Lali Investments Pty Ltd v Burnett Shire Council

Case [2003] QPEC 33


PLANNING & ENVIRONMENT COURT
OF QUEENSLAND

CITATION:

Lali Investments Pty Ltd v Burnett Shire Council [2003] QPEC 033

PARTIES:

LALI INVESTMENTS PTY LTD
Applicant
v
BURNETT SHIRE COUNCIL
Respondent

FILE NO:

1536 of 2003

DIVISION:

Planning and Environment Court

PROCEEDING:

Application

ORIGINATING COURT:

Brisbane

DELIVERED ON:

29 July 2003

DELIVERED AT:

Brisbane

HEARING DATE:

30 June 2003

JUDGE:

Quirk DCJ

ORDER:

-

CATCHWORDS:

BUILDING CONTROL AND TOWN PLANNING – town planning – development application – where public notification commenced earlier than required – whether applicant failed to inform council that public notification had commenced – substantial compliance

COUNSEL:

Mr M Hinson SC for the respondent
Mr D Fahl (Solicitor) for the applicant

SOLICITORS:

Lester Manning Lawyers for the applicant
Connor O’Meara for the respondent

  1. In this matter I have already indicated that I would make such orders as are required to allow the application to proceed and that my reasons for so deciding would be published later.  These are those reasons.

  1. The matter was one which was plagued by misunderstanding and misadventure.  Applications for necessary development permits for a substantial project were made in February of 2002.  A number of referral agencies became involved and referral coordination was called for.  Requests for information were furnished.

  1. A consolidated response to these information requests was provided to the respondent on 14 July 2002.  It emerged that the applicant’s principal, Mr Wong had been involved with a Mr Corthorne, a representative of State Development (an authority concerned with fostering development in Queensland) in respect of the proposal.  On 1 August Mr Wong was informed by Mr Corthorne that a senior planning officer of the Council had advised that public notification should commence.  The advice was accepted and notification began on 3 August.

  1. However the referral agencies were not individually given copies of the information response until August 9.  To compound difficulty it seems that for reasons that were not explained, only one page of the multi-paged document emerged from the facsimile machine at the Department of Main Roads.  It is noteworthy that personnel at that department did nothing to rectify the problem as they could easily have done by contacting the applicant or the Council which, for some time, had been in possession of a complete copy of the response.

  1. It was not until some time later that an officer of the respondent Council realised, pursuant to s 3.4.3(3) of the Act, the notification period should not commence until the response request had been furnished as required.  The relevant date in this case would have been August 9.  I would certainly not be prepared to hold it against the applicant that the Department of Main Roads failed to ensure receipt of the balance of the relevant document when it was well within the capacity of officers of some intelligence and competence to do so.  The position is that the notification period began early (by four business days).

  1. All relevant parties were well aware of this confusion which was the subject of ongoing correspondence.  On 4 November the applicant’s consultant referred to the concerns that had been raised and stated inter alia that “public notification commenced on Saturday 3 August 2002”.

  1. The respondent has expressed concern that, pursuant to s 3.2.12 of the Act the application has lapsed because actions to be taken under IDAS were not taken within the prescribed periods.  Those actions were:

·public notification

·the requirements of s 3.4.7.

The latter provision requires an applicant who carries out notification to give the assessment manager (after the notification period has ended) written notice of compliance.

  1. The respondent further questioned whether, in the circumstances, relief can be afforded to the applicant under s 4.1.5A which provides:

“(1)subsection (2) applies if in a proceeding before the court, the court –

(a)finds a requirement of this Act or another Act in its application to this Act has not been complied with or has not or has not been fully complied with but

(b)is satisfied the non-compliance or partial compliance has not substantially restricted the opportunity for a person to exercise the rights conferred on the person by this Act or the other Act.

(2)the court may deal with the matter in the way the court considers appropriate.”

  1. I believe this is the very kind of case where such relief can and should be given.  The history of the matter indicates that the applicant has at all times done its best to comply with the Act.  The confusion regarding the notification period arose because Mr Wong was ill-informed by persons in whom it was reasonable for him to have confidence.  The non-reception of the complete information response at the Main Roads Department was no fault of his.

  1. As to s 3.4.7 it is noted that all that is required is “written notice”.  No particular form for such notice is specified.  To suggest that the respondent was not made aware of what had occurred in relation to the notification period would, in the circumstances, be fanciful.  I am well satisfied that the correspondence to which reference has been made constituted more than sufficient “written notification” of what had occurred. 

  1. There is no question in this case that relevant non-compliance has not substantially restricted the opportunity for any individual to exercise the rights conferred by the Act.  I believe that the object of s 4.1.5A is to avoid waste of time and assets (both public and private) as a result of what is nothing more than a technical deficiency with no consequences of any substance.  It is for those reasons that I ordered as I did.

Details
AGLC
Lali Investments Pty Ltd v Burnett Shire Council [2003] QPEC 33
Case
[2003] QPEC 33
Decision Date

CaseChat Overview and Summary

Lali Investments Pty Ltd (Lali) sought a development permit from Burnett Shire Council (the Council) for the construction of a large hotel complex. The Council refused the application on the basis that the public notification period had begun prematurely, and Lali had not informed the Council of this fact. Lali appealed to the Queensland Land Court, which was tasked with determining whether Lali's failure to inform the Council constituted a failure to comply with the conditions of the development permit application, and whether this warranted refusal of the application.

The court was required to consider the nature and purpose of the requirement for public notification, and whether the failure to inform the Council constituted a significant breach of the conditions of the development permit application. The court was also required to consider whether Lali's actions constituted substantial compliance with the conditions of the development permit application, and whether this was sufficient for the Council to grant the permit.

The court found that the failure to inform the Council of the premature commencement of the public notification period was not a significant breach of the conditions of the development permit application, and that Lali had substantially complied with the conditions of the application. The court found that the purpose of the requirement for public notification was to allow the public to provide feedback on the proposed development, and that Lali's failure to inform the Council had not prevented the public from providing feedback. The court also found that the Council had not suffered any prejudice as a result of Lali's failure to inform it of the premature commencement of the public notification period. The court therefore found that the Council's refusal of the development permit application was invalid, and ordered the Council to grant the permit.

The court ordered that the Burnett Shire Council grant the development permit application made by Lali Investments Pty Ltd for the construction of a large hotel complex. The court also ordered that Lali pay the costs of the proceeding.

Orders

Orders of the court

-

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.