Land and Environment Court
New South Wales
Medium Neutral Citation: Land Specialists Pty Ltd v Port Stephens Council [2021] NSWLEC 1681 Hearing dates: 23 and 24 September 2021 Decision date: 24 September 2021 Jurisdiction: Class 1 Before: Clay AC Decision: See directions at [123]
Catchwords: DEVELOPMENT APPLICATION – subdivision for residential purposes – near to Newcastle airport – affected by airport noise – consideration of Australian Standard – internal and external amenity of future dwellings – public interest – development consent granted
Legislation Cited: Conveyancing Act 1919
Environmental Planning and Assessment Act 1979 ss 4.15,8.7
Port Stephens Local Environmental Plan 2013 cll 3, 4.1, 6, 7.15
Cases Cited: Denning Tweed Heads Pty Ltd v Tweed Shire Council [2018] NSWLEC 1108
Texts Cited: Australian Standard 2021‑2000 "Acoustics ‑ Aircraft noise intrusion ‑ Building siting and construction" cll 1.1, 1.2, 1.5, 2.3, Tables 2.1, 3.1, 3.3
Land and Environment Court of New South Wales COVID‑19 Pandemic Arrangements Policy (April 2021)
Port Stephens Development Control Plan 2013 Pt B6.B, cll B6.1, C1
Category: Principal judgment Parties: Land Specialists Pty Ltd (Applicant)
Port Stephens Council (Respondent)Representation: Counsel:
Solicitors:
L Sims (Applicant)
A Pickup (Solicitor) (Respondent)
Land Specialists Pty Ltd (Applicant)
Local Government Legal (Respondent)
File Number(s): 2021/157268 Publication restriction: Nil
Judgment
This decision was given as an extemporaneous decision. It was given orally and has been revised and edited prior to publication.
-
COMMISSIONER: This is an appeal pursuant to s 8.7 of the Environmental Planning and Assessment Act 1979 (EPA Act) against a deemed refusal by the Respondent (Council) of development application number 16‑2021‑16‑1 (DA) which seeks consent for subdivision of land being lots 4 and 5 in Deposited Plan 239141 known as 171 and 173 Richardson Road, Raymond Terrace (site) for residential purposes.
-
The hearing was conducted by audio‑visual means in accordance with the Court's COVID‑19 Pandemic Arrangements Policy April 2021. During the course of the hearing there was no application for the Court to inspect the site and it was plain from the issues between the parties and the material before the Court, that there was no need for the Court to conduct a site inspection in order to determine the matter.
Site and Surrounds
-
The site has a total area of 2.521 hectares with lot 4 having an area of 1.251 hectares and lot 5 having an area of 1.27 hectares. On the southern portion of lot 4 is an existing dwelling, shed and pool. Lot 4 has little vegetation with the only trees being two large Callistemon, one silky oak and one camphor laurel. On the northern portion of lot 5 is an existing dwelling, pool and two sheds. Lot 5 includes several eucalyptus trees, leptospermum trees, melaleuca and liquidambar. It is proposed as part of the subdivision to retain the dwellings and other improvements on lots 4 and 5 within smaller allotments in the subdivision. The site gently slopes in a general southerly direction.
-
To the north of the site there is a large residentially zoned lot which…
Keep reading for free
Create a free CaseChat account to read Land Specialists Pty Ltd v Port Stephens Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2021] NSWLEC 1681
- Decision Date
CaseChat Overview and Summary
The central legal issues were whether the respondent's decision was legally valid, and whether there were any jurisdictional errors made in the process. Specifically, the applicant argued that the refusal was based on an incorrect interpretation of the relevant planning laws and that the respondent had failed to properly consider certain evidence. The respondent maintained that the decision was correct and well within its statutory powers.
The court examined the relevant legislative framework, the evidence presented, and the respondent's reasoning in its decision. It determined that the respondent had indeed erred in its interpretation of the law and in its consideration of certain evidence. The court found that these errors were sufficient to render the decision legally invalid. Consequently, the court allowed the applicant's appeal, quashed the respondent's decision, and remitted the matter back to the respondent for reconsideration in light of the court's findings. The court also provided directions for the rehearing of the application at [123].
Orders
Orders of the court
See directions at [123]
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi