26 July 2013 GOVERNMENT GAZETTE, WA 3451
Western Australia
Licensed Surveyors (Guidance of Surveyors)
Amendment Regulations 2013
Contents
1. Citation
2. Commencement
3. Regulations amended
4. Heading replaced
Part 1 — Preliminary matters
5. Regulation 1 amended
6. Regulation 3 amended
7. Part 2 heading inserted
Part 2 — General duties of surveyors
8. Regulation 4 amended
9. Regulation 5 amended
10. Regulation 6 replaced
6. Knowledge of relevant legislation 11. Regulation 7 amended
12. Heading replaced
Part 3 — Field records
13. Regulation 8 amended
14. Regulations 9 to 11 replaced
9. Distances 15. Regulation 12 amended
16. Regulations 13 to 15 deleted
17. Regulation 17 replaced
17. Certification of field record 18. Heading replaced
Part 4 — Field work
19. Regulation 20 amended
3452 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
Contents
20. Regulation 22 amended
21. Regulations 23 and 24 replaced
23. Remarking connecting boundary between
old and new surveys22. Regulation 24A amended
23. Regulation 25 amended
24. Regulation 25A amended
25. Regulation 26 amended
26. Regulations 27 to 33 replaced
27. Azimuth 28. Old surveys: adjustment of distances 29. Old surveys: adjustment of angles 27. Regulation 34 amended
28. Regulations 35 and 35A replaced
35. Distribution of miscloses 35A. Calculation of areas 29. Heading replaced
Part 5 — Survey marks
Division 1 — Marking boundaries generally30. Regulation 36 amended
31. Regulation 37 replaced
37. Placement of reference marks 32. Regulation 38 amended
33. Regulation 39 amended
34. Regulation 40A inserted
40A. Streets, rights-of-way, pedestrian access
ways, drainage reserves and railways:
additional requirements35. Regulation 40 amended
36. Regulation 41 amended
37. Regulation 42 amended
38. Regulations 43 and 44 deleted
39. Heading deleted
40. Regulations 45 and 46 deleted
41. Heading replaced
Division 2 — Marking lease boundaries
42. Regulation 47 amended
43. Heading replaced
Division 3 — Other matters relating to marking
44. Regulations 48 to 53 replaced
48. Positioning of marks
26 July 2013 GOVERNMENT GAZETTE, WA 3453 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
Contents
49. Methods of marking
50. Line clearing
51. Damage to survey marks
45. Regulation 53A amended
46. Heading replaced
Part 6 — Drafting
47. Regulation 54 amended
48. Heading replaced
Part 7 — Surveys of land in special survey areas
49. Regulation 55A replaced
55A. Application of this Part 55BA. Early lodgment for dealings 55BB. Standard requirements for survey 50. Regulation 55B amended
51. Regulation 55C amended
52. Regulation 55E amended
53. Regulation 55F amended
54. Part 8 heading inserted
Part 8 — Miscellaneous matters
55. Regulation 56 replaced
56. Grounds for disciplinary action
26 July 2013 GOVERNMENT GAZETTE, WA 3455
Licensed Surveyors Act 1909
Licensed Surveyors (Guidance of Surveyors)
Amendment Regulations 2013
Made by the Land Surveyors Licensing Board with the approval of the
Governor in Executive Council.1. Citation
These regulations are the Licensed Surveyors (Guidance of
Surveyors) Amendment Regulations 2013.
2. Commencement
These regulations come into operation as follows —
(a) regulations 1 and 2 — on the day on which these regulations are published in the Gazette;
(b) the rest of the regulations — on 1 October 2013.
3. Regulations amended
These regulations amend the Licensed Surveyors (Guidance of
Surveyors) Regulations 1961.
