Maitland City Council v Link Building Services Pty Limited

Link copied
Case Copied 12 min read

Land and Environment Court


of New South Wales


CITATION: Maitland City Council v Link Building Services Pty Limited [2008] NSWLEC 71
This decision has been amended. Please see the end of the judgment for a list of the amendments.
PARTIES:

PROSECUTOR:
Maitland City Council

DEFENDANT:
Link Building Services Pty Limited
ACN 003 906 483
FILE NUMBER(S): 50018 of 2007
CORAM: Lloyd J
KEY ISSUES: Prosecution :- carrying out development without first obtaining development consent - plea of guilty - penalty - relevant objective considerations - gaining commercial advantage - no environmental harm - no direct expression of contrition and remorse - mitigating factors
LEGISLATION CITED: Crimes (Sentencing Procedure) Act 1999 s 3A
Environmental Planning and Assessment Act 1979 s 76A(1)(a) and s 125(1),
Fines Act 1996 Pt 2 Div 2
CASES CITED: Keir v Sutherland Shire Council [2004] NSWLEC 754
R v Elfar [2003] NSWCCA 358
R v McGourty [2002] NSWCCA 335
R v Qutami [2001] 127 A Crim R 369
R v Visconti [1982] 2 NSWLR 104
DATES OF HEARING: 31 January 2008
EX TEMPORE JUDGMENT DATE: 31 January 2008
LEGAL REPRESENTATIVES:

PROSECUTOR:
C J Leggat SC
Solicitors:
Thomson Norrie

DEFENDANT:
G Green (solicitor)
SOLICITORS:
Pike Pike & Fenwick


JUDGMENT:


IN THE LAND AND
ENVIRONMENT COURT


OF NEW SOUTH WALES

Lloyd J

Thursday, 31 January 2008

LEC No. 50018 of 2007

MAITLAND CITY COUNCIL v LINK BUILDING SERVICES PTY LIMITED [2008] NSWLEC 71

1

HIS HONOUR : The defendant, Link Building Services Pty Limited, pleads guilty to a charge that between 19 April 2005 and 5 December 2005 at East Maitland it committed an offence against s 125(1) of the Environmental Planning and Assessment Act 1979 (‘the EP&A Act ”) in that it carried out development being development which required development consent in circumstances where a development consent had not been obtained contrary to s 76A (1)(a) of the Act. The question for determination is the appropriate penalty which should be imposed.

2

The defendant entered a plea of guilty at an early opportunity and has co-operated with the prosecutor not only in its investigation of the offence but in the preparation of an agreed statement of facts.

3

It is convenient to briefly refer to the agreed statement of facts in order to understand the nature of the offence. The offence was committed on a property known as the Bank Hotel at Nos. 72-74 Melbourne Street, East Maitland.

4

The defendant corporation is and has been at all relevant times the owner of that property and is also a building company which is engaged in other building activities. The sole director and secretary of the defendant company is Mr Allan James Stivano.

5

The land at Nos. 72-74 Melbourne Street East Maitland is zoned 3(b) Support Business under the the Maitland Local Environmental Plan 1993 (“the LEP”). On land so zoned development consent is required to carry out any development other than prohibited development. The use of land for the purpose of a hotel is not prohibited development.

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Maitland City Council v Link Building Services Pty Limited and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2008] NSWLEC 71
Decision Date

CaseChat Overview and Summary

Maitland City Council prosecuted Link Building Services Pty Limited for carrying out development without obtaining the necessary development consent, an offence under the Environmental Planning and Assessment Act 1979. The defendant pleaded guilty, and the court had to determine the appropriate penalty. Key legal issues included the objective seriousness of the offence, the need for general deterrence, and the role of mitigating factors such as the defendant's plea of guilty and cooperation with the prosecutor.

The court found the offence to be a serious breach of planning laws, emphasizing the importance of ensuring compliance with development consent requirements to maintain the integrity of the planning system. While the council noted there was no significant environmental harm and the work was later approved, the deliberate nature of the contravention warranted a strong deterrent penalty. The court also considered the defendant's commercial motivation and the lack of direct expression of contrition and remorse by the defendant's director and secretary.

Ultimately, the court imposed a penalty of $17,500, reduced from an initial $25,000 due to mitigating factors. This penalty, combined with an agreed payment of $80,000 in prosecutor's costs, resulted in a total monetary punishment of $97,000. The court's decision aimed to adequately punish the defendant, deter both the defendant and others from similar offences, and recognize the harm caused to the community by the unlawful development.