| CITATION: | JW & MM Haylock Pty Ltd v Bakker & Kramer [2014] QCAT 120 |
| PARTIES: | JW & MM Haylock Pty Ltd (Applicant) |
| V | |
| Mr Jan Bakker and Ms Anna Kramer (Respondent) |
| APPLICATION NUMBER: | BDL266-11 |
| MATTER TYPE: | Building matters |
| HEARING DATE: | 28 January 2014 |
| HEARD AT: | Brisbane |
| DECISION OF: | Member Allen |
| DELIVERED ON: | 4 April 2014 |
| DELIVERED AT: | Brisbane |
| ORDERS MADE: | 1. Mr Bakker and Ms Kramer are ordered to pay to JW & MM Haylock Pty Ltd the amount of $5,149.75 within 14 days of today. |
| CATCHWORDS: | BUILDING DISPUTE – swimming pool - wrongful termination of contract – whether subject to Anshun Estoppel - calculation of damages Queensland Building and Construction Commission Act 1991 (Qld) s 77 Ms Anna Kramer and Anor v JW & MM Haylock Pty Ltd [2011] QCAT 296 |
APPEARANCES and REPRESENTATION (if any):
| APPLICANT: | Mr Wayne Haylock, director appeared for JW & MM Haylock Pty Ltd |
| RESPONDENT: | Mr Bakker and Ms Kramer were self-represented |
REASONS FOR DECISION
Introduction
JW & MM Haylock Pty Ltd trades as Burleigh Pools as a pool builder and was engaged by Mr Bakker and Ms Kramer to build a pool on their land at 10 Barton Street, Reedy Creek for the amount of $24,890.00 under a contract dated 1 September 2007[1]. Mr Bakker and Ms Kramer terminated the contract when the pool shell was completed due to their belief that it was at an incorrect height. They made application to the Tribunal claiming that Burleigh Pools failed to carry out the works in an appropriate and skilful way and sought damages in the amount of $21,400.05 for the money paid to Burleigh Pools of $17,421.00 and the amount of $3,983.05 paid to have the pool removed. That application[2] was dismissed on the ground that Mr Bakker and Ms Kramer were not entitled to terminate the contract.
[1]Exhibit 7.
Burleigh Pools made this application seeking damages due to Mr Bakker and Ms Kramer not being entitled to terminate the contract. The claim was for:-
a) Excavation
Cancellation of excavation due to
owners not showing up
(incl. GST plus 20%) $1,161.00
Extra rock excavation as invoiced
(incl. GST plus 20%) 6,597.00
Less contract allowance 2,000.00
$5,758.00
Interest from 14/11/07 to 10/08/12 6,388.00
Sub-Total $12,146.00
b) Loss of profit due to cancellation
of contract 1,489.00 Interest from 23/11/07 to 10/08/12 1,628.00
Sub-total $ 3,117.00
c)Filing costs $ 250.00
Total $15,513.00
ANSHUN ESTOPPEL
Mr Bakker and Ms Kramer have raised the question of whether an Anshun Estoppel[3] applies in relation to the application made by Burleigh Pools on the basis that the claim for damages should have been made at the time of the first application to the Tribunal. The Tribunal notes that Burleigh Pools was the respondent in that application and the decision was made in their favour.…
Keep reading for free
Create a free CaseChat account to read JW & Mm Haylock Pty Ltd v Bakker & Kramer and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] QCAT 120
- Decision Date
CaseChat Overview and Summary
The primary legal issues in the case were whether Anshun Estoppel applied to prevent Burleigh Pools from claiming damages after the initial application was dismissed, and the calculation of the damages Burleigh Pools was entitled to. The Tribunal considered whether the doctrine of Anshun Estoppel prevented Burleigh Pools from claiming damages after the dismissal of the respondents' application, and concluded that it did not. The Tribunal also examined the invoices provided by Burleigh Pools and accepted the sub-contractor invoices supporting the claimed amounts. The Tribunal found that the respondents were liable for the costs incurred due to their failure to attend the site or have an authorized agent sign the mark out form. The Tribunal calculated the damages due to Burleigh Pools, considering the costs to date, loss of profit, and interest. The Tribunal found that the total damages owed to Burleigh Pools were $5,149.75.
The Tribunal ordered Mr Bakker and Ms Kramer to pay Burleigh Pools the amount of $5,149.75 within 14 days of the decision. The Tribunal's decision provides guidance on the application of Anshun Estoppel and the calculation of damages in building disputes under Queensland law.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.