Mackenzie v Norton St. Project Pty Ltd

Link copied
Case Copied 15 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Mackenzie v Norton St. Project Pty Ltd [2025] NSWCATCD 25
Hearing dates: 26 November 2024
Date of orders: 24 April 2025
Decision date: 24 April 2025
Jurisdiction:Consumer and Commercial Division
Before: B Koch, General Member
Decision:

1.    The applicant is to cause the performance of the following fencing work between [xxxx], Leichhardt NSW and [xxxx], Leichhardt NSW within 60 days of the date of these orders:

(a)   demolition and removal of the existing fence between the properties in a manner appropriate having regard to the presence of asbestos in the existing fence; and

(b)   construction of a 1.8m high lapped and capped timber paling fence along the existing fence line, save that the fence is to be constructed around the existing Celtis tree on the existing fence line. To the extent the existing fence line is unclear at the time of construction, the fence is to be located on the boundary between the properties disclosed by the topographical survey adduced in evidence by the applicant.

2.    The fencing work is to be performed by a suitably licensed fencing contractor selected by the applicant.

3.    The fencing work is to be paid for by the applicant and the respondent is to contribute to the cost of the fencing work by way of making a payment to the applicant as set out in these orders.

4.    Within 21 days of completion of the fencing work, the applicant is to send to the respondent in writing a copy of all tax invoices that pertain to the fencing work the subject of these orders.

5.    Within 7 days of being provided with the documents the subject of order 4 above, the respondent is to pay the applicant the 50% of the cost of the fencing work up to a maximum of $3,327.50. If the total cost of the fencing work is less than $6,655, the respondent is to pay the applicant 50%. If the total cost of the fencing work exceeds $6,655, the respondent is to pay the applicant $3,327.50.

Catchwords:

DIVIDING FENCES — Whether sufficient dividing fence — Type of replacement fence — Location of replacement fence — Contribution to cost of fencing work

Legislation Cited:

Dividing Fences Act 1991 (NSW)

Cases Cited:

JDW Services Pty Ltd as Trustee for the JDW Superannuation Fund v O’Dea [2022] NSWCATCD 29

Nicholls v Fortmann [2020] NSWCATAP 52

Purcell v Chadwick [2018] NSWCATAP 250

Texts Cited:

Nil

Category:Principal judgment
Parties:

Katrina Mackenzie (Applicant)

Norton St. Project Pty Ltd (Respondent)
Representation:

Ms Mackenzie in person (Applicant)

Mr Tannous, director (Respondent)
File Number(s): 2024/00293240
Publication restriction: Nil

REASONS FOR DECISION

  1. The applicant and the respondent are adjoining owners of land in Leichhardt, New South Wales. The applicant seeks orders under the Dividing Fences Act 1991 (Act) in respect of part of the boundary between the parties’ properties.

  2. Both parties participated in the hearing of the application on 26 November 2024. The Tribunal has had…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mackenzie v Norton St. Project Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWCATCD 25
Decision Date

CaseChat Overview and Summary

In the matter of Mackenzie v Norton St. Project Pty Ltd, the court was asked to determine whether a sufficient dividing fence existed between the adjoining properties of the parties in Leichhardt, NSW. The applicant sought the removal of the existing fence and the erection of a new one, while the respondent contested the necessity and type of the proposed fence.

The legal issues before the court involved the adequacy of the existing dividing fence and the appropriate type, location, and cost-sharing of any replacement fence. The applicant argued that the existing fence did not meet the requirements of a dividing fence and requested the construction of a 1.8m high lapped and capped timber paling fence. The respondent opposed the type and location of the fence and disputed the cost-sharing arrangement proposed by the applicant.

The court found that the existing fence was not adequate as a dividing fence and ordered its demolition and replacement with a 1.8m high lapped and capped timber paling fence. The court also ruled that the fence should be constructed around an existing Celtis tree on the fence line and, where the fence line was unclear, should be located on the boundary disclosed by the topographical survey. The court determined that the respondent should contribute 50% of the cost of the fencing work, up to a maximum of $3,327.50. If the total cost exceeded $6,655, the respondent's contribution would be capped at $3,327.50.

The court's final orders mandated the applicant to carry out the specified fencing work within 60 days and to send a copy of all tax invoices to the respondent within 21 days of completion. The respondent was required to pay the applicant's specified contribution within 7 days of receiving the invoices.

Orders

Orders of the court

1. The applicant is to cause the performance of the following fencing work between [xxxx], Leichhardt NSW and [xxxx], Leichhardt NSW within 60 days of the date of these orders:

(a) demolition and removal of the existing fence between the properties in a manner appropriate having regard to the presence of asbestos in the existing fence; and

(b) construction of a 1.8m high lapped and capped timber paling fence along the existing fence line, save that the fence is to be constructed around the existing Celtis tree on the existing fence line. To the extent the existing fence line is unclear at the time of construction, the fence is to be located on the boundary between the properties disclosed by the topographical survey adduced in evidence by the applicant.

2. The fencing work is to be performed by a suitably licensed fencing contractor selected by the applicant.

3. The fencing work is to be paid for by the applicant and the respondent is to contribute to the cost of the fencing work by way of making a payment to the applicant as set out in these orders.

4. Within 21 days of completion of the fencing work, the applicant is to send to the respondent in writing a copy of all tax invoices that pertain to the fencing work the subject of these orders.

5. Within 7 days of being provided with the documents the subject of order 4 above, the respondent is to pay the applicant the 50% of the cost of the fencing work up to a maximum of $3,327.50. If the total cost of the fencing work is less than $6,655, the respondent is to pay the applicant 50%. If the total cost of the fencing work exceeds $6,655, the respondent is to pay the applicant $3,327.50.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established