PLANNING & ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Lali Investments Pty Ltd v Burnett Shire Council [2003] QPEC 033
PARTIES:
LALI INVESTMENTS PTY LTD
Applicant
v
BURNETT SHIRE COUNCIL
RespondentFILE NO:
1536 of 2003
DIVISION:
Planning and Environment Court
PROCEEDING:
Application
ORIGINATING COURT:
Brisbane
DELIVERED ON:
29 July 2003
DELIVERED AT:
Brisbane
HEARING DATE:
30 June 2003
JUDGE:
Quirk DCJ
ORDER:
-
CATCHWORDS:
BUILDING CONTROL AND TOWN PLANNING – town planning – development application – where public notification commenced earlier than required – whether applicant failed to inform council that public notification had commenced – substantial compliance
COUNSEL:
Mr M Hinson SC for the respondent
Mr D Fahl (Solicitor) for the applicantSOLICITORS:
Lester Manning Lawyers for the applicant
Connor O’Meara for the respondent
In this matter I have already indicated that I would make such orders as are required to allow the application to proceed and that my reasons for so deciding would be published later. These are those reasons.
The matter was one which was plagued by misunderstanding and misadventure. Applications for necessary development permits for a substantial project were made in February of 2002. A number of referral agencies became involved and referral coordination was called for. Requests for information were furnished.
A consolidated response to these information requests was provided to the respondent on 14 July 2002. It emerged that the applicant’s principal, Mr Wong had been involved with a Mr Corthorne, a representative of State Development (an authority concerned with fostering development in Queensland) in respect of the proposal. On 1 August Mr Wong was informed by Mr Corthorne that a senior planning officer of the Council had advised that public notification should commence. The advice was accepted and notification began on 3 August.
However the referral agencies were not individually given copies of the information response until August 9. To compound difficulty it seems that for reasons that were not explained, only one page of the multi-paged document emerged from the facsimile machine at the Department of Main Roads. It is noteworthy that personnel at that department did nothing to rectify the problem as they could easily have done by contacting the applicant or the Council which, for some time, had been in possession of a complete copy of the response.
It was not until some time later that an officer of the respondent Council realised, pursuant to s 3.4.3(3) of the Act, the notification period should not commence until the response request had been furnished as required. The relevant date in this case would have been August 9. I would certainly not be prepared to hold it against the applicant that the Department of Main Roads failed to ensure receipt of the balance of the relevant document when it was well within the capacity of officers of some intelligence and competence to do so. The position is that the notification period began early (by four business days).
All relevant parties were well aware of this confusion which was the subject of ongoing correspondence.…
Keep reading for free
Create a free CaseChat account to read Lali Investments Pty Ltd v Burnett Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2003] QPEC 33
- Decision Date
CaseChat Overview and Summary
The court was required to consider the nature and purpose of the requirement for public notification, and whether the failure to inform the Council constituted a significant breach of the conditions of the development permit application. The court was also required to consider whether Lali's actions constituted substantial compliance with the conditions of the development permit application, and whether this was sufficient for the Council to grant the permit.
The court found that the failure to inform the Council of the premature commencement of the public notification period was not a significant breach of the conditions of the development permit application, and that Lali had substantially complied with the conditions of the application. The court found that the purpose of the requirement for public notification was to allow the public to provide feedback on the proposed development, and that Lali's failure to inform the Council had not prevented the public from providing feedback. The court also found that the Council had not suffered any prejudice as a result of Lali's failure to inform it of the premature commencement of the public notification period. The court therefore found that the Council's refusal of the development permit application was invalid, and ordered the Council to grant the permit.
The court ordered that the Burnett Shire Council grant the development permit application made by Lali Investments Pty Ltd for the construction of a large hotel complex. The court also ordered that Lali pay the costs of the proceeding.
Orders
Orders of the court
-
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi