Lend Lease Project Management and Construction (Australia) Pty Ltd v Construction, Forestry, Mining and Energy Union

Link copied
Case Copied 20 min read

FEDERAL COURT OF AUSTRALIA

Lend Lease Project Management & Construction (Australia) Pty Ltd v Construction, Forestry, Mining and Energy Union [2011] FCA 387

Citation: Lend Lease Project Management & Construction (Australia) Pty Ltd v Construction, Forestry, Mining and Energy Union [2011] FCA 387
Parties: LEND LEASE PROJECT MANAGEMENT & CONSTRUCTION (AUSTRALIA) PTY LTD v CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION, CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION - CONSTRUCTION AND GENERAL DIVISION - QUEENSLAND CONSTRUCTION WORKERS DIVISIONAL BRANCH, CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION - CONSTRUCTION AND GENERAL DIVISION, QUEENSLAND BUILDERS' LABOURERS DIVISIONAL BRANCH, CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION, INDUSTRIAL UNION OF EMPLOYEES, QUEENSLAND, COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA, COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA, ELECTRICAL, ENERGY AND SERVICES DIVISION - QUEENSLAND DIVISIONAL BRANCH and AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER
File number: QUD 79 of 2011
Judge: LOGAN J
Date of judgment: 13 April 2011
Catchwords: INDUSTRIAL LAW – interim injunction – serious question to be tried – balance of convenience – where industrial action pursued in contravention of the Fair Work Australia order – where applicant sought an injunction to enforce order as an interested party under the Fair Work Act 2009 (Cth) – where there was likelihood of further industrial action – where project was of significance to the State of Queensland – where responsibility for industrial action rested on respondents – interim injunction issued against first, fourth and fifth respondents
Legislation: Building and Construction Industry Improvement Act 2005 (Cth) ss 38, 39, 44, 49
Fair Work Act 2009 (Cth) ss 421, 539
Federal Court of Australia Act 1976 (Cth) s 23
Date of hearing: 13 April 2011
Place: Brisbane
Division: GENERAL DIVISION
Category: Catchwords
Number of paragraphs: 32
Counsel for the Applicant: Mr J Murdoch SC
Solicitor for the Applicant: Middletons
Counsel for the Respondents: Mr MP Amerena
Solicitor for the Respondents: Hall Payne
Solicitor for the Intervenor: Norton Rose

IN THE FEDERAL COURT OF AUSTRALIA

QUEENSLAND DISTRICT REGISTRY

GENERAL DIVISION

QUD 79 of 2011

BETWEEN:

LEND LEASE PROJECT MANAGEMENT & CONSTRUCTION (AUSTRALIA) PTY LTD
Applicant

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First Respondent

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION - CONSTRUCTION AND GENERAL DIVISION - QUEENSLAND CONSTRUCTION WORKERS DIVISIONAL BRANCH
Second Respondent

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION - CONSTRUCTION AND GENERAL DIVISION, QUEENSLAND BUILDERS' LABOURERS DIVISIONAL BRANCH
Third Respondent

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION, INDUSTRIAL UNION OF EMPLOYEES, QUEENSLAND
Fourth Respondent

COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA
Fifth Respondent

COMMUNICATIONS, ELECTRICAL, ELECTRONIC, ENERGY, INFORMATION, POSTAL, PLUMBING AND ALLIED SERVICES UNION OF AUSTRALIA, ELECTRICAL, ENERGY AND SERVICES DIVISION - QUEENSLAND DIVISIONAL BRANCH
Sixth Respondent

AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSIONER
Intervenor

JUDGE:

LOGAN J

DATE OF ORDER:

13 APRIL 2011

WHERE MADE:

BRISBANE

THE COURT ORDERS THAT:

1.1      This Order is binding on and applies to:

1.1.1Construction Forestry Mining Energy Union (“CFMEU”);

1.1.2Construction, Forestry, Mining & Energy, Industrial Union of Employees, Queensland,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lend Lease Project Management and Construction (Australia) P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] FCA 387
Decision Date

CaseChat Overview and Summary

Lend Lease Project Management and Construction (Australia) Pty Ltd brought an application against the Construction, Forestry, Mining and Energy Union, and related entities, seeking an interim injunction to enforce a Fair Work Australia order against union-related industrial action. The court had to decide whether the applicant had a serious question to be tried and whether the balance of convenience favoured granting an injunction. The court found that there was a serious question to be tried as the applicant had shown that the unions were likely to continue their industrial action in contravention of the Fair Work Australia order. The court also found that the balance of convenience favoured granting the injunction as the project was of significant importance to the State of Queensland and the responsibility for the industrial action rested on the respondents. The court issued an interim injunction against the first, fourth and fifth respondents to prevent further industrial action in relation to the project.

