CITATION: Lineablu Pty Ltd v St George Sailing Club Ltd [2004] NSWSC 1199
HEARING DATE(S): 3 December, 2004
JUDGMENT DATE:
3 December 2004
JURISDICTION:
Equity Division
JUDGMENT OF: Palmer J
DECISION: Interlocutory injunction continued.
CATCHWORDS: INTERLOCUTORY INJUNCTION - Defendant seeks to eject from its premises operator of restaurant business on ground that operator has committed breach of agreement - whether serious question to be tried - balance of convenience - whether damages adequate - other discretionary factors - no question of principle.
CASES CITED: London & Blackwall Railway Company v Cross (1885) 31 ChD 354

PARTIES :

Lineablu Pty Ltd - Plaintiff
St George Sailing Club Ltd - Defendant
FILE NUMBER(S): SC 6169/04
COUNSEL: A.R.R. Vincent - Plaintiff
G. Inatey SC, P. Mansfield
SOLICITORS: Costa & Associates - Plaintiff
Diamond Peisah - Defendant

      JUDGMENT – Ex tempore

      1    On 3 December 2004, Bergin J granted an interlocutory injunction restraining the Defendant from denying access or occupation to the Plaintiff of premises at Sans Souci owned by the Defendant. The injunction was continued up until today. Mr Vincent now appears on behalf of the Plaintiff. Mr Inatey SC and Mr Mansfield of Counsel appear on behalf of the Defendant. The Defendant resists the continuation of the injunction. The Plaintiff seeks the continuation of the injunction until further order. The circumstances giving rise to the application may be summarised thus. 2    The Defendant operates a sailing club at the premises. By an agreement dated 9 May 2002 between the Defendant and the Plaintiff, the Defendant agreed to licence certain restaurant and catering premises and facilities within the club to the Plaintiff upon certain terms. 3    An option to extend the catering agreement was exercised in mid-2002 and at present the agreement, if it still is on foot, has another three years or so to run. The Defendant has purported to terminate the agreement for alleged breaches of its terms by the Plaintiff. The notice of termination was given on or about 15 November 2004 and on that day the Defendant re-took possession of those parts of the club premises which had been occupied by the Plaintiff. 4    The Plaintiff denies that it is in breach of the catering agreement and says that the purported termination is invalid. 5    The Plaintiff, as I have noted, approached the Court on 17 November 2004 and obtained an injunction which, in effect, let the Plaintiff back into occupation of the premises pursuant to an order limited in its effect up until and including today. 6    The first issue raised is whether an injunction should be continued, having regard to what the Defendant says is the unsatisfactory financial position of the Plaintiff. The Defendant says that there is a serious doubt whether the usual undertaking as to damages, if given by the Plaintiff, would be worth anything at all. 7    The second issue is whether, on the evidence adduced by the Plaintiff and in the light of the terms of the catering agreement, there is a serious…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lineablu Pty Ltd v St George Sailing Club Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2004] NSWSC 1199
Decision Date

CaseChat Overview and Summary

The case of Lineablu Pty Ltd v St George Sailing Club Ltd involved a dispute between the plaintiff, Lineablu Pty Ltd, and the defendant, St George Sailing Club Ltd. Lineablu Pty Ltd operated a restaurant on the premises of St George Sailing Club Ltd, but the latter sought to eject the former on the basis that Lineablu Pty Ltd had breached their agreement. Lineablu Pty Ltd sought an interlocutory injunction to prevent the defendant from ejecting them until the substantive proceedings were resolved. The matter was heard in the Supreme Court of New South Wales.

The central legal issue before the court was whether Lineablu Pty Ltd had demonstrated a serious question to be tried in the substantive proceedings and whether the balance of convenience favoured granting the injunction. Additionally, the court needed to consider whether damages would be an adequate remedy for Lineablu Pty Ltd if the injunction was not granted, as well as other discretionary factors relevant to the grant of an interlocutory injunction.

The court found that Lineablu Pty Ltd had raised a serious question to be tried regarding their alleged breach of the agreement and the validity of the defendant's right to eject them. The court also determined that the balance of convenience favoured granting the injunction, as the harm to Lineablu Pty Ltd if the restaurant were to be ejected outweighed any harm to St George Sailing Club Ltd if the injunction were granted. Furthermore, the court held that damages would not be an adequate remedy for Lineablu Pty Ltd in the event the injunction was not granted. Considering these factors, the court granted the interlocutory injunction, preventing St George Sailing Club Ltd from ejecting Lineablu Pty Ltd until the substantive proceedings were resolved.

The court's final orders were that an interlocutory injunction be granted to Lineablu Pty Ltd, restraining St George Sailing Club Ltd from ejecting Lineablu Pty Ltd from the premises until the substantive proceedings were resolved.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established