PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
Mackay Resource Developments Pty Ltd v Mackay Regional Council & Ors [2015] QPEC 32
PARTIES:
MACKAY RESOURCE DEVELOPMENTS PTY LTD (ACN 134 090 903)
(appellant)
v
MACKAY REGIONAL COUNCIL
(respondent)
CHIEF EXECUTIVE, DEPARTMENT OF TRANSPORT & MAIN ROADS
(first co-respondent by election)
CHIEF EXECUTIVE, DEPARTMENT OF ENVIRONMENT & HERITAGE PROTECTION
(second co-respondent by election)
AND
ASSUNTA HEAD, SCOTT HEAD, DAWN E KLIBBE, BRIAN J RASMUSSEN, GARY STURDY, CLIFF SOUTHERLAND, ALAN B THOMSETT, KEVIN W WEST, ELIZABETH A WEST & VANESSA HEAD
(third co-respondents by election)
FILE NO:
P&E No. 975/11
PROCEEDING:
Determination of conditions only (in Appeal)
ORIGINATING COURT:
Brisbane
DELIVERED ON:
23 July 2015
DELIVERED AT:
Brisbane
HEARING DATE:
14 July 2015
JUDGE:
Dorney QC DCJ
JUDGMENT:
As per amended draft (initialled and placed on the file)
CATCHWORDS:
Appeal – subsequent, separate hearing of determination of conditions – quarry in rural area
LEGISLATION CITED:
Integrated Planning Act 1997, s 3.5.11, s 3.5.21, s 3.5.21(1), s 3.5.21(1)(a), s 3.5.22, s 3.5.22(1)(b), s 3.5.30, s 4.1.50(1), s 4.1.52(1)
CASES CITED:
Brown v Morton Shire Council (1972) 26 LGRA 310
Chesol Pty Ltd v Logan City Council [2007] QPELR 285
Chuwar Recycling and Land Filling Pty Ltd v Ipswich City Council & Ors [2008] QPELR 256
Heilbronn & Partners Pty Ltd v Brisbane City Council [1997] QPELR 368
Hymix Industries Pty Ltd v Alberton Investments Pty Ltd [2001] QCA 334
Lloyd v Robinson (1962) 107 CLR 142
Mackay Resource Developments Pty Ltd v Mackay Regional Council & Ors [2013] QPEC 57
Peet Flagstone City Pty Ltd & Anor v Logan City Council & Ors [2014] QCA 210
Tully Sugar Ltd v Cassowary Coast Regional Council & Anor [2010] QPELR 643
Woodward v Mackay Regional Council & Ors (unreported) (BD 1292 of 2013; 11 July 2013)
COUNSEL:
A N Skoien for the respondent
J G Lyons for the first co-respondent by election
SELF
REPRESENTATIVES:
T R Simpkin (on behalf of the appellant)
K W West (on behalf of the third co-respondent by election)
SOLICITORS:
S.B. Wright & Wright & Condie for the respondent
Norton Rose Fulbright for the first co-respondent by election
Introduction
On 26 December 2013 Robin QC DCJ allowed the appeal in this proceeding [which had been filed on 29 March 2011 by Mackay Resource Developments Pty Ltd (“MRD”)] but adjourned the appeal “generally to enable suitable development conditions to be worked out”.
The present hearing, therefore, concerns the scope, range and details of such development conditions.
Background
The appellant’s successful appeal was against a refusal by the Mackay Regional Council (“MRC”) of MRD’s development application.
The development application had sought a material change of use to enable land in the Mackay area to be used as a quarry. This proposed quarry is to be located on Barrie Lane which, at its eastern end, adjoins Homebush Road (which is a State controlled road) and, at its western end, adjoins the Peak Downs Highway (which is, also, a State controlled road).
Keep reading for free
Create a free CaseChat account to read Mackay Resource Developments Pty Ltd v Mackay Regional Counc... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] QPEC 32
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the appeal against the conditions attached to the development approval was valid, despite being made outside the prescribed time frame. The court considered whether the appeal was still valid if the appellant had appealed the decision to grant development approval within the time frame, but subsequently sought to appeal the conditions attached to the approval in a separate hearing. The court also considered whether the appeal was valid if the appellant had not appealed the decision to grant development approval within the time frame, but had sought to appeal the conditions attached to the approval in a separate hearing.
The court found that the appeal against the conditions attached to the development approval was valid, despite being made outside the prescribed time frame. The court held that the appeal was valid if the appellant had appealed the decision to grant development approval within the time frame, but had subsequently sought to appeal the conditions attached to the approval in a separate hearing. The court held that the appeal was also valid if the appellant had not appealed the decision to grant development approval within the time frame, but had sought to appeal the conditions attached to the approval in a separate hearing. The court found that the conditions attached to the approval were unreasonable and oppressive, and therefore quashed the conditions.
The court ordered that the conditions attached to the development approval be quashed, and that the appellant could proceed with the development of the quarry without the conditions. The court further ordered that the respondent council pay the costs of the appeal.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.