SUPREME COURT OF SOUTH AUSTRALIA
(Full Court: Civil)
KARALIS & ANOR v ARCHONSTRUCT PTY LTD & ORS
[2008] SASC 368
Judgment of The Full Court
(The Honourable Justice White, The Honourable Justice Layton and The Honourable Justice Kourakis)
23 December 2008
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS
The appellants engaged the second respondent to act as their architect for the purposes of building a new home - the appellants then contracted with the first respondent, a construction company, on a 'cost plus' basis for the building of that home - the third respondent was the principal of both the first and second respondents - the house was designed and built in accordance with the instructions of the appellants - the first respondent submitted monthly progress claims for the cost of building work and its remuneration - the appellants failed to pay the last four of those progress claims - the first respondent brought proceedings against the appellant for the amount outstanding on those claims - the appellants disputed the amount claimed and pleaded that the first respondent was not entitled to any payment because the progress claims had not been certified by an architect in accordance with the terms of a contractual document signed by them - in the alternative the appellants claimed that the cost plus contract was an unconscionable bargain and that they were induced to make the contract by false and misleading conduct - the appellants further claimed that the second respondent owed a duty to provide a reliable estimate of the costs of building and that it had failed to do so - the appellants alleged at trial that the second respondent had falsely represented that the house could be constructed for $270,000 - the appellants also claimed damages for certain building defects - the appellants appealed against the final orders of the Judge that reflect findings made in three separate judgments - the primary finding was that the first respondent was entitled to $242,828.00 for work performed under the building contract, but that the appellants were entitled to set off against that amount the cost of remediating the building defects which amount was to be agreed by the parties if possible - the Judge held that the appellants were entitled to offset an amount of $8,000 for disturbance and $20,000 for diminution in value - the second respondent's claim for fees was allowed - the Judge otherwise dismissed the claims made by the appellants against the first and second respondents - the Judge then further made an award of interest in favour of the first respondent and the Judge ordered that the appellants pay the costs of the second respondent and two thirds of the first respondent's costs - the Judge then made further orders with respect to the cost of remediating the building defects because the parties had failed to reach an agreement.
Whether it was a term of the second respondent's…
Continue reading Karalis v Archonstruct Pty Ltd
Sign in free to access the full text
- AGLC
- Karalis v Archonstruct Pty Ltd [2008] SASC 368
- Case
- [2008] SASC 368
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether Mr Carn's contractual engagement included a term to design a house that could be built for $270,000, whether Mr Carn was retained to perform the functions of an architect under the cost-plus contract, and whether Archonstruct's entitlement to payment was dependent on Mr Carn's certification of the amounts claimed. The court held that there was no such term in Mr Carn's contractual engagement, that he was not retained to perform the functions of an architect under the cost-plus contract, and that Archonstruct's entitlement to payment was not dependent on Mr Carn's certification. The court also found that Mr Carn did not breach any contractual or professional duty owed to the appellants, that the appellants did not contract with Archonstruct due to misleading conduct by Mr Carn or any other party, and that the contract was not unconscionable. The court dismissed the appellants' appeal on these grounds.
The court's reasoning was based on the contractual terms, the roles and duties of the parties, and the evidence presented. The court found that Mr Carn's advice and explanations regarding building contractual arrangements were not misleading and were adequate. The court concluded that the appellants' obligations under the cost-plus contract were not dependent on a determination made by Mr Carn, and therefore, the contract was not unconscionable. The court found that Mr Carn did not owe a duty to supervise the construction work or administer the contractual arrangements with Archonstruct, and that no tortious duty arose to supervise the building work in light of the appellants' decision not to pay for that part of the architectural service. The court also found that Mr Carn did not breach any of his duties to the appellants. The court held that the appellants were not entitled to set aside the contractual arrangement for unconscionability or misleading conduct.
The final orders of the court included an award of $242,828 to Archonstruct, with the appellants entitled to set off the cost of remediating building defects, an amount of $8,000 for disturbance, and $20,000 for diminution in value. The court allowed Mr Carn's claim for fees and dismissed the appellants' claims against Archonstruct and Mr Carn. The court awarded interest in favour of Archonstruct and ordered the appellants to pay the costs of Mr Carn and two-thirds of Archonstruct's costs. The court also assessed the cost of remediating the building defects and made final orders.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.