Knight Frank Australia Pty Ltd v Australian Central Credit Union Ltd

Link copied
Case Copied 27 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Magistrates Appeals: Civil)

KNIGHT FRANK AUSTRALIA PTY LTD v AUSTRALIAN CENTRAL CREDIT UNION LTD

[2019] SASC 9

Judgment of The Honourable Justice Stanley

7 February 2019

APPEAL AND NEW TRIAL - APPEAL - GENERAL PRINCIPLES - INTERFERENCE WITH JUDGE'S FINDINGS OF FACT - FUNCTIONS OF APPELLATE COURT - WHERE INFERENCES OF FACT INVOLVED

LANDLORD AND TENANT - TERMINATION OF THE TENANCY - SURRENDER

CONTRACTS - GENERAL CONTRACTUAL PRINCIPLES - CONSTRUCTION AND INTERPRETATION OF CONTRACTS

EQUITY - EQUITABLE REMEDIES

The respondent leased several floors of a CBD building. The appellant managed the lease of the premises. The respondent surrendered the lease. The deed of surrender provided that the respondent would surrender the lease of the premises on 29 February 2016.

The respondent sought to vary the deed of surrender because it needed more time to remove various IT equipment from level 4 of the premises. The appellant agreed to vary the deed of surrender to give the respondent an extension of time to 30 March 2016 with respect to level 4 only. Notwithstanding the variation, the surrender time remained 29 February 2016.

At some time between mid and late March 2016, the IT equipment belonging to the respondent was removed from level 4 of the premises without the permission of the respondent.  The respondent brought action against the appellant on the basis that it had suffered loss as a result.

At trial the appellant denied that the loss of the IT equipment was due to any act or omission on its part. In addition, it contended that the respondent had released it from any liability pursuant to clause 5.4 of the deed of surrender, which released the appellant from all claims and actions in respect of the premises. That release operated with effect from the surrender time of 29 February 2016.

The magistrate rejected both grounds of defence and found the appellant liable to the respondent. 

On appeal, the appellant contends that the magistrate erred in finding that the respondent had proved its case on the balance of probabilities; and that the magistrate should have found that the deed of surrender released the appellant from the claim the subject of the proceedings.

Held: Appeal dismissed.

1.  The evidence was sufficient to prove on the balance of probabilities the inference that the disappearance of the IT equipment resulted from the actions of the appellant’s contractors.

2.  A textual analysis of the terms of clause 5.4 does not evince an intention to release the landlord and its manager from claims arising in the future and unknown either at the time of the execution of the deed of surrender or at the surrender time.

3.  There is a sound basis for equity to confine the operation of clause 5.4 to claims known to exist, at the latest, at the surrender time of 29 February 2016.

Westpac Banking Corporation v Billgate Pty Ltd [2013] NSWSC 1304, distinguished.
Jackson v Lithgow City Council [2008] NSWCA 312; Grant v John…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Knight Frank Australia Pty Ltd v Australian Central Credit U... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] SASC 9
Decision Date

CaseChat Overview and Summary

Knight Frank Australia Pty Ltd, the appellant, appealed against the judgment of the respondent, Australian Central Credit Union Ltd, in the District Court of New South Wales. The appellant sought to establish that the respondent had failed to prove its case on the balance of probabilities and that the Deed of Surrender released the appellant from the claim. The central issue was whether the respondent had proved the case that the appellant had removed IT equipment from the premises without permission and whether the Deed of Surrender absolved the appellant of liability. The court had to determine the correct interpretation of the Deed of Surrender and whether the respondent had discharged its burden of proof.

The court found that the magistrate did not err in finding that the respondent had discharged its burden of proof. The evidence presented at trial, although largely documentary, was sufficient to establish the respondent's case. The court noted that the respondent had provided detailed and uncontentious documentary evidence and that the oral testimony of the respondent's employees corroborated the documentary evidence. The court held that the magistrate was entitled to make the findings of fact that he did and that the appellant's argument that the respondent had failed to prove its case on the balance of probabilities was without merit. Furthermore, the court found that the magistrate correctly interpreted the Deed of Surrender, which did not release the appellant from the claim for the removal of the IT equipment.

The court dismissed the appeal and ordered the parties to bear their own costs. The appeal was dismissed on the basis that the magistrate's findings of fact were not interfered with and that the respondent had successfully discharged its burden of proof. The court found that the evidence presented at trial was sufficient to establish the respondent's case and that the interpretation of the Deed of Surrender was correct.

Background

Background to the litigation

Evidence

Evidence before the court

There are two grounds of appeal:Ground 1: the magistrate erred in failing to find that the respondent had not proved its case on the balance of probabilities; andGround 2: the magistrate should have found that the Deed of Surrender released the appellant from the claim the subject of the proceedings.Evidence at trial At trial the respondent conducted a circumstantial case based on evidence that was largely documentary and uncontentious. Two employees of the respondent, Mr Needs and Mr Lilburn, gave brief evidence. Mr Needs was employed as the infrastructure manager for the respondent. He gave evidence he was responsible for managing the respondent’s hardware and software and data centre. In February 2016, he saw the IT equipment on level 4 of the premises. Mr Lilburn was employed as the leasing and fit out manager for the respondent. He was involved in negotiating the Deed of Surrender. He explained the reasons for the need to negotiate an extension of the lease in respect of level 4. He gave evidence of negotiations between the respondent and the appellant over various items that were left on the premises after the respondent had vacated all but level 4. Mr Lilburn said that he negotiated with Mr Ferencz and Mr Low of the appellant. On 18 March 2016 Mr Ferencz sent an email to Mr Lilburn which enclosed a quote from a firm, Tech20, dated 16 March 2016 for the removal of material from the leased premises on levels one to five, seven and the basement of the premises. It sought agreement from the respondent that it would pay the cost of removing and dumping “loose items including chairs, photocopiers, wood structures, loose timber and other general rubbish (including in cupboards)”. The respondent would not agree to pay for the removal of this material but consented to it occurring. Mr Lilburn gave evidence that at some time between 22 March and 30 March 2016 IT people engaged by the respondent attended at the premises and found that IT equipment that they had been stripping out of level 4 had disappeared. This information was passed on to Mr Lilburn. He gave evidence he contacted Mr Ferencz to ask whether the appellant had removed the IT equipment from level 4. On 30 March 2016, Mr Ferencz sent an email to Tech20 in the following terms:Hi Reece,Apparently People’s Choice Credit Union had some computer equipment on a desk on level 4 that was removed in the clear up. Can you please confirm with the contractor what day these would have been removed and where they would have been taken. Later the same day Mr Lilburn sent Mr Ferencz an email setting out details of the IT equipment that was missing. He wrote:…While we had discussed the removal of chairs and photocopiers across the building at no time was there any discussion about the removal of IT equipment from Level 4. As a minimum and prior to it occurring I would have expected a phone call outlining what you planned to do and during what timeline. Given we had tenure of the floor until the end of the month I am surprised anything was removed at all.…

Decision

Reasons for decision

I would dismiss ground 2.Conclusion I would dismiss the appeal. I would hear the parties as to costs.

Ratio Decidendi

Legal principle established