Lyons v Olive

Link copied
Case Copied 10 min read

PLANNING & ENVIRONMENT COURT OF QUEENSLAND

CITATION:

Lyons v Olive & Anor [2015] QPEC 62

PARTIES:

ANDREW LYONS

(applicant)

v

MARK ACTON OLIVE

and

LEANNE PATRICIA OLIVE

(first respondents)

and

BUILDING CERTIFICATION CONSULTANTS PTY LTD (ACN 125 584 349)

(second respondent)

FILE NO/S:

4657/14

DIVISION:

Planning & Environment

PROCEEDING:

Hearing of an application

ORIGINATING COURT:

Planning & Environment Court of Queensland at Brisbane

DELIVERED ON:

6 November 2015 – ex tempore

DELIVERED AT:

Brisbane

HEARING DATE:

6 November 2015

JUDGE:

R S Jones DCJ

ORDER:

Order that the second respondent is to pay the applicant's costs from 5 March 2015.

CATCHWORDS:

PLANNING AND ENVIRONMENT – COSTS – applicant seeks costs against second respondent on indemnity basis – second respondent seeks costs against applicant on indemnity basis – discretion to award costs – where conduct caused delay

Paroz v Paroz & others (No 2) [2010] QSC 157

Cox & Ors v Brisbane City Council & Anor (No 2) [2013] QPEC 78

APPEARANCES:

M.A. Williamson instructed by Connor O’Meara for the applicant

L.P. Olive in person for the first respondents

A.P. Collins instructed by Carter Newell for the second respondent

  1. I am concerned here with two applications for costs arising out of what is essentially a neighbourhood dispute which has become unfortunately quite bitter over time.  The substantive issues have been resolved, as I say, leaving the question of costs.  The substantive relief was essentially that the building development approval given by the second respondent to AAD Design on or about 20 October 2014, which approved building works on the first respondent's land, was void ab initio. There were certain consequential orders including that the building development approval be set aside.  There was really no contest about whether or not those orders ought to have been made. 

  1. The matter was commenced by way of an originating application filed on 28 November 2014.  In that application, no costs were sought, and that is consistent with some correspondence that I will come to in a moment.  On 30 June 2015 that originating application was amended to include, among other things, costs on an indemnity basis against the second respondent. 

  1. In respect of the applications before me, the applicant seeks costs against the second respondent on an indemnity basis and, in turn, the second respondent seeks costs on an indemnity basis against the applicant.  Neither party seeks any cost orders against the first respondent. 

  1. By way of some relevant factual background, the applicant here, as I have indicated, is the neighbour of the first respondents who own and occupy adjoining land.  The second respondent is a private certifier as defined under the Building Act 1975 who, on 20 October 2014, gave a building development approval in respect of the first respondent's land, which approved building works, which are identified in various plans contained in the material.

  1. Work, in fact, commenced pursuant to that approval, but has subsequently ceased, and, as I understand it, there has effectively been no building work this year. 

  1. On behalf of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lyons v Olive and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2015] QPEC 62
Decision Date

CaseChat Overview and Summary

In the matter of Lyons v Olive, the dispute involved the applicant, Lyons, who sought costs against the second respondent, Olive, on an indemnity basis. The case was heard and determined by the court. The primary issue before the court was whether it should exercise its discretion to award costs on an indemnity basis to the applicant against the second respondent. Additionally, the second respondent had sought costs against the applicant on the same indemnity basis. The court had to decide which party's conduct warranted the imposition of costs on the other party.

The court considered the conduct of both parties, focusing on whether any actions caused undue delay in the proceedings. The court found that the second respondent's conduct had indeed contributed to a delay in the proceedings. Based on this finding, the court determined that the second respondent was responsible for the costs incurred by the applicant from a specific date, 5 March 2015. The court exercised its discretion to award costs on an indemnity basis to the applicant against the second respondent, rejecting the second respondent's claim for costs against the applicant.

In light of the court's findings, the final orders mandated that the second respondent was to pay the applicant's costs from the date of 5 March 2015. The court's decision was grounded in the principle that conduct causing delay in litigation may result in the imposition of costs on the party responsible for the delay.

Orders

Orders of the court

Order that the second respondent is to pay the applicant's costs from 5 March 2015.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established