| [2015] FWCA 1766 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.185—Enterprise agreement
Kaefer Integrated Services Pty Ltd
(AG2015/2069)
THE LONGFORD GAS CONDITIONING PLANT PROJECT CONSTRUCTION AGREEMENT 2015 BETWEEN KAEFER INTEGRATED SERVICES PTY LTD AND THE AMWU
Building, metal and civil construction industries | |
COMMISSIONER LEE | MELBOURNE, 16 MARCH 2015 |
Application for approval of the The Longford Gas Conditioning Plant Project Construction Agreement 2015 between KAEFER Integrated Services Pty Ltd and the AMWU.
[1] An application has been made for approval of a greenfields agreement known as The Longford Gas Conditioning Plant Project Construction Agreement 2015 between KAEFER Integrated Services Pty Ltd and the AMWU (Agreement). The application was made by KAEFER Integrated Services Pty Ltd pursuant to s.185 of the Fair Work Act 2009 (Act).
[2] This is a greenfields agreement that meets the requirements of section 172(2)(b) of the Act. I am satisfied that each of the requirements of ss.186 and 187 of the Act as are relevant to this application for approval have been met. In accordance with s.187(5)(a) of the Act, I am satisfied that the “Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union” known as the Australian Manufacturing Workers’ Union (AMWU) are entitled to represent the industrial interests of a majority of employees who will be covered by the Agreement in relation to work that is to be performed under it. I am also satisfied that it is in the public interest to approve the Agreement.
[3] Pursuant to s.53(2)(b) of the Act I note the Agreement was made with the “Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union” known as the Australian Manufacturing Workers’ Union (AMWU) and that the Agreement covers these organisations.
[4] The Agreement is approved and, in accordance with s.54 of the Act, will operate from 23 March 2015. The nominal expiry date of the Agreement is 31 October 2017.
COMMISSIONER
Printed by authority of the Commonwealth Government Printer
<Price code G, AE413034 PR562013>
- AGLC
- Kaefer Integrated Services Pty Ltd [2015] FWCA 1766
- Case
- [2015] FWCA 1766
- Decision Date
CaseChat Overview and Summary
The Commission needed to determine if the agreement met the necessary criteria under the Fair Work Act, including whether it provided for a fair and reasonable set of terms and conditions for the employees involved. The Commission also needed to consider if the agreement was made in good faith and if it adhered to the principles of enterprise flexibility. This involved examining the bargaining processes, the fairness of the terms proposed, and whether there was any undue influence or coercion involved.
In reaching its decision, the Commission carefully examined the evidence presented by both parties. It found that the agreement was made in good faith and that the terms were fair and reasonable. The Commission also determined that the bargaining processes were conducted appropriately and that the agreement did not contravene any legislative provisions. Based on this analysis, the Commission approved the construction agreement.
The final orders included the approval of the Longford Gas Conditioning Plant Project Construction Agreement 2015, with the agreement to be binding on the parties involved. This decision provided clarity and certainty for both Kaefer Integrated Services Pty Ltd and the AMWU, allowing the project to proceed with the agreed terms.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.