PLANNING & ENVIRONMENT COURT OF QUEENSLAND
CITATION:
Lake Maroona Pty Ltd v Gladstone Regional Council (No 2) [2017] QPEC 30
PARTIES:
LAKE MAROONA PTY LTD
Appellant
v
GLADSTONE REGIONAL COUNCIL
Respondent
FILE NO/S:
4722/16
PROCEEDING:
Appeal
DELIVERED ON:
25 May 2017
DELIVERED AT:
Brisbane
HEARING DATE:
On the papers
JUDGE:
Bowskill QC DCJ
ORDER:
For the reasons given on 10 May 2017, and today, the orders of the court are:
1. The appeal against the Council’s refusal of a request for an extension of the relevant period of the development approval is allowed;
2. The relevant period of the development approval for material change of use (multiple unit residential (28 units)) issued on 26 March 2012 with respect to land at Lot 2 on SP152150 be extended to 26 March 2020; and
3. Each party bear their own costs of the appeal.
CATCHWORDS:
PLANNING AND ENVIRONMENT – Costs
Sustainable Planning Act 2009 (Qld), s 457
Altitude Corporation Pty Ltd v Isaac Regional Council (No 2) [2015] QPELR 139
Cox v Brisbane City Council (No 2) [2014] QPELR 92
Ferreyra v Brisbane City Council (No 2) [2016] QPELR 374
Hydrox Nominees Pty Ltd v Noosa Shire Council (No 2) [2015] QPELR 168
YFG Shopping Centres Pty Ltd v Brisbane City Council (No 2) [2015] QPELR 8
COUNSEL:
K Wylie for the Appellant
M Batty for the Respondent
SOLICITORS:
Project Legal for the Appellant
MRH Lawyers for the Respondent
On 10 May 2017 I delivered my reasons for allowing Lake Maroona Pty Ltd’s appeal against the Council’s refusal of its request for an extension of the relevant period of its development approval: Lake Maroona Pty Ltd v Gladstone Regional Council [2017] QPEC 25.
I invited submissions from the parties both as to the appropriate form of order and as to costs. The parties are agreed as to orders 1 and 2. This decision sets out my reasons for making order 3, in relation to costs.
The power of the court to make an order for costs is conferred by s 457(1) of the Sustainable Planning Act 2009 which provides that:
“Costs of a proceeding or part of a proceeding, including an application in a proceeding, are in the discretion of the court.”[1]
[1]I note that s 457 has now been amended by the Local Government Electoral (Transparency and Accountability in Local Government) and Other Legislation Amendment Act 2017 (Act No. 12 of 2007), which was assented to on 19 May 2017. As amended, subject to a new s 457A (costs in particular circumstances, for example, where proceedings have been commenced for an improper purpose or are considered frivolous or vexatious) and s 457B (costs in particular proceedings, such as enforcement proceedings), s 457 will now provide that each party to a proceeding bear its own costs. This does not affect proceedings which were started before the commencement of the amendment (s 999), in relation to which the existing s 457 will continue to apply.
The discretion is a broad one, to…
Keep reading for free
Create a free CaseChat account to read Lake Maroona Pty Ltd v Gladstone Regional Council (No 2) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] QPEC 30
- Decision Date
CaseChat Overview and Summary
The primary legal issues revolved around the interpretation and application of the statutory framework governing development approvals and the discretion of the Council in granting or refusing extensions. Specifically, the court had to assess whether the Council had acted unreasonably in denying the extension request and whether the appellant had demonstrated sufficient grounds to warrant an extension. The court also considered the nature of the development and the potential impact on the surrounding area.
The court found that the Council had not adequately justified its refusal to extend the approval period, and that the appellant had presented a valid case for an extension. The court held that the refusal was unreasonable and that the appellant had met the necessary criteria to warrant an extension. Consequently, the appeal was allowed, and the approval period was extended to 26 March 2020. The court also ruled that each party should bear their own costs associated with the appeal.
In light of the findings, the court issued orders to allow the appeal against the Council’s refusal of the extension request, extend the relevant period of the development approval, and direct that each party bear their own costs of the appeal.
Orders
Orders of the court
For the reasons given on 10 May 2017, and today, the orders of the court are:
1. The appeal against the Council’s refusal of a request for an extension of the relevant period of the development approval is allowed;
2. The relevant period of the development approval for material change of use (multiple unit residential (28 units)) issued on 26 March 2012 with respect to land at Lot 2 on SP152150 be extended to 26 March 2020; and
3. Each party bear their own costs of the appeal.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi