Land and Environment Court
of New South Wales
CITATION: JMS Capital Pty Limited v Tweed Shire Council [2006] NSWLEC 535 PARTIES: APPLICANT:
RESPONDENT:
JMS Capital Pty Limited
ACN 108 749 355
Tweed Shire CouncilFILE NUMBER(S): 10156 of 2006 CORAM: Lloyd J KEY ISSUES: Development Consent :- lapse of consent – physical commencement – engineering work – does survey work constitute physical commencement?
LEGISLATION CITED: Environmental Planning and Assessment Act 1979 (NSW) s 99 (as at 22 December 1988) cf s 95 (as currently in force) CASES CITED: Drummoyne Municipal Council v Lebnan (1974) 131 CLR 350;
Hunter Development & Brokerage Pty Ltd v Cessnock City Council (2005) 63 NSWLR 124;
United Dominions Corporation Ltd v Woollahra Municipal Council [1973] 1 NSWLR 616DATES OF HEARING: 07/08/2006
DATE OF JUDGMENT:
08/29/2006LEGAL REPRESENTATIVES: APPLICANT:
T F Robertson SC
SOLICITORS:
Woolf AssociatesRESPONDENT:
P J McEwen SC
SOLICITORS:
Stacks Northern Rivers
JUDGMENT:
IN THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH WALES
Lloyd J
Tuesday, 29 August 2006
LEC No. 10156 of 2006
JUDGMENTJMS CAPITAL PTY LIMITED v TWEED SHIRE COUNCIL [2006] NSWLEC 535
Background
1 HIS HONOUR: On 22 December 1988 Tweed Shire Council granted development consent for a tourist resort on two adjoining parcels of land at Wooyung. The development involved the creation of an artificial lake, a nine-hole golf course, accommodation units, tennis courts, and other facilities. Parts of the site were set-aside as conservation areas.
2 The consent was granted subject to 30 conditions, including a condition specifying the surface dimensions, boundaries and the maximum depth of the proposed lake (condition 10); and a condition requiring consolidation of the separate parcels of land into one lot and under one title (condition 29).
3 On 8 December 2005 the applicant made an application to modify the consent to enable the development to be carried out in two substages. The stated intention of the modification is to enable the substantial earthworks to be carried out as a first stage prior to construction of buildings, car parking, infrastructure and other ancillary components.
4 On 28 February 2006 the applicant appealed to the Court against the failure of the council to determine the application. On 22 March 2006 the council resolved to defend the appeal on the ground that the consent has lapsed.
5 The following questions have now been referred to me for separate determination:
(1) Whether in the circumstances the purported survey work carried out at the subject land constitutes “ physical commencement ”?
(2) Whether in the circumstances the Court can grant consent to the application for modification of the consent?
The relevant legislation
6 The position is governed by s 99 of the Environmental Planning and Assessment Act 1979 (NSW) (“the EP&A Act”) as it was when the consent was granted on 22 December 1988. (That section has since been substantially re-enacted as s 95). That section relevantly stated that a development consent shall lapse unless the development the…
Keep reading for free
Create a free CaseChat account to read JMS Capital Pty Ltd v Tweed Shire Council and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2006] NSWLEC 535
- Decision Date
CaseChat Overview and Summary
The central legal issues were centered on the interpretation of "physical commencement" under the Environmental Planning and Assessment Act 1979 (NSW) and whether the survey work conducted by JMS Capital Pty Limited in January and February 1989 constituted such commencement. The court was required to determine whether the survey work done post-consent grant related to the approved development and if it was physically commenced on the land to which the consent applied.
Lloyd J examined the evidence presented, focusing on the survey work carried out by Mr. A P Hart, a registered surveyor. The court acknowledged that the survey work done after the consent grant, although largely replicating previous work, was necessary to enable compliance with specific conditions of the consent and to facilitate the approved development. The court held that the survey work constituted "building, engineering or construction work" and was necessary for the implementation of the approved development. Furthermore, Lloyd J concluded that the survey work carried out in January and February 1989 was extensive, replicating much of what had been done before but was necessary in order to implement the consent and comply with certain conditions. Therefore, the court found that the survey work constituted physical commencement of the approved development.
Based on the reasoning above, Lloyd J answered the two questions posed as follows: (1) the purported survey work carried out at the subject land constituted physical commencement, and (2) the court could grant consent to the application for modification of the consent.