Lockyer Valley Regional Council v Macandrews Industries Pty Ltd

Link copied
Case Copied 6 min read

PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND


CITATION:

Lockyer Valley Regional Council v Macandrews Industries Pty Ltd & Ors [2019] QPEC 38

PARTIES:

LOCKYER VALLEY REGIONAL COUNCIL
(Applicant)

v

MACANDREWS INDUSTRIES PTY LTD AND ORS
(Respondent)

And

LEAH-LARAINE MACANDREWS
(Respondent)

And

RICK BRENTON MACANDREWS
(Respondent)

FILE NO:

1330/19

DIVISION:

Planning and Environment Court

PROCEEDING:

Application

ORIGINATING COURT:

Planning and Environment Court of Queensland, Brisbane

DELIVERED ON:

17 July 2019, delivered ex tempore

DELIVERED AT:

Brisbane

HEARING DATE:

17 July 2019

JUDGE:

Everson DCJ

ORDER:

1.   Application to strike out dismissed

2.   Order that originating application be amended to reflect the Applicant’s draft

CATCHWORDS:

PLANNING AND ENVIRONMENT – APPLICATION – application to strike out originating application, or parts thereof – application to amend originating application – whether applicant is permitted under new legislative regime to seek declarations concerning alleged development offences on part of respondent

LEGISLATION:

Integrated Planning Act 1997 (Qld)

Planning Act 2016 (Qld)

Planning and Environment Court Act 2016 (Qld)

Sustainable Planning Act 2009 (Qld)

CASES:

Benfer v Sunshine Coast Regional Counsel [2019] QPEC 6

Mac Services Group Limited v Belyando Shire Council [2008] QPELR 503

COUNSEL:

B Rix for the applicant

R Quirk for the respondent

SOLICITORS:

Thomson Geer for the applicant

P & E Law for the respondent

  1. This is an application brought by the respondents seeking orders that the originating application, or parts of it, be struck out.  In response the applicant has sought to amend the originating application.  The amendments sought are not opposed. 

  1. The essence of the respondent’s contention is that the applicant is not permitted under the legislative regime which now applies in Queensland to seek declarations pursuant to section 11 of the Planning and Environment Court Act 2016 (“PECA”) concerning alleged development offences on the part of the respondents. The general declaratory jurisdiction is, inter alia, in the following terms:

“(1) Any person may start a P&E Court proceeding seeking a declaration (a declaratory proceeding) about:

(a) a matter done, to be done or that should have been for this Act or the Planning Act; or

...

(c) the lawfulness of land use or development under the Planning Act;

...

(4) the P&E Court may also make an order about any declaration it makes.”

  1. The ambit of this provision is clarified by section 346 of the Planning Act 2016 (“PA”):

“This section applies if –

(1)

(a) before the old Act was repealed, a proceeding could have been brought under the old Act, section 456 about a matter under the old Act that arose before the repeal; and

(b)     immediately before the repeal, the proceeding had not been started. 

…

(3) it is declared that … a person has a right and always had a right, to bring the proceeding about the matter under the P&E Court Act, part 2 division 3.”

  1. The reference in s 346(1)(a) is to section 456 of the Sustainable Planning Act 2009 (“SPA”), which is for present purposes, essentially the same…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lockyer Valley Regional Council v Macandrews Industries Pty... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] QPEC 38
Decision Date

CaseChat Overview and Summary

Lockyer Valley Regional Council sought a declaration from the Queensland Land Court that Macandrews Industries Pty Ltd had committed offences under the Planning Act 2016 (Qld) by carrying out development without approval. Macandrews Industries Pty Ltd filed an application to strike out the originating application or parts thereof, and an application to amend the originating application to reflect the applicant's draft. The court had to decide whether the applicant was permitted under the new legislative regime to seek declarations concerning alleged development offences on the part of the respondent.

The court found that the applicant's power to apply to the court for a declaration concerning an alleged development offence was preserved under the new legislative regime. The court noted that the new regime did not remove or restrict the applicant's power to seek declarations concerning alleged development offences, and that such declarations were necessary to ensure compliance with planning laws. The court rejected the respondent's argument that the applicant's application was an abuse of process, and held that the applicant had a legitimate interest in ensuring that the respondent complied with planning laws.

The court dismissed the application to strike out and ordered that the originating application be amended to reflect the applicant's draft. The court found that the applicant's draft was a reasonable reflection of the relief sought in the originating application, and that the respondent would not be prejudiced by the amendment. The court held that the amendment was necessary to ensure that the applicant's application was clear and concise, and that the respondent was aware of the relief sought.

Orders

Orders of the court

1. Application to strike out dismissed

2. Order that originating application be amended to reflect the Applicant’s draft

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established