QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Jones v McDonald & Anor Pty Ltd [2022] QCAT 219
PARTIES:
GRAEME JONES
(applicant)
V
JOEL MCDONALD
(respondent)
APPLICATION NO/S:
BDL158-20
MATTER TYPE:
Building matters
DELIVERED ON:
14 June 2022
HEARD AT:
Brisbane
DECISION OF:
Member Lember
ORDERS:
1. The respondent’s name is amended to “Joel McDonald”.
2. Within 28 days of the date of this order Joel McDonald must pay Graeme Jones the sum of $16,667.77.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – GENERALLY – where contract for a water feature – where builder sought variation for tiling costs – where applicant terminated contract – where works completed by a third party – whether applicant is entitled to payment of costs to complete building contract over the contract value – whether director of building company has personal liability to applicant
Queensland Building and Construction Commission Act 1991 (Qld), s 42, s 77, Schedule 1B, Schedule 2
Queensland Building and Construction Commission Regulation 2018 (Qld), s 54
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 3Braund v Sandrey and Marant Holdings Pty Ltd t/as SMS Projects [2021] QCAT 440
Robinson v Harman (1848) 1 Ex 850
Yongwoo Park v Betaland Pty Ltd [2017] QCAT 228APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
REASONS FOR DECISION
What is this application about?
The applicant homeowner, Mr Jones, engaged the respondent builder, Mr McDonald to convert an existing pond to a “high end” water feature under the terms of a Queensland Building and Construction Commission (“QBCC”) Level 2 Renovation, Extension and Repair contract dated 24 September 2019 (the “contract”).
According to the contract, the anticipated completion date for the works was 6 December 2019. However, by that date, the works were far from complete, the parties were in dispute over a variation relating to tiles and Mr Jones says the to-date works were defective.
Accordingly, Mr Jones:
(a)issued a breach notice on 3 December 2019;
(b)terminated the contract for failure to remedy the breach notice on 18 December 2019; and
(c)engaged another contractor to complete the works, which were done by 2 July 2020.
By an application for a domestic building dispute filed 3 July 2020, Mr Jones sought orders that the respondent pay him $16,320.97 being his costs incurred to rectify defective building work and to complete the building work over and above the original contract price, together with $345.80 being his filing fee paid on the application.
Mr McDonald filed a response on 3 August 2020 seeking dismissal of the claim on the grounds that the contract was wrongfully terminated, that he was refused entry to the site to complete works and that Mr Jones’ subsequent building costs incurred were “self-inflicted” due to Mr Jones unreasonably refusing to work with Mr McDonald, and by attempting to change the scope of the works.
Mr McDonald did not otherwise engage in…
Keep reading for free
Create a free CaseChat account to read Jones v McDonald & Anor Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QCAT 219
- Decision Date