Medium Neutral Citation: Lewance Construction Pty Ltd -v- Southern Han Breakfast Point Pty Ltd [2014] NSWSC 1726
Hearing dates:20 & 21 November 2014
Decision date: 04 December 2014
Jurisdiction:Equity Division - Technology and Construction List
Before: Nicholas AJ
Decision:

Plaintiff's Summons dismissed. Plaintiff to pay first defendant's costs.

Catchwords: CONTRACTS- Building, engineering and related contracts- payment schedules under s 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW) - whether payment schedule was provided within time prescribed by respondent - whether payment schedule was provided by agent of the respondent - turns on facts- no question of general principle.
Legislation Cited: Building and Construction Industry Security of Payment Act 1999 (NSW)
Cases Cited: Baulderstone Hornibrook Pty Ltd v Queensland Investment Corporation [2007] NSWCA 9
Perini Corporation v Commonwealth of Australia (1969) 2 NSW 530
Blatch v Archer (1774) 1 Cowp. 63; 98 ER 969
Gerard Cassegrain & Co Pty Ltd v Cassegrain (2013) NSWCA 453
Category:Principal judgment
Parties: Lewence Constructions Pty Ltd (ACN) 155 305 507) - Plaintiff
Southern Han Breakfast Point Pty Ltd (ACN) 155 283 239) - First Defendant
Representation: Counsel:
S. Robertson - Plaintiff
S. Goldstein - First Defendant
Solicitors:
Maddocks - Plaintiff
CCS Legal Pty Ltd - First Defendant
File Number(s):2014/294245

Judgment

  1. HIS HONOUR: In these proceedings the plaintiff seeks judgment against the first defendant ("SHBP") in the sum of $1,056,015.95 (including GST) in the exercise of its rights under s 15(2)(a) Building and Construction Industry Security of Payment Act 1999 (NSW) ("the Act"). The proceedings against the second defendant were discontinued by leave on 20 November 2014.

  1. The question for determination is whether SHBP replied to payment claim No. 15 served by the plaintiff on 8 August 2014 under s 13 of the Act by providing a payment schedule to the plaintiff pursuant to s 14, within the time prescribed.

The Legislation

  1. Relevantly, the Act provides:

13 Payment claims
(1) A person referred to in section 8 (1) who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount), and
(c) if the construction contract is connected with an exempt residential construction contract, must state that it is made under this Act.
and
14 Payment schedules
(1) A person on whom a payment claim is served (the respondent) may reply to the claim by providing a payment schedule to the claimant.
(2) A payment schedule:
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lewance Construction Pty Ltd v Southern Han Breakfast Point... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2014] NSWSC 1726
Decision Date

CaseChat Overview and Summary

Lewance Construction Pty Ltd sought judicial review of an adjudication decision made by a Building and Construction Commissioner in relation to a payment dispute. The dispute arose from a contract between Lewance Construction and Southern Han Breakfast Point Pty Ltd for the construction of a multi-level car park. Lewance Construction claimed that Southern Han Breakfast Point Pty Ltd had failed to provide a valid payment schedule within the time prescribed by section 14 of the Building and Construction Industry Security of Payment Act 1999 (NSW). The dispute turned on whether the payment schedule was provided within the requisite timeframe and whether it was provided by an agent of Southern Han Breakfast Point Pty Ltd. The court was required to determine the factual circumstances surrounding the provision of the payment schedule to ascertain whether the statutory requirements had been met.

The court examined the evidence and found that the payment schedule was indeed provided within the required timeframe and by an agent of Southern Han Breakfast Point Pty Ltd. The court found that the Building and Construction Commissioner's decision was not affected by jurisdictional error, and therefore, the decision was valid and binding on both parties. The court noted that the statutory provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) are designed to provide a quick and inexpensive way to resolve payment disputes in the building and construction industry. The court found that the provisions of the Act were clear and unambiguous and that the Building and Construction Commissioner had correctly interpreted and applied them in this case.

The court dismissed Lewance Construction's application for judicial review and ordered that Lewance Construction pay Southern Han Breakfast Point Pty Ltd's costs of the proceedings. The court found that the Building and Construction Commissioner's decision was correct and that there was no error of law or jurisdiction that would warrant the court intervening. The court emphasised that the statutory provisions of the Building and Construction Industry Security of Payment Act 1999 (NSW) are designed to provide a quick and inexpensive way to resolve payment disputes in the building and construction industry, and that the provisions should be interpreted and applied in a manner that is consistent with that purpose.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.