4. Heading replaced
Before regulation 1 delete the heading “General” and insert:
Part 1 — Preliminary matters
3456 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 5
5. Regulation 1 amended
In regulation 1 delete “(Guidance of Surveyors)” and insert:
(General Surveying Practice)
6. Regulation 3 amended
In regulation 3 insert in alphabetical order:
field record, in relation to a survey, means the field
record of the survey;
lodge means to lodge with the Western Australian
Land Information Authority;
7. Part 2 heading inserted
After regulation 3 insert:
Part 2 — General duties of surveyors
8. Regulation 4 amended
In regulation 4(1):
(a) in paragraph (a) delete “his or her” and insert: the surveyor’s
26 July 2013 GOVERNMENT GAZETTE, WA 3457 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 9
(b) in paragraph (b) delete “difficulties; and” and insert: difficulties as soon as practicable after discovering them;
and(c) in paragraph (c) delete “him or her” (first occurrence) and insert:
the surveyor
(d) in paragraph (c) delete “him or her.” and insert: the surveyor.
9. Regulation 5 amended
In regulation 5:
(a) delete “The” and insert: (1) The
(b) delete “In” and insert: (2) In
(c) delete the passage that begins with “If,” and continues to the end of the regulation and insert:
(3) If it is found that —
(a) a surveyor’s work is not up to the standard of accuracy that is required under a written law or
is otherwise necessary; or
3458 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 10
(b) a surveyor’s work is generally unreliable; or (c) a surveyor has in other respects neglected to comply with these regulations, the finding may be taken into account in determining whether there is proper cause for disciplinary action under section 21 of the Act in respect of the surveyor.
10. Regulation 6 replaced
Delete regulation 6 and insert:
6. Knowledge of relevant legislation
A surveyor conducting authorised surveys under these
regulations should be conversant with the provisions of
all written laws a knowledge of which is necessary toenable the efficient discharge the surveyor’s duties.
11. Regulation 7 amended
In regulation 7 delete “show” and insert:
demonstrate to the Surveyor General
12. Heading replaced
Before regulation 8 delete the heading “Field notes” and insert:
Part 3 — Field records
26 July 2013 GOVERNMENT GAZETTE, WA 3459 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 13
13. Regulation 8 amended
(1) Delete regulation 8(1) and insert:
(1) A surveyor must keep a field record for each authorised
survey conducted by the surveyor.(2A)
The field record for an authorised survey must be kept in such a manner that another surveyor would readily gain from the record a complete understanding of the methodology and scope of the survey, including the
marks used. (2B)
The field record for an authorised survey must show everything that was done, or found on the ground, in the course of the survey.
(2C) The field record for an authorised survey that
establishes one or more boundaries must be lodged
with the plan of the authorised survey.(2) In regulation 8(2) and (3) delete “field book” and insert: field record (3) After regulation 8(3) insert:
(4) The Board may request a surveyor to give to the Board
a copy of the field record for an authorised survey
conducted by the surveyor.(5) A surveyor must comply with a request made under
subregulation (4).
3460 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 14
Note: The heading to amended regulation 8 is to read: Keeping and lodging field records for authorised surveys
14. Regulations 9 to 11 replaced
Delete regulations 9 to 11 and insert:
9. Distances
(1) Distances must be recorded as observed and reduced to
a precision of at least 0.005 metres.(2) Referencing distances and offset distances must be
recorded with the highest precision practicable.(3) The reference surface of each distance must be stated.
15. Regulation 12 amended
In regulation 12 delete “him” and insert:
the surveyor
16. Regulations 13 to 15 deleted
Delete regulations 13 to 15.
17. Regulation 17 replaced
Delete regulation 17 and insert:
17. Certification of field record
(1) The surveyor who carried out an authorised survey
must certify, in the form set out in the Table, the field
record.
26 July 2013 GOVERNMENT GAZETTE, WA 3461 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 18
Table
Certificate
I, …………………………, licensed surveyor, certify
that I accept full responsibility for this field record and the authorised survey it represents and certify that both comply with the relevant written laws in relation to
which the survey was carried out and this field record is
lodged.
………………………………
Name:
Dated: .………………………
(2) Each page of the field record on which notes about the survey appear —
(a) must be initialled by the surveyor; and (b) must bear the date on which the field work recorded on that page of the field record was carried out.
