Mackay Resource Developments Pty Ltd v Mackay Regional Council (No. 2)

Link copied
Case Copied 8 min read

PLANNING & ENVIRONMENT COURT OF QUEENSLAND

CITATION:

Mackay Resource Developments Pty Ltd v Mackay Regional Council & Ors (No. 2) [2015] QPEC 39

PARTIES:

MACKAY RESOURCE DEVELOPMENTS PTY LTD (ACN 134 090 903)

(appellant)

v

MACKAY REGIONAL COUNCIL

(respondent)

CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT & MAIN ROADS

(first co-respondent by election)

CHIEF EXECUTIVE, DEPARTMENT OF ENVIRONMENT AND HERITAGE PROTECTION

(second co-respondent by election)

AND

ASSUNTA HEAD, SCOTT HEAD, DAWN E KLIBBE, BRIAN J RASMUSSEN, GARY STURDY, CLIFF SOUTHERLAND, ALAN B THOMSETT, KEVIN W WEST, ELIZABETH A WEST & VANESSA HEAD

(third co-respondents by election)

FILE NO:

P&E No. 975/11

PROCEEDING:

Appeal

ORIGINATING COURT:

Brisbane

DELIVERED ON:

21 August 2015

DELIVERED AT:

Brisbane

HEARING DATE:

On the papers (submissions filed 30 July 2015 and 11 August 2015)

JUDGE:

Dorney QC DCJ

ORDER:

1.       That there be no order as to costs of the Appeal.

CATCHWORDS:

Costs – whether exception to each party paying its own costs established

LEGISLATION CITED:

Integrated Planning Act 1997, s 4.1.23(1), s 4.1.23(2), s 4.1.23(2)(b)

Sustainable Planning Act 2009, s 819, s 820, s 821

CASES CITED:

Australian Conservation Foundation Gold Coast Inc. v Gold Coast City Council [1997] QPELR 84

Mackay Resource Developments Pty Ltd v Mackay Regional Council & Ors [2013] QPEC 57

Mudie v Gatton Shire Council & Anor [2002] QPEC 30

Oceanic Sun Line Special Shipping Co. Inc. v Fay (1988) 165 CLR 197

Wheldon v Beaudesert Shire Council & Anor [1995] QPLR 177

COUNSEL:

A N Skoien for the respondent

J G Lyons for the first co-respondent by election

SELF

REPRESENTATIVES:

T R Simpkin (on behalf of the appellant)

K W West (on behalf of the third co-respondent by election)

SOLICITORS:

S.B. Wright & Wright & Condie for the respondent

Norton Rose Fulbright for the first co-respondent by election

Introduction

  1. On 23 July 2015 I made orders in accordance with a draft that I amended, initialled and placed on the file, such orders including leave for any party to this proceeding to file, and serve, submissions on costs.

  1. On 30 July 2015 the appellant filed its submissions. Because of problems faced by the respondent in obtaining relevant material from the original hearing (which was not the subject of any consideration by me), it filed its submissions on 11 August 2015. No other party has chosen to file any submissions on costs.

Concern

  1. The concern that I had about the issue of costs was primarily – although the appeal itself and my subsequent consideration of relevant conditions were brought, and heard, pursuant to the Integrated Planning Act 1997 (“IPA”) [but which for other purposes was repealed on 18 December 2009 by the Sustainable Planning Act 2009 (“SPA”)] – as to whether the IPA applied exclusively to the issue of costs or whether costs were an exception: by reason of the effect of the transitional provisions of the SPA applying the IPA here (see ss 819 to 821 of the SPA) or the effect of the amending Act in…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Mackay Resource Developments Pty Ltd v Mackay Regional Counc... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] QPEC 39
Decision Date

CaseChat Overview and Summary

Mackay Resource Developments Pty Ltd, the appellant, challenged a decision made by the Mackay Regional Council, the respondent, in relation to a development application. The case reached the Queensland Court of Appeal, where the central issue was whether the appellant was entitled to an exception from the usual rule that each party bears its own costs. The appellant argued that the respondent's handling of the development application process was unreasonable, and thus warranted a costs order in its favour. The court had to determine if the respondent's conduct was so unreasonable as to justify a departure from the general principle of each party bearing their own costs.

The court assessed the circumstances under which an exception to the usual costs order might be granted. It considered the conduct of the parties during the proceedings, particularly the respondent's handling of the development application and the subsequent litigation. The court found that while the respondent's actions were not entirely without fault, they did not reach the level of unreasonableness necessary to warrant a costs order against the respondent. The court emphasised that the imposition of costs against a party should be a measure of last resort, reserved for cases where the opposing party's conduct is egregious.

Consequently, the court held that the appellant was not entitled to an exception from the usual rule of each party bearing its own costs. The appeal was dismissed, and as a result, no order was made regarding the costs of the appeal. The decision underscores the importance of the principle that each party bears its own costs, except in cases of exceptional circumstances where the conduct of the opposing party is clearly unreasonable and warrants a departure from this rule.

Orders

Orders of the court

1. That there be no order as to costs of the Appeal.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.