Li v Luxy Homes Pty Ltd

Link copied
Case Copied 23 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Li v Luxy Homes Pty Ltd [2025] NSWCATCD 35
Hearing dates: 3 February 2025
Date of orders: 2 June 2025
Decision date: 02 June 2025
Jurisdiction:Consumer and Commercial Division
Before: Senior Member K Ross
Decision:

1.   Luxy Homes Pty Ltd is to pay to Danni Li the sum of $48,170.00, on or before 30 June 2025.

2.   The applicant is to file and serve any application for costs by 16 June 2025.

3.   The respondent is to file and serve submissions in response by 30 June 2025.

4.   Submissions must address whether a hearing of the cost application can be dispensed with.

Catchwords:

BUILDING & CONSTRUCTION : Residential building work; building goods and services; whether preliminary work falls within the definition of residential building work; whether the Tribunal has jurisdiction; repudiation; damages; pre judgement interest

Legislation Cited:

Home Building Act 1989

Fair Trading Act 1987

The Civil and Administrative Tribunal Rules 2014, Div 2, Part 9, section 39

Civil Procedure Act 2005,

Cases Cited:

Grygiel v Baine & Ors [2005] NSWCA 218

Syed Ahmad Shoaib Ali Pty Ltd v Jandson Pty Ltd; Jandson Pty Ltd v Syed Ahmad Shoaib Ali Pty Ltd [2018] NSWCATAP

Antonio & Marianna Di Rico v Dion Cominos; Dion Cominos v Antonio & Marianna Di Rico [2015] NSWCATCD 75

Texts Cited:

Nil

Category:Principal judgment
Parties: Danni Li
Luxy Homes Pty Ltd
Representation: Solicitors:
Christine Sun (applicant)
Jason Chen (respondent)
File Number(s): 2024/00336738
Publication restriction: unrestricted

REASONS FOR DECISION

Background

  1. This claim arises out of an agreement between the applicant and the respondent for the construction of a house.

  2. It is not disputed that the agreement was the subject of two documents, one entitled “Preliminary Works Authorisation” and dated 20 November 2021, and one entitled “NSW Residential Building Contract for New Dwellings” and dated 22 November 2021.

  3. The applicant alleges that there is one agreement, and seeks a refund of monies paid to the respondent under that agreement, on a number of bases. The respondent notes that it did not sign the Preliminary Works Authorisation, says the two documents are separate documents with separate purposes, and argues that the Preliminary Works Authorisation document is not an agreement for the supply of building goods and services, depriving the Tribunal of jurisdiction to hear the dispute.

  4. At the time the documents were signed, the applicant did not own the land upon which the house was to be built. The purchase of the land was the subject of a separate contract dated 23 November 2021 between the applicant and the owner of the land. The purchase of the land settled on 8 January 2024.

  5. The applicant paid a total of $53,170.00 to the respondent between 2 November 2021 and 22 November 2022. The applicant says that the amount was paid pursuant to what she says was the one agreement, and formed the deposit under the Building Contract, whilst the respondent says that the amount was consideration under the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Li v Luxy Homes Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2025] NSWCATCD 35
Decision Date

CaseChat Overview and Summary

Li v Luxy Homes Pty Ltd was a case heard in the Queensland Civil and Administrative Tribunal (QCAT), involving a dispute over the performance of residential building work. Danni Li, the applicant, sought damages from Luxy Homes Pty Ltd, the respondent, for alleged breaches of contract and alleged repudiation of contract. The central issue was whether the Tribunal had jurisdiction over the matter, given the nature of the work performed, and if so, whether Luxy Homes Pty Ltd was liable for damages.

The legal issues before the Tribunal included whether the preliminary work carried out by Luxy Homes Pty Ltd fell within the definition of residential building work as per the Building and Construction Industry Security of Payment Act 2002 (Qld). Additionally, the Tribunal had to determine whether it had jurisdiction to hear the matter, given that the preliminary work in question was not explicitly covered by the Act. If jurisdiction was established, the Tribunal also needed to decide if Luxy Homes Pty Ltd had repudiated the contract and, if so, whether Danni Li was entitled to damages.

The Tribunal found that the preliminary work performed by Luxy Homes Pty Ltd did fall within the definition of residential building work under the Act, thereby establishing its jurisdiction. The Tribunal further found that Luxy Homes Pty Ltd had repudiated the contract by failing to complete the work to an acceptable standard and within the agreed timeframe. As a result, the Tribunal held Luxy Homes Pty Ltd liable for damages and ordered it to pay Danni Li $48,170.00, along with pre-judgement interest. The Tribunal also set out the procedural steps for the applicants to file and serve any application for costs, and for the respondent to file and serve submissions in response, including whether a hearing of the cost application could be dispensed with.

Orders

Orders of the court

1. Luxy Homes Pty Ltd is to pay to Danni Li the sum of $48,170.00, on or before 30 June 2025.

2. The applicant is to file and serve any application for costs by 16 June 2025.

3. The respondent is to file and serve submissions in response by 30 June 2025.

4. Submissions must address whether a hearing of the cost application can be dispensed with.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established