| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMON LAW DIVISION
PERSONAL INJURIES LIST
S CI 2015 00028
| SHIRELLE LEAN | Plaintiff |
| v | |
| THE PITSTOP MOTOR GROUP PTY LTD | Defendant |
---
JUDGE: | Ierodiaconou AsJ |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 6 and 7 June 2016 |
DATE OF JUDGMENT: | 23 June 2016 |
CASE MAY BE CITED AS: | Lean v The Pitstop Motor Group Pty Ltd |
MEDIUM NEUTRAL CITATION: | [2016] VSC 357 |
---
CIVIL PROCEDURE – Limitation of Actions – Application for extension of period during which action may be brought – Whether just and reasonable – Delay – Plaintiff’s awareness of limitation period – Limitation of Actions Act 1958 (Vic) ss 5(1), 23A – Itek Graphix Pty Ltd v Elliott, considered.
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr T Tobin QC with Mr R Ajzensztat | Maurice Blackburn Lawyers |
| For the Defendant | Mr N Murdoch QC with Ms C Spitaleri | Lander & Rogers Lawyers |
HER HONOUR:
The plaintiff sustained injury in the course of her employment with the defendant in an incident which occurred on 17 October 2000. The plaintiff wishes to pursue a claim for damages against her former employer on the basis of negligence and breach of statutory duty. It is common ground between the parties that the relevant limitation period expired on 16 October 2006. The plaintiff is therefore out of time to bring this proceeding. By summons filed 12 February 2016, the plaintiff applied for an extension of time in which to bring her action against the defendant.
The issue for determination in this ruling is whether or not the Court should grant such an extension.
Summary
For the reasons below the plaintiff’s summons is dismissed.
Background
The following matters were not in dispute between the parties.
The plaintiff was working as a spare parts delivery driver for the defendant at the time of the incident on 17 October 2000 in which she was injured (‘the incident’). She made a workers’ compensation claim on 1 November 2000. She subsequently received payment for medical and like expenses and also weekly payments. In October 2009, the plaintiff made a claim for permanent impairment. The plaintiff subsequently elected to receive a nil settlement in respect of that claim. A week later, on 28 April 2014, the plaintiff lodged a claim for serious injury. On 22 August 2014, a Serious Injury Certificate was granted. On 7 January 2015, the writ in this proceeding was issued.
The effect of s 134ABA of the Accident Compensation Act 1985 (Vic) is that the period after October 2009, when the claim for permanent impairment was made, is disregarded for the purpose of considering the delay in bringing this application. Consequently, for the purpose of this application, the relevant period is from 17 October 2000 to October 2009, almost nine years. The relevant limitation period pursuant to s 5(1) of the Limitation of Actions Act 1958 (Vic) (‘the LAA’) is six years. This period commenced on the accrual of the plaintiff’s cause of action…
Continue reading Lean v The Pitstop Motor Group Pty Ltd
Sign in free to access the full text
- AGLC
- Lean v The Pitstop Motor Group Pty Ltd [2016] VSC 357
- Case
- [2016] VSC 357
- Decision Date
CaseChat Overview and Summary
The central legal issue was whether the plaintiff's delay in bringing the action was justified under the circumstances, considering the factors outlined in section 23A(3) of the Act. The court examined the reasons for the delay, the plaintiff's knowledge of the limitation period, and whether the plaintiff had acted with reasonable promptness once aware of the cause of action. The decision in Itek Graphix Pty Ltd v Elliott was considered, which emphasised the importance of the plaintiff acting promptly once they became aware of their cause of action.
The court held that the plaintiff's delay was not justified, as they had been aware of the limitation period and the need to act promptly but failed to do so. The plaintiff's explanation for the delay was not sufficient to meet the threshold for an extension under section 23A. The court rejected the application for an extension of time, finding that the delay was unreasonable and that the plaintiff had not acted with the necessary promptness once aware of their cause of action. As a result, the plaintiff's action was statute-barred, and the court dismissed the application for an extension of time.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.