Medium Neutral Citation: Lasovski v Traj Developments Pty Ltd [2022] NSWCATCD 85 Hearing dates: 24 March 2022 Date of orders: 20 June 2022 [amended 11 August 2022] [further amended 14 September] Decision date: 20 June 2022 Jurisdiction: Consumer and Commercial Division Before: R Alkadamani, Senior Member
Pursuant to Section 63 of the Civil and Administrative Tribunal Act 2013, reasons published are amended to read as follows:Decision: 1. Traj Developments Pty Ltd, at no cost to Julie Lasovski and David Ristevski, remove all the windows and glazed doors referred to at pages 5-10 of the BASIX certificate under the heading “Windows, glazed doors and skylights” which do not have thermally broken frames and replace and install new windows and glazed doors that have aluminium frames that are thermally broken and that otherwise comply with the Contract, including the BASIX Certificate, being the document forming part of exhibit 3, and perform all necessary carpentry, plasterboard work or similar work, including providing the necessary materials (“the Work”);
2. Traj Developments Pty Ltd complete the Work within 60 days of the date of these orders, or such other time as the parties may agree;
3. Traj Developments Pty Ltd perform the Work in a proper and workmanlike manner;
4. Traj Developments Pty Ltd provide and install, at no cost to Julie Lasovski and David Ristevski, the scaffolding and other equipment which may be necessary to undertake the Work safely;
5. Traj Developments Pty Ltd undertake, at no cost to the Julie Lasovski and David Ristevski, all necessary carpentry, plasterboard work or similar work in connection with the Work, including providing the necessary labour and materials;
6. Traj Development Pty Ltd install, in a proper and workmanlike manner and at no cost to Julie Lasovski and David Ristevski, sarking in the top roof area above the entrance of the dwelling and the area on the left hand side of the KLIPLOK roof within 60 days of the date of these orders, or such other time as the parties may agree;
7. Julie Lasovski and David Ristevski provide Traj Developments Pty Ltd and/or its contractors reasonable access to the dwelling and the property for the purpose of carrying out the Work and/or install the sarking;
8. Traj Developments Pty Ltd pay Julie Lasovksi and David Ristevksi’s costs of and incidental to these proceedings on the ordinary basis as agreed or assessed.
Catchwords: BUILDING AND CONSTRUCTION – Contract – Terms – Defects – Work Order
CONTRACTS – Express terms – incorporation of terms
COSTS – whether r 38 applies – amount claimed or in dispute
Legislation Cited: Civil and Administrative Tribunal Act 2013 (NSW)
Civil and Administrative Tribunal Rules 2014
Home Building Act 1989 (NSW)
Cases Cited: Allen v TriCare (Hastings) Ltd [2017] NSWCATAP 25
Clements v Murphy [2018] NSWCATAP 152
Deacon v National Strategic Constructions; National Strategic Constructions v Deacon [2017] NSWCATAP 185
Khan v Kang [2014] NSWCATAP 48
Nguyen v Perpetual Trustee Company Ltd; Perpetual…
Keep reading for free
Create a free CaseChat account to read Lasovski v Traj Developments Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] NSWCATCD 85
- Decision Date
CaseChat Overview and Summary
The primary legal issues the court had to address were whether the plaintiffs had sufficiently identified the defects in the construction work, and if so, whether Traj Developments Pty Ltd was liable for those defects. The court needed to determine whether the defects were apparent and whether the plaintiffs had given reasonable notice to the defendants. Additionally, the court had to consider whether the defects were caused by the defendants' breach of the contract, and if so, what remedies were available to the plaintiffs.
The court found that the plaintiffs had adequately identified the defects and provided sufficient notice to the defendants. The court held that the defendants were liable for the defects because they had not complied with the express terms of the contract and the BASIX Certificate. The court emphasised that the defendants were required to install windows and doors that had thermally broken frames, which they had failed to do. The court ordered the defendants to remove the defective windows and doors and replace them with new ones that met the required standards. The court also ordered the defendants to install the necessary sarking in the top roof area, again within a specified timeframe. The court ruled that the defendants were to bear the cost of the required works and the plaintiffs' legal costs.
The court’s orders included specific directives for the defendants to rectify the defects within a stipulated period, provide necessary materials and equipment, and complete the work in a professional manner. The plaintiffs were also required to allow reasonable access to the property for the defendants to perform the mandated works. Furthermore, the court ordered the defendants to pay the plaintiffs' legal costs as per the agreed or assessed terms.
Orders
Orders of the court
1. Traj Developments Pty Ltd, at no cost to Julie Lasovski and David Ristevski, remove all the windows and glazed doors referred to at pages 5-10 of the BASIX certificate under the heading “Windows, glazed doors and skylights” which do not have thermally broken frames and replace and install new windows and glazed doors that have aluminium frames that are thermally broken and that otherwise comply with the Contract, including the BASIX Certificate, being the document forming part of exhibit 3, and perform all necessary carpentry, plasterboard work or similar work, including providing the necessary materials (“the Work”);
2. Traj Developments Pty Ltd complete the Work within 60 days of the date of these orders, or such other time as the parties may agree;
3. Traj Developments Pty Ltd perform the Work in a proper and workmanlike manner;
4. Traj Developments Pty Ltd provide and install, at no cost to Julie Lasovski and David Ristevski, the scaffolding and other equipment which may be necessary to undertake the Work safely;
5. Traj Developments Pty Ltd undertake, at no cost to the Julie Lasovski and David Ristevski, all necessary carpentry, plasterboard work or similar work in connection with the Work, including providing the necessary labour and materials;
6. Traj Development Pty Ltd install, in a proper and workmanlike manner and at no cost to Julie Lasovski and David Ristevski, sarking in the top roof area above the entrance of the dwelling and the area on the left hand side of the KLIPLOK roof within 60 days of the date of these orders, or such other time as the parties may agree;
7. Julie Lasovski and David Ristevski provide Traj Developments Pty Ltd and/or its contractors reasonable access to the dwelling and the property for the purpose of carrying out the Work and/or install the sarking;
8. Traj Developments Pty Ltd pay Julie Lasovksi and David Ristevksi’s costs of and incidental to these proceedings on the ordinary basis as agreed or assessed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi