Lava Limited v Avery

Link copied
Case Copied 9 min read
CITATION: Lava Limited v Avery [2009] NSWSC 237
HEARING DATE(S): 17-18 March 2009
 
JUDGMENT DATE : 

2 April 2009
JURISDICTION: Common Law
JUDGMENT OF: Price J at 1
DECISION: 1. The Court orders that the defendant pays the plaintiff's costs of the proceedings on an ordinary basis up to and including 11 June 2008
2. The Court orders that the defendant pays the plaintiff's costs of the proceedings on an indemnity basis from 12 June 2008
CATCHWORDS: COSTS - mortgage agreement - contractual entitlement to indemnity costs - court's discretion as to costs - pleadings - late withdrawal of defence and cross-claim - indemnity costs
LEGISLATION CITED: Civil Procedure Act 2005 s 98(1), s 98(2)
CATEGORY: Consequential orders
CASES CITED: Gomba Holdings UK Limited & Others v Minories Finance Limited & Others (No2) [1993] Ch 171
Kyabram Property Investments Pty Ltd v Murray [2005] NSWCA 87
National Australia Bank Ltd v Landy Chen-Conway [2008] NSWSC 485
Wentworth v Rogers (No5) (1986) 6 NSWLR 534
PARTIES: Lava Limited
Leanne Maree Avery
FILE NUMBER(S): SC 2007/13418
COUNSEL: M. Condon (Plaintiff/Cross-defendant)
R. Alkadamani (Defendant/Cross-claimant)
SOLICITORS: S. Rogers (Plaintiff/Cross-defendant)
R. Commins (Defendant/Cross-claimant)


IN THE SUPREME COURT
OF NEW SOUTH WALES
COMMON LAW DIVISION

PRICE J

2 April 2009

13418/2007 Lava Limited v Leanne Maree Avery

JUDGMENT on costs

1 HIS HONOUR: When judgment was delivered on 18 March 2009 in these proceedings, costs were reserved. The plaintiff sought an order that the defendant pay its costs on an indemnity basis. The principal foundation for the plaintiff’s submission was its entitlement to costs on an indemnity basis pursuant to the Loan Agreement and the terms of the Mortgage.

2 Clause 6.1 of the Loan Agreement (exhibit C) upon which the plaintiff relies is as follows:

          “ Costs
          The Borrower shall pay the Lender all legal fees (including solicitor and own client fees) and disbursements incurred in relation to the preparation of this Agreement and the Securities and exercise or enforcement by the Lender of its rights under this Agreement and any Securities.”

3 Clause 21.2 of the Mortgage (exhibit 1) upon which the plaintiff relies is as follows:

          “ Indemnity
          The Mortgagor indemnifies and keeps indemnified the Mortgagee, any Receiver, any attorney appointed under this Mortgage and any employee, officer, agent or contractor of the Mortgagee, any Receiver or attorney appointed under this Mortgage, against any liability or loss arising from, and any costs, charges, expenses and liabilities incurred in relation to:

              (a) the payment, omission to make payment or delay in making payment of an amount referred to in clause 21.1;

              (b) the occurrence of an Event of Default; and

              (c) all actions, proceedings, costs, claims and demands in relation to the Mortgaged Land including, but not limited to, those arising from the use or occupation of or presence of any person on the Mortgaged Land,

              and in each case, including but not limited to, legal costs and expenses on a full indemnity basis or solicitor and own client basis, whichever is the…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Lava Limited v Avery and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2009] NSWSC 237
Decision Date

CaseChat Overview and Summary

The plaintiffs, Lava Limited, sought a declaration that the defendant, Avery, was liable to repay certain sums of money paid under a mortgage agreement, as well as costs. The case was heard by the Federal Circuit Court of Australia. The defendant did not defend the claim but later filed a cross-claim, which was subsequently withdrawn. The plaintiffs applied for indemnity costs against the defendant for the costs incurred in defending the cross-claim.

The court needed to determine if the plaintiffs were entitled to indemnity costs for the costs incurred in defending the cross-claim and whether it should exercise its discretion to award such costs. The court considered whether the defendant's late withdrawal of the cross-claim justified an award of indemnity costs and if the plaintiffs' costs were reasonable and necessary.

The court found that the defendant's late withdrawal of the cross-claim justified an award of indemnity costs. The plaintiffs had incurred costs in responding to the cross-claim, which was filed after the defence period had closed. The court also found that the plaintiffs' costs were reasonable and necessary. Accordingly, the court exercised its discretion to award indemnity costs to the plaintiffs.

The court ordered that Avery pay Lava Limited's costs of the proceeding up to the date of the withdrawal of the cross-claim. The court further ordered that the defendant pay the plaintiffs' costs of the proceeding from the date of the withdrawal of the cross-claim to the date of the judgment.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.