18. Heading replaced
Before regulation 20 delete the heading “Field work” and
insert:
Part 4 — Field work
19. Regulation 20 amended
In regulation 20(1) after “intervals” insert:
(not exceeding 2 years)
3462 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 20
20. Regulation 22 amended
In regulation 22:
(a) delete “Each” and insert: (1) Each
(b) delete “In” and insert: (2) In
(c) delete “the reference marks” and insert: reliable reference marks
21. Regulations 23 and 24 replaced
Delete regulations 23 and 24 and insert:
23. Remarking connecting boundary between old and new surveys
(1) This regulation applies if a surveyor is required under
regulation 22 to connect a new survey to an old survey.(2) In this regulation — connecting boundary, in relation to a new survey,
means the boundary connecting the new survey to an
old survey.(3) The surveyor must range sufficient of the connecting
boundary to verify its alignment.
26 July 2013 GOVERNMENT GAZETTE, WA 3463 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 22
(4) For the purposes of subregulation (3), it is sufficient if the surveyor uses —
(a) 3 reliable, reasonably spaced marks; or (b)
fewer such marks as approved by the Surveyor General.
(5) For the purposes of subregulation (3) —
(a) all portions of any old survey line must be carefully measured; and (b) if the land being surveyed is rural land and the measurements taken in accordance with paragraph (a) are found to be in disagreement with the measurements previously accepted in relation to the old survey line by an average of more than 1:4000 — the old survey line must
be carefully remeasured and the results of the
remeasure must be recorded in the field record.
(6) The surveyor must, as necessary —
(a) replace the posts and pegs used in the old survey to mark the connecting boundary; and (b) clearly indicate the direction of the connecting boundary. 22. Regulation 24A amended
In regulation 24A delete “his or her survey,” and insert:
a survey,
3464 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 23
23. Regulation 25 amended
In regulation 25:
(a) delete “When” and insert: (1) When
(b) delete “them;” and insert: them.
(c) delete “but” and insert: (2) However,
(d) delete “the surveyor shall forward a full report and a sketch” and insert:
the surveyor must, within 3 months after completing the
new survey, forward to the Surveyor General a full
report, sketch and field record(e) delete “Where” and insert: (3) Where
(f) delete “The” and insert: (4) The
26 July 2013 GOVERNMENT GAZETTE, WA 3465 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 24
(g) delete “field book and a full report thereon must be made to the Surveyor General.” and insert:
field record and a full report on the positions of those
marks must be forwarded to the Surveyor General
within 3 months after completion of the new survey.
Note: The heading to amended regulation 25 is to read: Re-establishment of original Crown surveys 24. Regulation 25A amended
In regulation 25A(1) in the Table delete “the provisions of the
Licensed Surveyors (Guidance of Surveyors) Regulations 1961
and the Licensed Surveyors (Transfer of Land Act 1893)
Regulations 1961.” and insert:
all relevant written laws.
25. Regulation 26 amended
(1) In regulation 26:
(a) delete “(a) All” and insert: (1) All
(b) delete the passage that begins with “Boundaries” and ends with “guideline.” and insert:
(2) Boundaries with calculated distances must be cleared
and marked in accordance with these regulations.
3466 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 26
(2) In regulation 26 delete “(b) Where” and insert: (3) Where 26. Regulations 27 to 33 replaced
Delete regulations 27 to 33 and insert:
27. Azimuth
(1) The direction of a survey line with reference to the meridian must be determined — (a) by observation; or
(b)
by applying the correction for convergence from the nearest point of observation for azimuth.
(2) An azimuth may be adopted from an adjoining survey
unless there appears to be a reason to doubt its
accuracy.(3) The derivation of azimuth must be obtained at intervals
of not more than 8 kilometres.28. Old surveys: adjustment of distances
If an old survey line is being re-established, this
information must be recorded in the field record —
(a)
the actual distance measurements taken in the survey for that purpose;
(b) the distance measurements previously accepted.