The court noted that the Fair Work Act 2009 (Cth) allowed an interested party to seek an injunction to enforce a Fair Work Australia order. The court found that Lend Lease was an interested party as it had a direct interest in the enforcement of the order. The court also found that the unions were likely to continue their industrial action in contravention of the order and that there was a serious question to be tried as to whether the industrial action was lawful. The court noted that the balance of convenience favoured granting the injunction as the project was of significant importance to the State of Queensland and the responsibility for the industrial action rested on the respondents. The court issued an interim injunction against the first, fourth and fifth respondents to prevent further industrial action in relation to the project. The injunction required the respondents to stop, not engage in and/or not organise industrial action as defined in the order in respect of work being conducted at the site. The injunction also required the respondents to take reasonable steps to bring the existence of the order to the attention of their officials, delegates, officers, employees and agents and to withdraw any authorisation, encouragement or direction to engage in industrial action. The injunction took effect on pronouncement and remained in force until 4.30 pm on 27 April 2011. The matter was adjourned for directions on 27 April 2011 at 2:15pm and costs were reserved.

Orders

Orders of the court

1.1 This Order is binding on and applies to:

1.1.1 Construction Forestry Mining Energy Union (“CFMEU”);

1.1.2 Construction, Forestry, Mining & Energy, Industrial Union of Employees, Queensland, (“CFMEUQ”);

1.1.3 Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia (“CEPU”);

1.1.4 The officials, delegates, officers, employees and agents of the unions referred to above in 1.1.1 to 1.1.3; and

1.1.5 All subcontractors engaged by Lend Lease Project Management & Construction (Australia) Pty Ltd at the site.

1.2 All persons listed in the above clauses 1.1.1 to 1.1.5 must comply with the terms of clause 2 and 3 of this Order.

1.3 In this order site means:

(a) In Queensland:

i. Brisbane Supreme Court and District Court Project site, 419 George Street Brisbane.

2 INDUSTRIAL ACTION TO STOP, NOT OCCUR AND NOT BE ORGANISED

2.1 All person and organisations bound by this Order must stop, not engage in and/or not organise industrial action as defined in clause 4 in respect of work being conducted at the site and must not further engage in, recommence, or threaten to engage in, industrial action as defined in clause 4 whilst the Order remains in operation.

2.2 The CFMEU, CFMEUQ and CEPU and must:

2.2.1 stop organizing and refrain from further organizing or recommencing the organisation of industrial action as defined in clause 4.

2.2.2 not aid, abet, direct, counsel, procure, authorise, influence or encourage any person to whom this Order applies to engage in conduct referred to in clause 2.2.1 above.

2.2.3 Not threaten or propose to do any of the things referred to in clause 4.

2.3 The officials, delegates, employees and agents of the unions identified in the above clauses 1.1.1. to 1.1.5 must:

2.3.1 stop, organizing and refrain from further organizing or recommencing the organisation of industrial action as defined in clause 4.

2.3.2 not aid, abet, direct, counsel, procure, authorise, influence or encourage any person to whom this Order applies to engage in conduct referred to in clause 2.3.1 above.

2.3.3 Not threaten or propose to do any of the things referred to in clause 4.

3 OTHER DIRECTIONS

3.1 The unions identified in the above clauses 1.1.1 to 1.1.3 must each as soon as is reasonably practicable:

3.1.1 Take all reasonable steps to bring the existence of this Order to the attention of their officials, delegates, officers, employees and agents; and

3.1.2 Notify them of the explicit withdrawal of any authorization, encouragement or direction to engage in industrial action as defined in clause 4; and

3.1.3 Issue and distribute (including but not limited to posting, and maintaining for the duration that the Order is in force, on the home page of each union listed in 1.1.1 to 1.1.3 and their branch websites) a communication to the persons mentioned in clauses 1.1.4 to 1.1.5 which:

3.1.3.1 Includes a copy of this Order;

3.1.3.2 Includes a copy of the Recommendation of 12 April 2011 (PR508402);

3.1.3.3 States that the industrial action on the site is to cease and is cancelled;

3.1.3.4 States that members or persons eligible to be members of the union on the site must engage in work as directed by their employer or principal subcontractor at the ordinary commencement of work on Thursday 14 April 2011.

4 DEFINITION OF INDUSTRIAL ACTION

4.1 For the purpose of this Order, the expression industrial action means:

4.1.1 a failure or refusal by a person to attend for work or a failure or refusal to perform any work at all by employees who attend for work;

4.1.2 a ban, limitation or restriction on the performance of work by a person or on the acceptance of or offering for work by a person;

4.1.3 the performance of work by a person in a manner different from that in which it is customarily performed, or the adoption of a practice in relation to work by a person, the result of which is a restriction or limitation on, or a delay in, the performance of work.

4.2 For the purpose of this Order, industrial action does not include:

4.2.1 protected industrial action within the meaning of s408 of the Fair Work Act 2009

4.2.2 action by employees that is authorised or agreed to by his or her employer; or

4.2.3 action by an employee or subcontractor if:

4.2.3.1 the action was based on a reasonable concern by the employee about an imminent risk to his or her health or safety; and

4.2.3.2 the employee did not unreasonably fail to comply with a direction by his or her employer to perform other available work, whether at the same or another workplace, that was safe and appropriate for the employee to perform.

5. This Order takes effect on pronouncement and will remain in force until 4.30 pm on 27 April 2011.

6. Liberty to apply and if need be by telephone or video-link.

7. The matter be adjourned for directions on 27 April 2011 at 2:15pm.

8. Costs reserved.

Note:

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established