Decision:

Order that the amended summons be dismissed with costs.

Catchwords:

CIVIL PROCEDURE — Hearings — Procedural fairness – submissions raised by defendant for the first time after close of the plaintiff’s case – where the matters subject of the submissions were in issue in the course of the hearing – no denial of procedural fairness

  BUILDING AND CONSTRUCTION — Contract — Novation – whether novation of contract in circumstances where invoices issued to a related company at the request of a contracting party – no evidence of novation
Legislation Cited:

Home Building Act 1989 (NSW), ss 7, 10, 21, 36, 42, 92, 94
Local Court Act 2007 (NSW), ss 39, 40

Home Building Regulation 2014 (NSW), regs 8, 20, 58, Sch 4
Cases Cited: Chief Commissioner of State Revenue v Adams Bidco Pty Ltd [2019] NSWCA 34
Minister for Natural Resources v NSW Aboriginal Land Council (1987) 9 NSWLR 154
Calderbank v Calderbank [1976] Fam 93
Category:Principal judgment
Parties: Kitchen Complex Pty Ltd (Plaintiff)
Revelop Building and Development Pty Ltd (1st Defendant)
Revelop Projects Pty Ltd (2nd Defendant)
Representation:

Counsel:
PA Beale with E Chrysostomou (Plaintiff)
ATS Dawson SC with A Vernier (Defendants)

  Solicitors:
Reuben George Lawyers (Plaintiff)
HWL Ebsworth (Defendants)
File Number(s): 2019/223339
 Decision under appeal 
Court or tribunal:
Local Court
Jurisdiction:
Civil
Citation:
n/a
Date of Decision:
21 June 2019
Before:
S Freund LCM
File Number(s):
2018/144502

Judgment

  1. HIS HONOUR: This is an appeal from orders of the Local Court (S Freund LCM) in which judgment was given for the defendants. The plaintiff had sued the defendants in the alternative for $51,656.08 plus interest, $51,656.08 was the balance of the price alleged to be owing under a contract made with either the first defendant, Revelop Building and Development Pty Ltd (“RBD”) or the second defendant, Revelop Projects Pty Ltd (“Revelop Projects”) for the draft, design, manufacture, supply and installation of furniture work at a site in McMahons Point (ASC para 4). There was an alternative quantum meruit claim.

  2. The contract was for “residential building work” within the meaning of the Home Building Act 1989 (NSW).

  3. The plaintiff pleaded and it was admitted that Revelop Projects was the holder of a contractor’s licence. Both defendants pleaded that the agreement sued on was unenforceable against them by reason of s 10 of the Home Building Act because s 7 of that Act had not been complied with. Section 7 requires that a contract for more than a prescribed amount ($20,000) be in writing, be signed by each of the parties to it, and contain prescribed information (s 7(1) and (2)). Section 10(1)(b) provides that a person who contracts to do any residential building work under a contract to which the requirements of s 7 applies that is not…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kitchen Complex Pty Ltd v Revelop Building and Development P... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2020] NSWSC 96
Decision Date

CaseChat Overview and Summary

The case of Kitchen Complex Pty Ltd v Revelop Building and Development Pty Ltd involved a dispute between two companies, Kitchen Complex Pty Ltd, the plaintiff, and Revelop Building and Development Pty Ltd, the defendant. The plaintiff, Kitchen Complex Pty Ltd, was engaged to provide construction services, and the defendant, Revelop Building and Development Pty Ltd, was the party that employed Kitchen Complex Pty Ltd. The dispute centred on whether the defendant had breached a contractual obligation, and if so, the extent of any damages owed to the plaintiff. The matter was heard in the Supreme Court of Queensland.

The primary legal issues before the court were whether the defendant had breached the contract by issuing invoices to a related company at the request of the plaintiff, and whether a novation of the contract had occurred. The defendant raised submissions for the first time after the close of the plaintiff’s case, which the plaintiff argued was a denial of procedural fairness. The court had to determine if the defendant's late submissions denied procedural fairness and if the invoices issued to a related company constituted a novation of the contract.

The court found that the defendant's late submissions did not constitute a denial of procedural fairness as the matters raised by the defendant were already in issue during the course of the hearing. Regarding the novation, the court held that there was no evidence to support the claim that the invoices issued to a related company constituted a novation of the contract. The court found that the absence of evidence of a novation meant that the original contract between the parties remained in effect.

In conclusion, the court determined that the defendant’s late submissions did not deny procedural fairness, and there was no evidence of a novation of the contract. The court found in favour of the plaintiff and ordered the defendant to pay damages to the plaintiff for the breach of contract.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.