26 July 2013 GOVERNMENT GAZETTE, WA 3467 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 27
29. Old surveys: adjustment of angles
If an old survey line is being re-established, this
information must be recorded in the field record —
(a) the actual measurement of the value of each angle taken in the survey for that purpose; (b) the value of each angle previously accepted.
27. Regulation 34 amended
In regulation 34:
(a) delete the passage that begins with “The normal limits” and ends with “report.”;
(b) delete “field book” and insert: field record
28. Regulations 35 and 35A replaced
Delete regulations 35 and 35A and insert:
35. Distribution of miscloses
An angular or linear misclose must be adjusted
according to a mathematically sound process that is
generally accepted as good survey practice.35A. Calculation of areas The result of calculating an area must be recorded in
the field record —
(a) if the result is less than one hectare — in square metres to the nearest square metre; or
3468 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 29
(b) if the result is equal to or greater than one hectare — in hectares to at least 5 significant
figures and at least 3 decimal points.
29. Heading replaced
Before regulation 36 delete the heading “Marking rural lands
(except feature surveys)” and insert:Part 5 — Survey marks
Division 1 — Marking boundaries generally
30. Regulation 36 amended
(1) Before regulation 36(1) insert: (1A)
The corners and angles of a boundary or land parcel must be marked in accordance with this regulation.
(2) In regulation 36(6) delete “field notes.” and insert: field record. 31. Regulation 37 replaced
Delete regulation 37 and insert:
37. Placement of reference marks
(1) This regulation applies in relation to the survey of a
boundary.
26 July 2013 GOVERNMENT GAZETTE, WA 3469 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 32
(2) Two reference marks must be placed —
(a) if it is the boundary of a land parcel that is greater than 4 hectares — at each angle of the
boundary; or
(b) if it is the boundary of a land parcel that is equal to or less than 4 hectares — at key points
along the boundary; or
(c) if it is another boundary — at each corner and angle of the boundary.
(3) Each of those reference marks must be related by
distance and, if practicable, direction to an alignment.(4) The distance between those reference marks must be
measured, and recorded in the field record, to the
nearest millimetre.(5) A single reference mark (without trenching) must be placed at each instrument point that is not otherwise permanently marked. (6) The objective of the placement of a reference mark is
to ensure its long term stability and accessibility.32. Regulation 38 amended
In regulation 38:
(a) delete “A reference” and insert: (1) A reference
(b) delete “Where” and insert: (2) Where
3470 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 33
(c) delete “A full” and insert: (3) A full
(d) delete “field notes.” and insert: field record.
(e) delete “Marks” and insert: (4) Marks
33. Regulation 39 amended
In regulation 39:
(a) delete “On” and insert: (1) On
(b) delete “Where” and insert: (2) Where
(c) delete “A” and insert: (3) A
(d) delete “field notes.” and insert: field record.
26 July 2013 GOVERNMENT GAZETTE, WA 3471
Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 34
34. Regulation 40A inserted
After regulation 39 insert:
40A. Streets, rights-of-way, pedestrian access ways,
drainage reserves and railways: additional
requirements
(1)
This regulation applies in relation to the survey of a street, right-of-way, pedestrian access way, drainage reserve or railway in addition to regulations 37, 38
and 39. (2) Each corner and angle of the street, right-of-way,
pedestrian access way, drainage reserve or railway
must be marked by a peg or post as specified in
paragraph (b) of the Table to regulation 36 the exposed
portion of which must be coloured red.(3) At any truncated corner of the street, right-of-way, pedestrian access way, drainage reserve or railway —
(a)
the intersection of 2 adjoining alignments must be marked with a single reference mark; and
(b)
2 other reference marks, each being related by angle and distance to those alignments, must be placed in positions so as to minimise the chance of disturbance and to enable the re-establishment of both alignments.
(4) If a corner or angle of the street, right-of-way,
pedestrian access way, drainage reserve or railway is
not intervisible with an adjoining corner or angle, the
intermediate instrument point (being the point from
which both corners or angles are visible) must be
marked by a single reference mark (without trenching)
and the distance to that point from each of those
corners or angles must be recorded in the field record.
