutory requirements and that builders perform their work with due care and skill. It also underscores the homeowner's right to compensation when a builder fails to meet these standards.
Orders
Orders of the court
Respondent to pay Applicant $16,953.55 within 21 days.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.