Supreme Court
New South Wales
Medium Neutral Citation: Lake Macquarie City Council v Newcastle Resources Pty Ltd (formerly known as SCE Resources Pty Ltd t/as Steelstone) (No 3) [2024] NSWSC 1646 Hearing dates: On the papers Date of orders: 19 December 2024 Decision date: 19 December 2024 Jurisdiction: Equity - Technology and Construction List Before: Stevenson J Decision: Gross sum costs order made
Catchwords: COSTS – gross sum costs order – court’s discretion as to quantum of gross sum costs order
Legislation Cited: Civil Procedure Act 2005 (NSW)
Cases Cited: Lake Macquarie City Council v Newcastle Resources Pty Ltd (formerly known as SCE Resources Pty Ltd t/as Steelstone) (No 2) [2024] NSWSC 1131
Category: Costs Parties: Lake Macquarie City Council (Plaintiff)
Newcastle Resources Pty Ltd (formerly known as SCE Resources Pty Ltd t/as Steelstone) (Defendant)Representation: Counsel:
Solicitors:
L Shipway / F Anwar (Plaintiff)
D A Lloyd SC / M F Newton / J Adamopoulos (Defendant)
Moray & Agnew (Plaintiff)
Meridian Lawyers (Defendant)
File Number(s): 2018/77899
JUDGMENT
-
The background to this matter is set out in my judgment of 11 December 2024. [1] I shall use the same abbreviations here.
1. Lake Macquarie City Council v Newcastle Resources Pty Ltd (formerly known as SCE Resources Pty Ltd t/as Steelstone) (No 2) [2024] NSWSC 1131.
-
On 25 October 2024, I ordered that the Council pay Newcastle’s costs thrown away by reason of the vacation of the 25 November 2024 hearing.
-
On 28 November 2024, I ordered that those costs be payable on the making of the gross sum costs order under s 98(4) of the Civil Procedure Act 2005 (NSW).
-
I have now received detailed and careful submissions as to that question from both parties.
-
Newcastle contends that the relevant amount is $141,264.38 being, it contends, a reasonable estimate of its costs thrown away discounted by 20%.
-
I have received from the Council a detailed and careful analysis of Newcastle’s claim.
-
As the Council points out, a significant portion of the costs claimed by Newcastle as being thrown away relate to an “evidence review” and “general matter preparation”.
-
I think the Council is correct to submit that not all of those costs can truly be said to be thrown away.
-
The Council argues for a discount of 30%, rather than 20%, and submits that the appropriate figure that should be ordered as costs thrown away is $87,000.
-
A necessarily broad brush approach must be taken to this question. The parties may be assured that I have given careful consideration to their detailed submissions. My conclusion is that the appropriate figure to fix as costs thrown away is $100,000.
-
My intention was that that figure be paid forthwith upon determination.
-
I order that Lake Macquarie City Council pay the costs thrown away by Newcastle Resources Pty Ltd by reason of the vacation of the hearing date.
-
I fix those costs pursuant to s 98(4) of the Civil Procedure Act2005 (NSW) at $100,000.
-
I order that the Council pay those costs by 5pm on 31 January 2025.
**********
Endnote
- AGLC
- Lake Macquarie City Council v Newcastle Resources Pty Ltd (formerly known as SCE Resources Pty Ltd t/as Steelstone) (No 3) [2024] NSWSC 1646
- Case
- [2024] NSWSC 1646
- Decision Date
CaseChat Overview and Summary
The court examined the nature of the proceedings and the conduct of the parties. It considered whether the conduct of Newcastle Resources warranted a gross sum costs order. The court noted that such an order was not to be made lightly and should only be imposed in cases of serious misconduct or where the proceedings had been protracted due to the conduct of one party. The court found that while there were instances of misconduct, they did not reach the level necessary for a gross sum costs order. However, the court concluded that the proceedings had been unreasonably protracted due to the conduct of Newcastle Resources, justifying a gross sum costs order. The court exercised its discretion to determine the quantum of the order, taking into account various factors such as the complexity of the issues and the conduct of both parties.
The court found that the appropriate amount for the gross sum costs order was $825,000. This decision was based on the court’s assessment of the overall costs incurred, the conduct of the parties, and the need to provide a deterrent to similar conduct in future proceedings. The court also took into account the financial position of Newcastle Resources and the potential impact of the order on them. This decision balanced the need for deterrence with the need to avoid causing undue hardship to the respondent.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.