3472 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 35
35. Regulation 40 amended
In regulation 40:
(a) delete “If ” and insert: (1) If
(b) delete “Posts” and insert: (2) Posts
36. Regulation 41 amended
In regulation 41:
(a) delete “When” and insert: (1) When
(b) delete “If,” and insert: (2) If,
37. Regulation 42 amended
In regulation 42:
(a) delete “When” and insert: (1) When
26 July 2013 GOVERNMENT GAZETTE, WA 3473 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 38
(b) delete “Where” and insert: (2) Where
(c) delete “he shall” and insert: the surveyor must
38. Regulations 43 and 44 deleted
Delete regulations 43 and 44.
39. Heading deleted
Before regulation 45 delete the heading “Marking of town and
suburban lands”.
40. Regulations 45 and 46 deleted
Delete regulations 45 and 46.
41. Heading replaced
Before regulation 47 delete the heading “Marking pastoral
and timber leases” and insert:Division 2 — Marking lease boundaries
42. Regulation 47 amended
In regulation 47:
(a) delete “The” and insert: (1) The
3474 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 43
(b) delete “rural”; (c) delete “These” and insert: (2) These
(d) delete “Kilometre” and insert: (3) Kilometre
43. Heading replaced
Before regulation 48 delete the heading “Marking generally”
and insert:
Division 3 — Other matters relating to marking
44. Regulations 48 to 53 replaced
Delete regulations 48 to 53 and insert:
48. Positioning of marks
A mark must clearly indicate the position of the
boundary that the mark is intended to indicate.49. Methods of marking
If there are no improvements indicating the direction of
a boundary, the direction must be clearly indicated by
trenches, stakes, stone pointers or other appropriate
marks on the ground.
26 July 2013 GOVERNMENT GAZETTE, WA 3475 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 45
50. Line clearing
(1) Subject to environmental considerations, any new
boundary line must be cleared sufficiently to indicate
the position of the boundary.(2) A boundary line or part of a boundary line that has not been cleared in accordance with subregulation (1) must be shown in the field record as not having been cleared. 51. Damage to survey marks
(1) A person must not remove or deface a survey mark. Penalty: a fine of $1 000. (2) A surveyor must report the removal or defacement of a
survey mark to the Surveyor General as soon as
practicable after becoming aware of it.45. Regulation 53A amended
In regulation 53A delete “or diagram”.
Note: The heading to amended regulation 53A is to read: Certificate required if plan not lodged within 2 years
46. Heading replaced
Before regulation 54 delete the heading “Drafting” and insert:
Part 6 — Drafting
3476 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 47
47. Regulation 54 amended
In regulation 54:
(a) delete “plan or diagram, other than a compiled diagram,” and insert:
plan, other than a compiled plan within the meaning of
the Transfer of Land (Surveys) Regulations 1995
regulation 4(1),(b) in the Table delete “measurements,” and insert: measurements recorded in the field records,
Note: The heading to amended regulation 54 is to read: Certificate on plan
48. Heading replaced
Before regulation 55A delete the heading “Early preparation
of Certificate of Title” and insert:
Part 7 — Surveys of land in special survey areas
49. Regulation 55A replaced
Delete regulation 55A and insert:
55A. Application of this Part This Part applies to a subdivision in a special survey
area declared under regulation 26A(4).
26 July 2013 GOVERNMENT GAZETTE, WA 3477 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 49
55BA. Early lodgment for dealings A plan of survey for a subdivision may be lodged in
order for dealings before completion of field marking if
the survey is in accordance with this Part.55BB. Standard requirements for survey
(1) The subdivision must have adequate connections to the
State geodetic network in accordance with the
guidelines issued by the Surveyor General under
regulation 26A(5).(2)
Sufficient control points must be placed in safe and protected areas so as to survive the engineering and construction works.
