KULLEEN Pty Ltd as trustee for the Gismondi Family Trust trading as Italsteel Structural Engineering WA v Rostruct Pty Ltd

Case [2013] WADC 172


KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA -v- ROSTRUCT PTY LTD [2013] WADC 172
Last Update:  12/11/2013
KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA -v- ROSTRUCT PTY LTD [2013] WADC 172
Jurisdiction: DISTRICT COURT OF WESTERN AUSTRALIA   Citation No: [2013] WADC 172
Case No: CIV:896/2012   Heard: 2 SEPTEMBER 2013
Coram: STEVENSON DCJ   Delivered: 08/11/2013
Location: PERTH   Supplementary Decision:
No of Pages: 48   Judgment Part: 1 of 1
Result: Subcontract is a fixed sum contract, not a rates contract
No repudiation of outstanding works by Rostruct
Other claims allowed in part
[Click here for Judgment in Adobe Acrobat Format ]
Parties: KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA
ROSTRUCT PTY LTD

Catchwords: Contract Contract formation Construction Whether fixed sum or rates contract Contractual terms Interpretation of contract terms Breach of contract Alleged repudiation Right to terminate Damages Overpayment
Legislation: Construction Contracts Act 2004 s 13, s 14

Case References: Command Energy Pty Ltd v Nauru Phosphate Royalties Trust [2003] VSC 261
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623



JURISDICTION : DISTRICT COURT OF WESTERN AUSTRALIA

                  IN CIVIL
LOCATION : PERTH CITATION : KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA -v- ROSTRUCT PTY LTD [2013] WADC 172 CORAM : STEVENSON DCJ HEARD : 2 SEPTEMBER 2013 DELIVERED : 8 NOVEMBER 2013 FILE NO/S : CIV 896 of 2012 BETWEEN : KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA
                  Plaintiff

                  AND

                  ROSTRUCT PTY LTD
                  Defendant

Catchwords:

Contract - Contract formation - Construction - Whether fixed sum or rates contract - Contractual terms - Interpretation of contract terms - Breach of contract - Alleged repudiation - Right to terminate - Damages - Overpayment

Legislation:

Construction Contracts Act 2004 s 13, s 14

(Page 2)

Result:

Subcontract is a fixed sum contract, not a rates contract
No repudiation of outstanding works by Rostruct
Other claims allowed in part

Representation:

Counsel:


    Plaintiff : Mr S D Pentony
    Defendant : Mr G J Douglas

Solicitors:

    Plaintiff : Lavan Legal
    Defendant : Hotchkin Hanly Lawyers


Case(s) referred to in judgment(s):

Command Energy Pty Ltd v Nauru Phosphate Royalties Trust [2003] VSC 261
Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623


(Page 3)

      STEVENSON DCJ:



Introduction

1 This action concerns four unresolved disputes between the plaintiff (Italsteel) and the defendant (Rostruct) arising out of a subcontract made in April 2010 for the erection of structural steel at the Bulkyplex Complex in Cannington (the works). The development comprises four buildings known as buildings A, B, C and D (the site). But for these issues, the works are complete.

2 Italsteel fabricates and supplies structural steel. Rostruct is a steel rigger engaged in the business of erecting structural steel.

3 The first dispute…

Continue reading KULLEEN Pty Ltd as trustee for the Gismondi Family Trust tra...

Sign in free to access the full text

Details
AGLC
KULLEEN PTY LTD as trustee for the GISMONDI FAMILY TRUST trading as ITALSTEEL STRUCTURAL ENGINEERING WA -v- ROSTRUCT PTY LTD [2013] WADC 172
Case
[2013] WADC 172
Decision Date

CaseChat Overview and Summary

The case involved Kulleen Pty Ltd, as trustee for the Gismondi Family Trust trading as Italsteel Structural Engineering WA, as the plaintiff, and Rostruct Pty Ltd, as the defendant. The dispute centred around the interpretation and execution of a subcontract under which Italsteel was to provide structural engineering services to Rostruct for a fixed sum. The dispute escalated to claims of repudiation of contract, alleged breaches, and claims for overpayment.

The key legal issues the court had to address were whether the subcontract was a fixed sum contract or a rates contract, the nature of any repudiation by Rostruct, and the validity of claims for damages. The plaintiff argued that the subcontract was a fixed sum contract, and that Rostruct repudiated its obligations. The defendant maintained that the contract was a rates contract and denied any repudiation. Additionally, Rostruct claimed that it had overpaid Italsteel.

The court concluded that the subcontract was indeed a fixed sum contract, not a rates contract, based on the explicit terms of the agreement. The court found that Rostruct had not repudiated its obligations under the contract. However, it was determined that Rostruct was entitled to a set-off for overpayments made to Italsteel. As a result, the court allowed the plaintiff's claims in part, affirming the fixed sum nature of the contract but reducing the damages payable to the plaintiff due to the overpayment set-off.

Orders

Orders of the court

Subcontract is a fixed sum contract, not a rates contract

No repudiation of outstanding works by Rostruct

Other claims allowed in part

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.