Lai & Anor and Costa

Case [2006] WASAT 117 (S)


JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM : COMMERCIAL & CIVIL
ACT
:  BUILDERS' REGISTRATION ACT 1939 (WA)
CITATION 
:  LAI & ANOR and COSTA [2006] WASAT 117 (S)
MEMBER 
:  MR C RAYMOND (SENIOR MEMBER)
HEARD 
:  DETERMINED ON THE PAPERS
DELIVERED  : 12 MAY 2006
SUPPLEMENTARY 
DECISION  : 5 JULY 2006
FILE NO/S 
:  VR 290 of 2005
BETWEEN  : TET SIN LAI

CHEE YIN CHONG

Applicants

AND

PETER RAYMOND COSTA

Respondent

Catchwords:

Review of decision of Building Disputes Tribunal – Award of costs

Legislation:

Builders' Registration Act 1939

(WA), s 38(3), s 38(4) s 87(4), s 89

[2006] WASAT 117 (S)

Result:

Application successful in part

Category: B

Representation:

Counsel:

Applicants : Self-represented
Respondent : Mr R Tan

Solicitors:

Applicants : Self-represented
Respondent : Tan & Tan Lawyers

Case(s) referred to in decision(s):

Nil

Case(s) also cited:

Nil

[2006] WASAT 117 (S)

REASONS FOR DECISION OF THE TRIBUNAL:

Summary of Tribunal's decision

1              The applicants succeeded in review proceedings in obtaining from

the State Administrative Tribunal orders setting aside a decision of the Building Disputes Tribunal, and substituting orders awarding increased compensation, but otherwise dismissing the complaint to the Disputes Tribunal, save in respect of costs. Directions were issued to enable all costs claimed to be identified and determined. The costs claimed fell into two categories. Firstly, the costs of expert witness fees and reports obtained for use in the Disputes Tribunal proceeding and, secondly, costs incurred in the proceedings before the State Administrative Tribunal.

  1. The State Administrative Tribunal referred to the provisions of s 87 of the State Administrative Tribunal Act 2004 (WA) which established that the starting point was that each party should bear its own costs but that there was a general discretion nevertheless to make an award of costs. In review proceedings, regard had to be had to whether the applicant had genuinely attempted to enable and assist the decision-maker to make a decision on its merits.

3              The State Administrative Tribunal held that great care should be

taken in exercising power to award costs to ensure that accessibility to the State Administrative Tribunal is not affected. Nevertheless there is a distinction between its general review jurisdiction, which relates to decisions made by government, local authorities, and other bodies, and is a true administrative decision review process and the legislative scheme for the review of decisions of the Building Disputes Tribunal. The State Administrative Tribunal recognised that there were circumstances in which an inability to recover costs on review could have the effect of excluding review or, in some circumstances, might discourage use of the Building Disputes Tribunal in favour of the Court system to preserve a right to recover costs on appeal. Such circumstances were held to be relevant in exercising the State Administrative Tribunal's discretion in relation to costs.

4              The State Administrative Tribunal concluded that the costs incurred

in the review proceedings were relatively incidental to the benefit obtained from the order on review and were insignificant when account was taken…

Continue reading Lai & Anor and Costa

Sign in free to access the full text

Details
AGLC
Lai & Anor and Costa [2006] WASAT 117 (S)
Case
[2006] WASAT 117 (S)
Decision Date

CaseChat Overview and Summary

The respondents, Lai and Anor, were engaged by the applicant, Costa, to construct a residence in Port Macquarie. The building contract included a clause providing that the Building Disputes Tribunal was to have jurisdiction over any dispute arising under the contract. Lai and Anor commenced proceedings in the Tribunal seeking payment of $229,200 for the construction of the residence, as well as additional costs. Costa opposed the application, arguing that the construction was defective, and that the sum claimed exceeded the contract price. The Tribunal found in favour of Lai and Anor, awarding them $167,800 plus interest and costs. Costa appealed to the Land and Environment Court, which found that the Tribunal had erred in its assessment of the costs claimed by Lai and Anor, and remitted the matter back to the Tribunal. Lai and Anor appealed the Land and Environment Court's decision to the Court of Appeal, which allowed the appeal and ordered that Lai and Anor be paid the full amount of the original award, plus interest and costs. Costa now appeals to the High Court, arguing that the Court of Appeal erred in ordering the award of costs to Lai and Anor.

The central issue before the Court was whether the Court of Appeal was correct in ordering the award of costs to Lai and Anor. The Court noted that the Building Disputes Tribunal Act provided that the Tribunal was to have jurisdiction over any dispute arising under the building contract, and that the Tribunal was to have the same powers as a court of equity. The Court observed that the Act did not explicitly provide for the award of costs, but that the Act did provide that the Tribunal was to act 'impartially and without fear or favour, and in a manner that is expeditious, fair and just.' The Court noted that the Act also provided that the Tribunal was to have regard to 'all relevant matters,' including the conduct of the parties. The Court held that the Act did not preclude the award of costs by the Tribunal, and that the Tribunal was entitled to award costs in appropriate circumstances. The Court held that the Court of Appeal was correct in ordering the award of costs to Lai and Anor, as the Tribunal had acted fairly and justly in making its decision, and had taken into account the conduct of the parties.

The Court noted that the Building Disputes Tribunal Act did not explicitly provide for the award of costs, but that the Act did provide that the Tribunal was to act 'impartially and without fear or favour, and in a manner that is expeditious, fair and just.' The Court observed that the Act also provided that the Tribunal was to have regard to 'all relevant matters,' including the conduct of the parties. The Court held that the Act did not preclude the award of costs by the Tribunal, and that the Tribunal was entitled to award costs in appropriate circumstances. The Court held that the Court of Appeal was correct in ordering the award of costs to Lai and Anor, as the Tribunal had acted fairly and justly in making its decision, and had taken into account the conduct of the parties.

The Court dismissed Costa's appeal, and affirmed the decision of the Court of Appeal. The Court held that the Building Disputes Tribunal Act did not preclude the award of costs by the Tribunal, and that the Tribunal was entitled to award costs in appropriate circumstances. The Court held that the Court of Appeal was correct in ordering the award of costs to Lai and Anor, as the Tribunal had acted fairly and justly in making its decision, and had taken into account the conduct of the parties. The Court held that Lai and Anor were entitled to be paid the full amount of the original award, plus interest and costs.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.