Khan v Filardo Ercan Archtects Pty Ltd (Civil Dispute)
Case
•
[2023] ACAT 35
•19 June 2023
Details
AGLC
Case
Decision Date
Khan v Filardo Ercan Archtects Pty Ltd (Civil Dispute) [2023] ACAT 35
[2023] ACAT 35
19 June 2023
CaseChat Overview and Summary
The applicant, Khan, engaged the respondent, Filardo Ercan Architects Pty Ltd, to design a house. A dispute arose concerning the quality of the design and the timeliness of the services provided. The matter was heard by the Civil and Administrative Tribunal of New South Wales. Khan alleged that Filardo Ercan Architects breached the guarantee of due care and skill, the guarantee of reasonable timeliness, and an implied term of the contract. Khan further argued that the brief provided by him was apt to serve as an implied contractual term and that he was not obliged to pay the invoice issued before the contract was terminated.
The court examined whether the respondent had breached the guarantees under Australian consumer law and the implied term of the contract. It considered the adequacy of the brief provided by Khan and whether it was appropriate to imply a contractual term. The court also assessed whether Khan was required to pay the invoice issued before the contract was terminated.
The court found that Filardo Ercan Architects had breached the guarantee of due care and skill and the guarantee of reasonable timeliness. It determined that the brief provided by Khan was not apt to serve as an implied contractual term. The court held that Khan was obliged to pay the invoice issued before the contract was terminated. The Tribunal ordered Khan to pay the outstanding invoice and interest on that amount.
The Tribunal further ordered that Khan must pay the respondent $6,270 for the unpaid invoice dated 1 April 2022, along with interest on that amount calculated in accordance with the Court Procedures Rules 2006 from 8 April 2022 to 7 February 2023, within 28 days of the date of the decision.
The court examined whether the respondent had breached the guarantees under Australian consumer law and the implied term of the contract. It considered the adequacy of the brief provided by Khan and whether it was appropriate to imply a contractual term. The court also assessed whether Khan was required to pay the invoice issued before the contract was terminated.
The court found that Filardo Ercan Architects had breached the guarantee of due care and skill and the guarantee of reasonable timeliness. It determined that the brief provided by Khan was not apt to serve as an implied contractual term. The court held that Khan was obliged to pay the invoice issued before the contract was terminated. The Tribunal ordered Khan to pay the outstanding invoice and interest on that amount.
The Tribunal further ordered that Khan must pay the respondent $6,270 for the unpaid invoice dated 1 April 2022, along with interest on that amount calculated in accordance with the Court Procedures Rules 2006 from 8 April 2022 to 7 February 2023, within 28 days of the date of the decision.
Details
Key Legal Topics
Areas of Law
-
Contract Law
-
Consumer Law
Legal Concepts
-
Breach of Contract
-
Unconscionable Conduct
-
Implied Terms
-
Compensatory Damages
-
Termination of Contract
Actions
Download as PDF
Download as Word Document
Most Recent Citation
Khan v Filardo Ercan Architects Pty Ltd ACN 647 677 263 (Appeal) [2024] ACAT 22
Cases Citing This Decision
2
Cases Cited
3
Statutory Material Cited
4
Scenic Tours Pty Ltd v Moore
[2018] NSWCA 238
Gail Savage v Rabea Hatem Fairs
[2018] ACTMC 17