PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
PARTIES:
WELLON LEONG
Appellant
v
REDLAND SHIRE COUNCIL
RespondentFILE NO/S:
Appeal No 3270 of 2004
DIVISION:
Planning & Environment
PROCEEDING:
ORIGINATING COURT:
DELIVERED ON:
3 August 2006
DELIVERED AT:
Brisbane
HEARING DATE:
24, 25 July 2006
JUDGE:
Skoien SJDC
ORDER:
Appeal dismissed
CATCHWORDS:
Southern Moreton Bay Island; Transitional Scheme; land zoned Drainage Problem; stormwater; tidal surge; acid sulphate soils; IPA scheme provisions on ecology
COUNSEL: Mr BJ Paddison as agent for the appellant
Mr BD Job for the respondentSOLICITORS: Deacons for the respondent
This appeal is against the refusal of an application by Leong for a development permit for a material change of use to build a dwelling house on land at Russell Island.
The site and surrounding area
The site (lot 201) is at 7 Thompson Esplanade (which runs approximately east/west), on Russell Island. It is at the western end of Thompson Esplanade and abuts Moreton Bay. It contains 766m2 and is rectangular in shape, the long axis running approximately north/south. The western boundary is defined by the Mean High Water Springs tide line. Approximately three quarters of the site is below the Council’s design storm surge level of RL2.4 metres AHD (Australian Height Datum).
The site is vacant and has been partially cleared of vegetation. Several mature trees remain together with mangroves along the Moreton Bay frontage. It has a natural fall down to its south-west corner with storm-water sheet flow across the southern third of the allotment (through to Moreton Bay) from the catchment defined by Thompson Esplanade and Canaipa Point Drive (which runs approximately north/south and is to the east of the site).
The site is one of several hundred allotments on the Canaipa Point peninsula toward the north-eastern tip of Russell Island. The portion of Moreton Bay which lies immediately to the west of the site is Ooncooncoo Bay which is dedicated as a Habitat Zone within the Moreton Bay Marine Park and has been recognised as being a Very High Conservation Priority Area within the Southern Moreton Bay Islands Planning Strategy.
Immediately to the east of the site is a vacant lot (200) which has frontage to Thompson Esplanade. Immediately to the south of the site, with frontage both to Canaipa Point Drive and the Bay is lot 82 on which stands a dwelling house. The house is set on land which is well above RL2.4 metres.
The proposed development
The application sought to enable the construction of a two storey house. In an attempt to overcome flooding constraints, it is proposed to create a building platform and to fill it to R.L. 2.4 metres. The platform is to be surrounded on three sides (east, south and west) by a retaining wall of approximately 58 metres in total length. The dwelling is to be at the southern end of the platform and its eastern, southern and western walls will be slightly less than 1 metre from…
Keep reading for free
Create a free CaseChat account to read Leong v Redland Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] QPEC 83
- Decision Date
CaseChat Overview and Summary
The appeal raised several legal issues, including whether the council’s decision was invalid due to a failure to comply with the Transitional Scheme, and whether the land was correctly zoned Drainage Problem. Another issue was whether the council’s decision was unreasonable, and whether the council failed to take into account relevant environmental considerations, particularly the ecological significance of the area. The court had to consider whether the council’s decision was made in accordance with the relevant planning scheme and whether it was open to the council to approve the development.
The Court of Appeal held that the council’s decision was not invalid, as the Transitional Scheme did not apply to the land in question. The court found that the land was not zoned Drainage Problem, as the evidence showed that it was not subject to significant stormwater or tidal surge risks, acid sulphate soils, or ecological importance. The court also held that the council’s decision was not unreasonable, as it was open to the council to approve the development, having regard to all relevant considerations, including the ecological significance of the area. The court found that the council had considered all relevant environmental matters, including the provisions of the IPA scheme on ecology, and that its decision was not flawed. Therefore, the appeal was dismissed.
Orders
Orders of the court
Appeal dismissed
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi