Civil and Administrative Tribunal
New South Wales
Medium Neutral Citation: Keogh v Samchris Pty Ltd [2024] NSWCATCD 32 Hearing dates: 22 and 24 August 2023 Date of orders: 08 March 2024 Decision date: 08 March 2024 Jurisdiction: Consumer and Commercial Division Before: L. Wilson, Senior Member Decision: 1. The respondent must, within six months of these orders:
(a) rectify Items 1 – 3, 28, 31, 73 (master bedroom water leak) in accordance with the agreed scope of work plus the additional work set out by the homeowners’ expert at CB1755 to 1757.
(b) rectify Items 4, 5 – 15, 16 – 18, 27, 33 – 68 in accordance with the agreed scope of works at CB1757, CB1758, CB1761, CB1762.
2. The application is otherwise dismissed.
3. Each party must pay their own costs.
4. If either party wishes to apply for a cost order different to Order 3:
(a) they must make that cost application by 29 March 2024.
(b) the other party may respond to that application with written submissions filed and served by 19 April 2024.
(c) Parties may provide cost submissions in reply if they wish, on or before 26 April 2024.
(d) In any cost application or cost submissions, parties must indicate their attitude to the Tribunal deciding the question of costs on the papers (that is, dispensing with a hearing on costs).
(e) in the event any party makes an application pursuant to Order 4(a), Order 3 lapses.
Catchwords: Home building – Reliance on flawed designs or specifications – Clause 40 contract
Home building – s.18F defence
Home building – Major defects – preferred outcome
Home building – Variations paid by homeowners – Homeowners seeking refund – s.48K(3)
Legislation Cited: Home Building Act 1989 (NSW), 3B, 18B, 18E, 18F, 48A, 48K, 48MA
Civil and Administrative Tribunal Rules 2014 (NSW) 38
Cases Cited: Akerman v Harvey Norman Designs and Renovations (Home Building) [2007] NSWCTTT 722
David Cameron Jones t/as Oz Style Homes v Panchal [2018] NSWCATAP 238
Diao v Rawson Homes Pty Ltd [2021] NSWCATAP 273
Jones v Dunkel (1959) 101 CLR 298
Li v MACD Developments Pty Ltd [2015] NSWCATAP 287
Moody v M K Building Services Group Pty Ltd [2022] NSWCATAP 212
Professional Construction Service Pty Ltd v The Owners - SP 92156 [2023] NSWCATAP 323
S Turnell and W Turnell v Atlantic Construction Pty Ltd [2014] NSWCATCD 89
The Owners – Strata Plan No 66375 v King [2018] NSWCA 170
Category: Principal judgment Parties: Steven John Keogh (first applicant)
Jacqueline Mary Keogh (second applicant)
Samchris Pty Ltd (respondent)Representation: Counsel:
Solicitors:
M. Klooster (applicants)
J.R.B Pearson (respondents)
Michael Atkinson & Associates (applicants)
Lawandi Lawyers (respondent)
File Number(s): 2022/00410158 (Previously HB 22/39599) Publication restriction: Nil
REASONS FOR DECISION
-
This is a home building dispute which arises from the home building contract between the parties to renovate the applicants’ residential property in Baulkham Hills. They entered the contract in January 2018 and the building works were completed by about October 2018. This application was lodged…
Keep reading for free
Create a free CaseChat account to read Keogh v Samchris Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NSWCATCD 32
- Decision Date
CaseChat Overview and Summary
The primary legal issues the Commission needed to address were whether the defects identified by Mr. Keogh were indeed due to flaws in the design or specifications provided by Samchris, and if the builder could successfully invoke the s.18F defence. Additionally, the Commission had to consider the impact of variations paid by the homeowner on the claim for a refund under s.48K(3) of the Home Building Act. The Commission was also required to determine the preferred outcome for the rectification of the major defects, as well as the appropriate cost orders for both parties.
In its reasoning, the Commission found that several of the defects identified by Mr. Keogh were indeed due to flaws in the design and specifications provided by Samchris, and thus were the builder’s responsibility to rectify. However, it was also determined that the builder was not liable for all defects, as some arose from the homeowner’s choices and decisions. The Commission held that Samchris was not entitled to rely on the s.18F defence, as they had not taken all reasonable steps to ensure the homeowner was aware of the defects before the issue of the certificate of final inspection. The Commission dismissed the claim for a refund under s.48K(3) as it was found that the homeowner had already received a variation for the works in question. Consequently, the Commission ordered the builder to rectify the specified defects within six months, and dismissed the rest of the application. Each party was ordered to bear their own costs, with a specific timeline provided for any party wishing to apply for a cost order.
Orders
Orders of the court
1. The respondent must, within six months of these orders:
(a) rectify Items 1 – 3, 28, 31, 73 (master bedroom water leak) in accordance with the agreed scope of work plus the additional work set out by the homeowners’ expert at CB1755 to 1757.
(b) rectify Items 4, 5 – 15, 16 – 18, 27, 33 – 68 in accordance with the agreed scope of works at CB1757, CB1758, CB1761, CB1762.
2. The application is otherwise dismissed.
3. Each party must pay their own costs.
4. If either party wishes to apply for a cost order different to Order 3:
(a) they must make that cost application by 29 March 2024.
(b) the other party may respond to that application with written submissions filed and served by 19 April 2024.
(c) Parties may provide cost submissions in reply if they wish, on or before 26 April 2024.
(d) In any cost application or cost submissions, parties must indicate their attitude to the Tribunal deciding the question of costs on the papers (that is, dispensing with a hearing on costs).
(e) in the event any party makes an application pursuant to Order 4(a), Order 3 lapses.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.