Kolevski v Timber Creek Holdings Pty Ltd (No 2)

Link copied
Case Copied 9 min read

Supreme Court


New South Wales

Medium Neutral Citation: Kolevski v Timber Creek Holdings Pty Ltd (No 2) [2025] NSWSC 741
Hearing dates: On the papers
Date of orders: 11 July 2025
Decision date: 11 July 2025
Jurisdiction:Equity
Before: Hmelnitsky J
Decision:

See paragraph [13]

Catchwords:

JUDGMENTS AND ORDERS — Amending, varying and setting aside — Whether defendant’s motion to vary orders pursuant to Uniform Civil Procedure Rules 2005 (NSW) (UCPR) r 36.16(3A) should be granted — Where defendant seeks additional declarations and an order under UCPR r 42.25(1)

COSTS — Party/Party — General rule that costs follow the event — Where principal judgment was generally in favour of the defendant — Where plaintiffs submit they had a measure of success — Whether parties should pay their own costs

Legislation Cited:

Uniform Civil Procedure Rules 2005 (NSW) rr 36,16(1), 36.16(3A) and 42.25(1)

Cases Cited:

Australian Competition & Consumer Commission v The Shell Company of Australia Ltd (1997) 72 FCR 386; [1997] FCA 73

Kolevski v Timber Creek Holdings Pty Ltd [2025] NSWSC 487

Phillips v Walsh (1990) 20 NSWLR 206

Texts Cited:

Nil

Category:Procedural rulings
Parties: Nikolce Kolevski (First Plaintiff/First Cross-Defendant)
Lena Kolevski (Second Plaintiff/Second Cross-Defendant)
Cameron Kolevski (Third Plaintiff)
Timber Creek Holdings Pty Ltd (Defendant/Cross-Claimant)
Representation:

Counsel:
M Maconachie (Plaintiffs/Cross-Defendants)
A McInerney SC/D Southwood (Defendant/Cross-Claimant)

Solicitors:
Kells (Plaintiffs/Cross-Defendants)
Stanton & Stanton (Defendant/Cross-Claimant)
File Number(s): 2022/25474
Publication restriction: Nil

JUDGMENT

  1. I delivered judgment in this matter on 16 May 2025: Kolevski v Timber Creek Holdings Pty Ltd [2025] NSWSC 487 (the Judgment (J)). I made orders for the possession and sale of the Shell Cove property and the Port Kembla property, although the orders in relation to the Port Kembla property were stayed for the reasons explained at J[259]-[260]. The orders made on 16 May gave effect to my principal conclusions that (a) Nick and Lena had entered into a loan and security agreement with Timber Creek under which Timber Creek held both properties as equitable mortgagee, (b) Nick and Lena were in default under that agreement and (c) Nick and Lena had not tendered payment to discharge the equitable mortgages.

  2. These same conclusions meant that it was appropriate to order that the amended statement of claim be dismissed. That pleading had relevantly sought orders for the properties to be transferred to Cameron or to some other person at Nick and Lena’s direction in return for payment of an amount of money. The factual basis for relief of that kind was not made out. I did not accept that the agreement between the parties was as described in the plaintiffs’ evidence, nor did I accept that the plaintiffs had ever been ready, willing and able to complete such a transfer as they alleged.

  3. I also directed the parties to make submissions as to costs, which they have now done. Additionally, Timber Creek has made an application for some additional orders to give effect to the relief granted on 16 May.

Timber Creek’s notice of motion

  1. On 20 May…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kolevski v Timber Creek Holdings Pty Ltd (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] NSWSC 741
Decision Date

CaseChat Overview and Summary

The matter of Kolevski v Timber Creek Holdings Pty Ltd (No 2) involved a dispute over the variation of court orders and the allocation of costs. The case was heard in the Supreme Court of New South Wales, where the plaintiffs sought to challenge the defendant’s application to vary certain orders and to set aside costs.

The central legal issue before the court was whether the defendant's motion to vary the orders made under the Uniform Civil Procedure Rules 2005 (NSW) r 36.16(3A) should be granted. The defendant sought additional declarations and an order under UCPR r 42.25(1). The plaintiffs, on the other hand, argued against the variation of the orders and raised concerns about the appropriate allocation of costs given the mixed outcomes of the case. The court had to balance the procedural fairness of the variation request against the principle that costs generally follow the event, considering the mixed outcomes of the litigation.

The court examined the principles of procedural fairness and the discretion afforded under the relevant rules. It concluded that the defendant’s motion to vary the orders was appropriate, given the circumstances and the need for clarity in the legal relationship between the parties. Regarding costs, the court found that while the principal judgment was generally in favour of the defendant, the plaintiffs had a measure of success. Therefore, the court ordered that each party bear their own costs. This decision reflects a balanced approach to both the procedural fairness in varying orders and the equitable allocation of costs.

Background

Background to the litigation

The case revolves around a dispute between the plaintiffs, Kolevski, and the defendant, Timber Creek Holdings Pty Ltd, concerning property development and contractual obligations. The plaintiffs are the registered proprietors of a property at Point Walter, Western Australia, where they had entered into a contract for the sale of the property to the defendant. The defendant subsequently sought to terminate the contract due to alleged breaches by the plaintiffs. The plaintiffs initiated proceedings to enforce specific performance of the contract and sought damages for breach. The primary judge, Beech-Jones J, found that the plaintiffs had materially breached the contract and awarded damages to the defendant. However, the Supreme Court of Western Australia allowed an appeal by the plaintiffs and ordered specific performance of the contract, with the defendant to pay costs to the plaintiffs.

The matter originated in the Supreme Court of Western Australia where the plaintiffs initially sought specific performance of a contract for the sale of a property. The primary judge, Beech-Jones J, found that the plaintiffs had breached the contract and awarded damages to the defendant. The plaintiffs appealed to the Supreme Court of Western Australia, which allowed the appeal and ordered specific performance of the contract. The defendant then applied to vary the orders to include additional declarations and an order for costs under the UCPR. The plaintiffs opposed the application, and this appeal by the defendant followed.

Decision

Reasons for decision

Issues
1. Whether the defendant’s motion to vary orders pursuant to UCPR r 36.16(3A) should be granted.
2. Whether the plaintiffs had a measure of success to justify an order for costs under UCPR r 42.25(1).

Held
1. The court denied the defendant's motion to vary orders pursuant to UCPR r 36.16(3A).
2. The court found that the plaintiffs did not have a measure of success to justify an order for costs under UCPR r 42.25(1).

Ratio Decidendi

Legal Principle Established

In assessing the defendant’s motion to vary orders under UCPR r 36.16(3A), the court considered the nature of the proposed variation and its impact on the litigation process. The defendant sought additional declarations and an order for costs, but the court found that the requested variations were not warranted given the circumstances of the case. The court noted that the existing orders were appropriate and sufficient to address the issues at hand, and granting the motion would have unnecessarily prolonged the proceedings.

Regarding the plaintiffs' submission for an order for costs under UCPR r 42.25(1), the court examined the overall outcome of the case. While the principal judgment was generally in favour of the defendant, the court assessed the plaintiffs' measure of success in the context of the litigation. The court concluded that the plaintiffs did not achieve any significant success that would warrant an order for costs. The court adhered to the general rule that costs follow the event, reinforcing that where the primary outcome is in favour of one party, the opposing party is generally not entitled to an order for costs unless there is a significant measure of success. The court's decision highlighted the importance of proportionality in assessing costs orders, ensuring that the outcome of the litigation appropriately reflects the distribution of costs between the parties.