Kempsey Shire Council v Tebran Pty Limited (No 2)

Link copied
Case Copied 5 min read

Land and Environment Court


of New South Wales


CITATION: Kempsey Shire Council v Tebran Pty Limited (No 2) [2008] NSWLEC 64
PARTIES:

APPLICANT
Kempsey Shire Council

RESPONDENT
Tebran Pty Limited
FILE NUMBER(S): 40413 of 2007
CORAM: Jagot J
KEY ISSUES: Costs :- civil enforcement proceedings - respondent succeeded on all issues - no circumstance displacing the usual order as to costs - applicant ordered to pay respondent's costs as agreed or assessed.
LEGISLATION CITED: Environmental Planning and Assessment Act 1979
CASES CITED: Kempsey Shire Council v Tebran Pty Limited [2007] NSWLEC 731
DATES OF HEARING: 1 February 2008
EX TEMPORE JUDGMENT DATE: 1 February 2008
LEGAL REPRESENTATIVES:

APPLICANT
Mr G Underwood
SOLICITORS
Cooney Harvey Doney

RESPONDENT
Mr I J Hemmings
SOLICITORS
Thorntons


JUDGMENT:


        THE LAND AND
        ENVIRONMENT COURT
        OF NEW SOUTH WALES

        Jagot J

        1 February 2008

        40413 of 2007

        KEMPSEY SHIRE COUNCIL
        Applicant

        TEBRAN PTY LIMITED
        Respondent

        JUDGMENT

Jagot J:

1 On 8 November 2007 I delivered my principal reasons in the matter of Kempsey Shire Council v Tebran Pty Limited [2007] NSWLEC 731. In those proceedings the Council had sought certain declarations and orders to the effect that Tebran was carrying out development in breach of the applicable environmental planning instrument and, thereby, in breach of s 76A(1) of the Environmental Planning and Assessment Act 1979.

2 However, I accepted the arguments of the respondent that, on the proper construction of the environmental planning instrument, the activities that were admitted to be carried out on the land in fact were permissible without development consent. Accordingly, I made orders as set out in [54] of my principal reasons to the effect that the Class 4 application be dismissed as well as an order that the applicant pay the respondent’s costs as agreed or assessed. I stayed the costs order to give the Council an opportunity to consider whether it wished to be heard in relation to costs (in which event the costs order was set aside).

3 As it turns out the Council did wish to be heard in relation to costs and has come before the Court today arguing that there should be no order for costs of the proceedings. The Council so submits based on a limited set of circumstances. In effect what the Council says is that from about 26 October 2006 to 30 April 2007 or thereabouts, the parties proceeded on a common assumption that development consent was required for the activities (and indeed two development applications were lodged on 15 May 2007). In the event, the Council officer responsible for assessing the development applications recommended refusal of the development applications and thereafter they were withdrawn. A few days after the development applications were withdrawn the Court fixed the proceedings for hearing. The Council says that this is a relevant circumstance to the costs discretion, and also relies on the following two matters. First, according to the Council, the respondent’s points of defence of 15 June 2007 did not disclose the legal argument which…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kempsey Shire Council v Tebran Pty Limited (No 2) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] NSWLEC 64
Decision Date

CaseChat Overview and Summary

The Land and Environment Court of New South Wales was presented with a case involving Kempsey Shire Council, the applicant, and Tebran Pty Limited, the respondent. The Council had sought declarations and orders that Tebran was carrying out development in breach of the applicable environmental planning instrument, which would have constituted a breach of section 76A(1) of the Environmental Planning and Assessment Act 1979. However, the court ruled in favour of Tebran, accepting their argument that the activities carried out on the land were permissible without development consent. Consequently, the Council's Class 4 application was dismissed, and the court ordered the Council to pay Tebran's costs as agreed or assessed, subject to a stay to allow the Council to consider whether it wished to be heard in relation to costs.

The court was required to decide whether any circumstances existed that would displace the usual order as to costs, as requested by the applicant. The applicant argued that the mere fact of the lodgement and subsequent withdrawal of the development applications should not be seen as an admission by the respondent that the Council's legal position was correct. The applicant also contended that the respondent's points of defence did not adequately disclose the legal argument advanced in their written submissions. Furthermore, the applicant argued that there was no substantive cross-examination of any of the deponents during the hearing.

The court considered the written submissions from both parties and heard arguments from them. The court found that the lodgement of the development applications should not be characterized as an admission by the respondent that the Council's legal position was correct, as it was a common practice for respondents to lodge development applications to avoid legal debate. The court also noted that the respondent's points of defence disclosed the matters on which the respondent relied at the hearing, and it was not clear what further information could have been included. Finally, the court acknowledged that some affidavit evidence became redundant and that the deponents were not cross-examined, but this was due to the parties reaching an agreement on the relevant facts, which led to a shorter hearing.

In conclusion, the court determined that none of the circumstances to which the Council had referred should displace the ordinary principle that the respondent is entitled to be compensated in relation to the proceedings. Therefore, the court made an order that the applicant is to pay the respondent's costs of the proceedings (including the costs of the hearing on 1 February 2008), as agreed or assessed.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established