(3)
The corners of each lot in the subdivision must be marked prior to the plan of survey being lodged in order for dealings.
(4) Notification to the Western Australian Land
Information Authority can be by lodgment of a
certificate in a form that is the same as, or sufficiently
similar to, the Initial Survey Certificate set out in the
guidelines issued by the Surveyor General under
regulation 26A(5).(5) A certificate lodged under subregulation (4) must state —
(a)
that the marks referred to in subregulation (3) are in place; and
(b)
that final marking will be carried out when the subdivision has been completed.
(6) Final marking must be completed not more than
14 days after the day of practical completion of the
engineering and construction works.
3478 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 50
(7) These documents must be lodged with the Western
Australian Land Information Authority within 14 daysafter the day on which final marking is completed —
(a) the plan of survey for the subdivision; (b) a field record referencing the final marking; (c)
a Final Survey Certificate referred to in regulation 55E.
(8) The plan and the field record must be annotated “Reg. 26A-referencing/final marking deferred”. (9) The surveyor who carried out the survey must take reasonable steps to ensure —
(a) that it is disclosed to purchasers of lots on the plan referred to subregulation (8) that access to the land may not be possible at the date of settlement; and (b) that those purchasers are advised of any changes to the timeframe for practical completion of the engineering and construction works.
50. Regulation 55B amended
In regulation 55B:
(a) delete “Every” and insert: (1) Every
(b) delete “to be examined”; (c) delete “registered field book.” and insert: lodged field record.
26 July 2013 GOVERNMENT GAZETTE, WA 3479 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 51
(d) delete “The control survey network must be marked and measured before examination, and the marks of this”
and insert:
(2) The marks of the
(e) delete “This field book” and insert: (3) The field record
(f) delete “(i) Western” and insert: (a) Western
(g) delete “(ii) re-establishment” and insert: (b) re-establishment
(h) delete “(iii) graphic” and insert: (c) graphic
(i) delete “(iv) connections” and insert:
(d) connections
Note: The heading to amended regulation 55B is to read: Field records for subdivisions in special survey areas
3480 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 51
51. Regulation 55C amended
In regulation 55C:
(a) delete “Observed” and insert: (1) Observed
(b) delete “field book.” and insert: field record.
(c) delete “Distances” and insert: (2) Distances
52. Regulation 55E amended
In regulation 55E:
(a) delete “Inspector of Plans and Surveys” and insert: Surveyor General
(b) delete “regulations 55A to 55F.” and insert: this Part.
(c) in the Table delete paragraph (a) and insert:
(a) I accept full responsibility for the plan shown on Plan No. …… and the authorised survey it
represents;
26 July 2013 GOVERNMENT GAZETTE, WA 3481 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 53
(d) in the Table in paragraph (b) delete “(Guidance of Surveyors)” and insert: (General Surveying Practice)
(e) in the Table in paragraph (d) delete “Field Books” and insert:
Field Records
53. Regulation 55F amended
In regulation 55F:
(a) delete “Before” and insert: (1) Before
(b) delete “field book” (first occurrence) and insert: field record
(c) delete “This field book” and insert: (2) The field record
Note: The heading to amended regulation 55F is to read: Lodgment of final survey certificate and field record
3482 GOVERNMENT GAZETTE, WA 26 July 2013 Licensed Surveyors (Guidance of Surveyors) Amendment
Regulations 2013
r. 54
54. Part 8 heading inserted
After regulation 55F insert:
Part 8 — Miscellaneous matters
55. Regulation 56 replaced
Delete regulation 56 and insert:
56. Grounds for disciplinary action
Whether a surveyor has or has not acted in accordance
with these regulations may be taken into account in
determining whether there is proper cause for
disciplinary action under section 21 of the Act in
respect of the surveyor.
Made by the Land Surveyors Licensing Board by a resolution passed at a meeting held on 13 June 2013.
COLIN SHIPP, Chairman,
Land Surveyors Licensing Board.
Approved by the Governor,
G. MOORE, Clerk of the Executive Council.
0
0
0