Kay and Ors v Wingecarribee Council

Link copied
Case Copied 7 min read

Land and Environment Court


of New South Wales


CITATION: Kay and Ors v Wingecarribee Council [2007] NSWLEC 50
PARTIES:

APPLICANT
Arthur Geoffrey Kay, Lesley S. Kay and Gordon Kay

RESPONDENT
Wingecarribee Council
FILE NUMBER(S): 10551 of 2006
CORAM: Hussey C
KEY ISSUES: Appeal :- Section 121B Order - Cease unauthorised quarrying activities and rehabilitate area
LEGISLATION CITED: Environmental Planning and Assessment Act 1979
CASES CITED: Cassanitti v Canada Bay Council [2002] 123 LGERA 53;
Stuchbury v Pittwater Council [1999] NSWLEC 177
DATES OF HEARING: 04/10/2006
 
DATE OF JUDGMENT: 

8 February 2007
LEGAL REPRESENTATIVES:

APPLICANT
Mr M. Baird, barrister

RESPONDENT
Mr B. Bilinsky, solicitor
of B. Bilinsky and Co.



JUDGMENT:

      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      Hussey C

      Date : 9 February 2007

      10551 of 2006 Arthur Geoffrey Kay, Lesley S. Kay and Gordon Kay v Wingecarribee Council

      JUDGMENT

      Background.

1 This appeal was lodged against a Section 121B Order to cease all quarrying activities and rehabilitate an excavated area on a rural property situated at Lot 40 Inveray Road, Sutton Forest. The property is described as Lot 40 in DP 751284 and has an area of approximately 65 ha.

2 The property is zoned 1(a) (Rural “A”) under the Wingecarribee Local Environmental Plan.

3 The proceedings commenced with a view and the parties agreed that the matter be determined by way of an on-site hearing (OSH). Following the view and hearing of preliminary submissions, I gave my initial findings that the existing scope and presentation of the material excavation and transport operations on the site were extensive and could be classified as "quarrying/extractive industry", which apparently would require development consent. No development consent has been issued for this type of activity on the subject site.

4 Following this, the applicant gave an undertaking to cease all quarrying activities and transportation of extracted material off-site.

5 However, Mr Baird’s submissions raised some detailed questions about the validity of the Order and accordingly the matter was adjourned to allow the respondent to reply. This resulted in the submission of detailed written submissions.


      The Order.

6 The s 121B Order No. 1 was issued on 23 May 2006 and relevantly included the following provisions:


          The Council of the Shire of Wingecarribee (the ”Council”) hereby orders you to cease all quarrying activities and rehabilitate the quarried area in accordance with a rehabilitation plan approved by council on your property at Lot 40 DP751284 Inveray Road, Sutton Forest (the “Property”), within the time specified.

          Pursuant to Section 121L of the Environmental Planning and Assessment Act 1979 , you are advised that the reasons for the giving of the above Order are as follows:
      • No approval has been granted for quarrying operations under the provisions of the Environmental Planning and Assessment Act, 1979.
      Submissions.

7 In the first instance, Mr…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Kay and Ors v Wingecarribee Council and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2007] NSWLEC 50
Decision Date

CaseChat Overview and Summary

The appeal in this case was brought by Arthur Geoffrey Kay, Lesley S. Kay and Gordon Kay against the Wingecarribee Council. The dispute related to a Section 121B Order made by the Council to cease all quarrying activities and rehabilitate an excavated area on a rural property located at Lot 40 Inveray Road, Sutton Forest. The property is zoned as Rural “A” under the Wingecarribee Local Environmental Plan and is approximately 65 hectares in size. The applicants were ordered to cease all quarrying activities and rehabilitate the quarried area in accordance with a rehabilitation plan approved by the Council. The applicants appealed against the Order, contending that the excavation works were for a farm dam and, therefore, did not require development consent.

The primary legal issues the court had to decide were whether the Order was valid and if the applicants' activities on the property constituted quarrying, requiring development consent. The applicants argued that the excavation works were for a farm dam, and thus not subject to the requirement for development consent. The court, however, disagreed, finding that the scale of the excavation did not present as a farm dam and was, in fact, consistent with quarrying activities. The court also considered whether the Order was valid, specifically if it provided adequate reasons for its issuance. The court noted that the Order should make intelligible the basis for the decision to issue the order, so that affected persons have sufficient information to decide whether to accept the order or appeal it.

The court found that the Order was valid and appropriate, given the scale of the unauthorised excavation and the potential environmental damage. The court noted that the applicants had undertaken extensive excavation and transport operations that could be classified as quarrying, which apparently required development consent. The court considered that rehabilitation of the excavated area was necessary to prevent environmental damage and ordered the applicants to submit a rehabilitation plan within three months, including an appropriate timeframe to complete the works and a landscape provision and maintenance program. The court allowed the appeal in part, modifying the original Order to clarify the requirements for the rehabilitation works.

In summary, the Land and Environment Court upheld the validity of the Section 121B Order issued by the Wingecarribee Council. The court found that the applicants' activities on the property constituted quarrying, requiring development consent, and that the Order was valid and appropriate. The court modified the original Order, requiring the applicants to submit a rehabilitation plan within three months, including an appropriate timeframe to complete the works and a landscape provision and maintenance program. The court emphasised the importance of providing adequate reasons for the issuance of an order, ensuring affected persons have sufficient information to decide whether to accept the order or appeal it.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.