CITATION: Sweeney v Magnay [2011] QCAT 648
PARTIES: Luke Sweeney t/as Luke Sweeney Constructions v Ms Sarah Magnay
APPLICATION NUMBER: BD488-06
MATTER TYPE: Building matters
HEARING DATE: 25, 26, 27, 28 August 2009, 19, 20, 21, 22, 23 October 2009 and 3, 4 December 2009
HEARD AT: Brisbane
DECISION OF: Mr Paul Favell, Member
DELIVERED ON: 25 February 2011
DELIVERED AT: Brisbane
ORDERS MADE: The Tribunal orders that the Applicant pay the Respondent the sum of $126,869.86 by 4pm on 28 March 2011.
CATCHWORDS: Domestic Building Contract – minor works contract – renovation – incorrect level of slab – scope of works – defects – variation
Domestic Building Contracts Act 2000, ss 17A, 26, 29(2)(a), 72(2), 79, 82, 83, 84(4), 90
Notley, Bl v QBSA and Harvey [2005] QCCTB 100
Gary Norwood Homes Pty Ltd v QBSA (unreported, Bne DC, 20/6/97)
Collyer v QBSA [1998] QBT 71
Ross v Rangel [2004] QCCTB 98 (28 May 2004)
Rukat v Rukat [1975] 1 All ER 343
O’Brien (FG) UD v Elliott [1965] NSWR 1437
LIDA Build Pty Ltd v Miller (No 2) [2010] QCAT 431
Black, G. D Toowoomba Resort Pty Ltd [2007] QCCTB 122 (3 September 2007)APPEARANCES and REPRESENTATION (if any):
APPLICANT: R G Poiner of Counsel for the Applicant RESPONDENT: S B Whitten of Counsel for the Respondent, instructed by Mills Oakley REASONS FOR DECISION
Introduction
[1]The Applicant, Luke Sweeney t/as Luke Sweeney Constructions, and the Respondent, Sarah Magnay, executed a contract on 20 September 2005 concerning work at 12 Reid Street, Windsor to demolish the lower level of the house and then re-build it completely with new rooms and a set of internal stairs for $79,000.00.
[2]A second contract executed on 23 October 2005 was for work to demolish the carport attached to the existing house and then build a new carport in a different location for $31,000.00.
[3]Works on the first contract proceeded until December 2005. The Applicant contends that as at 23 December 2005 the contract was practically at completion save for minor works that could not be completed before the Respondent completed the proposed retaining wall. Accordingly he claimed the last payment. The Respondent refused to pay and the Applicant then discontinued with the works. The second contract was never commenced.
Factual Background and Claims
[4]The Applicant is a licensed builder. The Respondent has no particular expertise in construction and her husband, Graham Magnay, has limited expertise in construction having worked as a sub-contract painter.
[5]The Applicant met with the Respondent and her husband in or about May 2005. The Applicant was taken through a “walk through” of the house and was provided with the architectural plans.
[6]The Applicant provided the Respondent with quote number 341 dated 27 July 2005 for the proposed floor extension. The Applicant provided a separate quote for the carport, number 342, dated 27 July 2005.
[7]The parties executed two separate contracts for the lower level house works and carport works on 20 September and 23 October 2005 respectively.
[8]The…
Keep reading for free
Create a free CaseChat account to read Luke Sweeney t/as Luke Sweeney Constructions v Sarah Magnay and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QCAT 648
- Decision Date
CaseChat Overview and Summary
The legal issues primarily revolved around the interpretation of the contract and whether the Applicant had deviated from the agreed scope of works, resulting in additional charges. The Respondent argued that the slab level was incorrectly set, which led to further issues with the renovations, and that the Applicant had not adhered to the contract's terms. The Applicant, on the other hand, contended that the Respondent had approved the works and that any additional costs were due to her requests for variations.
The Tribunal found that the Applicant had indeed deviated from the agreed scope of works, resulting in additional costs that were not justified. It was determined that the slab level was incorrectly set, and the Respondent had not approved these changes. Additionally, the Tribunal ruled that the Applicant had not kept proper records, which further complicated the assessment of the dispute. Consequently, the Tribunal ordered that the Applicant reimburse the Respondent the sum of $126,869.86 by a specified date.
Orders
Orders of the court
The Tribunal orders that the Applicant pay the Respondent the sum of $126,869.86 by 4pm on 28 March 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi