| IN THE SUPREME COURT OF VICTORIA AT MELBOURNE | Not Restricted | |
JUDICIAL REVIEW AND APPEALS LIST
S CI 2011 02926
| RAKESH KUMAR KHANNA and | Appellants |
| SUDHA KHANNA | |
| – and – | |
| NADA KULATHAYENDRAN | |
| Respondent |
---
JUDGE: | MUKHTAR AsJ | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 27 February 2012 | |
DATE OF JUDGMENT: | 15 June 2012 | |
CASE MAY BE CITED AS: | Khanna v Kulathayendran | |
MEDIUM NEUTRAL CITATION: | [2012] VSC 250 | |
---
APPEAL ― Appeal from Tribunal on a question of law ― Domestic building contract ― Builder’s claims for variations and final payment under contract ― Owners’ claim for incomplete or unperformed works under contract ― Owners’ additional claim for damages for overdue completion under separate agreement which modified contract ― Tribunal’s decision based apparently on a quantum meruit basis and credibility findings ― No apparent regard to contractual or statutory provisions ― Appeal allowed
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr C Northrop | Scammell Black Mileo |
| For the Defendant | Mr M T Lapirow | Davies Moloney |
HIS HONOUR:
This appeal from an order of the Victorian Civil and Administrative Tribunal concerns a dispute under a domestic building contract.
The appellants are the owners of land at 8 First Street in Clayton South. They engaged the respondent to build, behind their existing home, a single storey unit to be made available as a rental property. The contract price under the standard form “New Homes Contract” published by the Master Builders Association was $171 200. As the price exceeded $5000 it was a “major domestic building contract “as defined in the Domestic Building Contracts Act. Under the Act a builder must not make a major domestic building contract unless it is in writing, sets out in full all the terms of the contract, and the contract must include the plans and specifications of the work.[1] Such a contract also attracts the provisions of Part 3 of the Act which includes laws about the variation of plans and specifications, progress payments, completion of works, and the entitlement of a builder to demand final payment under the contract.
[1]Section 31
The case in the Tribunal was conducted by “pleadings” in, I think, good form and content. In his points of claim which was all predicated on the written contract (as it had to be), the builder claimed payment for the cost of six variations of $7390 and $17 120 as payment of the Final Claim on Completion of the Works. (I am using terminology in accordance with defined terms in the contract.) That makes a total claim of $24 510. As an indicator to what will unfold in this appeal, the variations were alleged to be unwritten and made in conversations between the builder and the first appellant Mr Khanna (who is the husband of the second appellant). But for the purposes of this appeal there are only three variations that matter, which are small in amount, but as can happen in these cases, they spawn legal disputes and attrition at a cost that exceeds the amount at…
Continue reading Khanna v Kulathayendran
Sign in free to access the full text
- AGLC
- Khanna v Kulathayendran [2012] VSC 250
- Case
- [2012] VSC 250
- Decision Date
CaseChat Overview and Summary
The central legal issue before the court was whether the Tribunal had correctly applied the contractual and statutory provisions in making its decision. The court was required to determine if the Tribunal's decision, which appeared to be based on a quantum meruit basis and credibility findings, had appropriately considered the contractual terms and statutory requirements. The owners argued that the Tribunal had failed to adequately apply the contractual and statutory provisions, leading to an unjust outcome.
The court found that the Tribunal's decision did not appear to take into account the contractual or statutory provisions governing the dispute. The court held that the Tribunal had based its decision on a quantum meruit basis, which was not aligned with the contractual terms. The court emphasised the importance of adhering to the contractual and statutory framework in resolving disputes, particularly in construction contracts. As a result, the court allowed the appeal and remitted the matter back to the Tribunal for reconsideration in light of the contractual and statutory provisions.
The final orders of the court included the allowance of the appeal and the direction that the Tribunal reconsider the matter, ensuring that its decision was based on the contractual and statutory provisions that applied to the dispute. The court's decision underscored the necessity for tribunals to carefully consider the specific terms of contracts and relevant legislation when making decisions in construction disputes.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.