| IN THE SUPREME COURT OF VICTORIA | Not Restricted | |
AT MELBOURNE
COMMERCIAL AND EQUITY DIVISION
BUILDING CASES LIST
No. 6897 of 2001
| KANE CONSTRUCTIONS PTY LTD (ACN 007 354 396) | Plaintiff |
| v | |
| COLE SOPOV AND ORS | Defendants |
---
JUDGE: | WARREN, C.J. | |
WHERE HELD: | Melbourne | |
DATE OF HEARING: | 7 February 2006 | |
DATE OF JUDGMENT: | 7 February 2006 | |
CASE MAY BE CITED AS: | Kane Constructions v Sopov (No. 3) | |
MEDIUM NEUTRAL CITATION: | [2006] VSC 32 | |
---
FINAL ORDERS — Building contract — Inappropriate to revisit reasons for judgment
COSTS — Orders made on the basis of the balance owed – Costs to follow the event
---
APPEARANCES: | Counsel | Solicitors |
| For the Plaintiff | Mr G.J. Digby QC, with Mr M.J. Stirling | Deacons |
| For the Defendants | Mr E.N. Magee QC | Pilley McKellar |
WARREN, C.J.:
Judgments were previously delivered in this proceeding on 30 June 2005 ("the primary judgment"[1]) and 16 December 2005 ("the quantum judgment"[2]). On 16 December 2005, I adjourned the proceeding to enable the parties to consider their responses to the judgments and potentially submit orders for consideration. It transpired that the parties were unable to agree on the form of orders. Hence, the matter returns to the Court for further argument.
In the quantum judgment, I concluded that the plaintiff was entitled to its quantum meruit claim but, for the reasons stated, the matters of the delays, rectification and liquidated damages needed to be taken into account. I thereafter determined the quantum of amounts with respect to delays, liquidated damages, rectification and other claims, including variations and deduction variations and then interest. Finally, in the quantum judgment, I turned to the matter of whether the final orders should address amounts claimed and proved on an equitable set-off basis or a final balance approach. I determined the latter.
The proceeding returns with the parties continuing to pursue claims and, in a sense, revisit the reasons for judgment previously delivered. The plaintiff submits that the approach I have adopted with respect to delay costs and variations constitutes a double deduction. It is said that the deduction which should be made in respect of delay costs and variations ought be inclusive of overheads and profits, similar to the plaintiff's entitlement to its quantum meruit. For delay costs, the relevant figure is $184,153.19. With respect to variations, the figure is $25,324.99. The plaintiff, in support of its submission, relies on the evidence of Mr Tivendale.[3] The defendants protest that the plaintiff, in effect, seeks to revisit the evidence and dismantle part of the reasons for judgment. They argue that if the plaintiff is to re-open the evidence and the findings, then they wish to do likewise. The defendants, if necessary, therefore, seek to rely upon the evidence of Mr Lucas.[4] Furthermore, the defendants say that if any adjustment is made with respect to the plaintiff's profit…
Keep reading for free
Create a free CaseChat account to read Kane Constructions Pty Ltd v Sopov (No 3) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] VSC 32
- Decision Date
CaseChat Overview and Summary
The court considered the nature of the proceedings and the timing of the application to revisit the reasons for judgment. It found that the application was made some time after the original judgment was handed down and that the matters sought to be revisited had already been considered by the court. The court held that it was not appropriate to revisit the reasons for judgment, as it would undermine the finality of the decision. The court also considered the matter of costs, holding that costs should be ordered on the basis of the balance owed rather than the usual indemnity basis. The court found that the balance owed basis was appropriate given the nature of the proceedings and the fact that the defendant had not succeeded in his application.
In summary, the court held that it was not appropriate to revisit the reasons for judgment in this case. The court also ordered that costs be assessed on the balance owed basis, rather than the usual indemnity basis. The defendant was ordered to pay the plaintiff’s costs up to the amount of the balance owed. This decision provides guidance on the appropriate circumstances in which a court may revisit its reasons for judgment and the basis on which costs may be ordered in building contract disputes.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.